As part of the Summer 2023 Parking Lot Renewal project, the three parking lots surrounding Reser Stadium will be closed in phases, starting on Wednesday, July 19 and ending Saturday, July 22. The project will be completed in four phases, with each closure lasting one day. See schedule and map below.

Wednesday, July 19 – Valley Football Center Lot (NW section between SW 30th St. and SW Ralph Miller Lane)

Thursday, July 20 – Reser Stadium Lot (south section bordering SW Western Blvd.)

Friday, July 21 – LaSells Stewart West Lot (section SE of the stadium between SW Western Blvd. and SW 26th St.)

Saturday, July 22 – Valley Football Center Lot (west section in front of Samaritan Athletic Medicine Center)

The map shows closures of the three parking lots surrounding Reser Stadium on the west and south-east sides.

Other possible impacts include noise, dust and mud near the construction site.

For questions or comments on this closure, contact Kristie Liddle at (541) 737-9618.

As part of the LaSells Stewart Center Mechanical & Roof Renewal Project, a section of SW Stadium Ave. located directly behind The LaSells Stewart Center and just south of Bloss Hall will be closed to allow for crane activity on Tuesday, July 18 from 7 A.M. to 2 P.M. The B2 parking lot east of The LaSells Stewart Center will also be closed. The entrance to SW Stadium Ave. from SW Western Blvd. will be closed. Both the east and west sidewalks on Stadium Ave. directly behind The LaSells Stewart Center will be closed. A vehicle detour will be available from Western Blvd. along the east and north side of the LaSells Stewart Center East parking lot.

The map shows a road closure on SW Stadium Ave. directly behind LaSells Stewart Center. The east and west sidewalks on Stadium Ave., behind LaSells Stewart Center, are also marked as closed. The LaSells Stewart Center East parking lot is marked as closed. A vehicle detour is marked from SW Western Blvd. along the east and north side of the LaSells Stewart Center East parking lot.

For questions or comments on this closure, contact Construction Manager Justin Fuszek at (541) 740-5260.