As part of the UHDS Vision Phase 1 project, several parking lots along SW Stadium Ave. will be impacted by intermittent parking space and drive lane closures starting Friday, Jan. 31 through Wednesday, Feb. 12.

The impacted lots will remain open, but various parking spaces and drive lanes may be temporarily closed during this time frame.

Impacted parking lots

  • 3259 – LaSells Stewart Center East Lot (B2)
  • 3270 – Bloss Hall South Lot (B2)
  • 3273 – Bloss Hall West Lot (B2)
  • 3280 – May Way Lot (R)
A map showing closures in several parking lots along SW Stadium Ave.

For questions or comments on this closure, contact Construction Manager Tarrigon Van Denburg at (714) 390-5313.

As part of the Bloss Hall Renovation project, a crane will be working within a fenced construction area on SW Stadium Ave. on Wednesday, January 29. The work zone and road closure will be located on the west side of Bloss Hall. A section of parking spaces between Bloss Hall and CH2M Hill Alumni Center (Bloss Hall West Lot) will be closed.

Vehicles may detour through the Bloss Hall West Lot or access Stadium Ave. from SW 26th St.

The sidewalk between Bloss Hall and Arnold Dining Center will be closed.

Other possible impacts include noise near the work area.

A map showing a fenced construction area and crane location on SW Stadium Ave., west of Bloss Hall.

For questions or comments on this closure, contact Josh Walsh at (541) 737-0927.

As part of the Hinsdale Lab Addition project, the parking lot on the east side of the Hinsdale Wave Research Lab will be closed along with the westbound lane on SW Jefferson Way. This closure will be in effect starting on Monday, January 27 through Friday, February 14. The south sidewalk on Jefferson Way will also be closed in this area. Pedestrians may use the north sidewalk as a detour.

Flaggers will be present to direct traffic and assist pedestrians.

The east entrance of Hinsdale Wave Research Lab will be closed. The north entrance will remain open.

Other possible impacts include noise near the work area.

A map showing a street lane, parking lot and sidewalk closure on SW Jefferson Way, near Hinsdale Wave Research Lab.

For questions or comments on this closure, contact Construction Manager Derek Bennett at (541) 609-6111.

Ziply Fiber will be installing aerial fiber as part of a city of Corvallis project at the intersection of SW Western Blvd and SW 15th St. on Thursday, January 16. This work will require the traffic signal to be shut down from 9 a.m. to 12 p.m. Flaggers will be directing traffic through the intersection. Efforts will be made to maintain pedestrian access when possible. Sidewalk closures may be necessary.

A map showing the intersection of SW Western Blvd. and SW 15th St.

The building air fans will be shut down one at a time to perform preventive maintenance and change air filters in Ag. Life & Sciences January 15, 2025 7:00 am – 12:00 pm. Building occupants may notice slight pressure & air flow changes throughout the building.

For questions or comments on this closure contact Richard Olsen at 541-737-7025.

As part of the Washington Way Improvement project, the walkway around the sand volleyball courts at Dixon Recreation Center will be closed starting Monday, January 13 through Wednesday, January 15. The west sidewalk on SW 26th St. and the north sidewalk on SW Washington Way will remain open.

A map showing a closure of the walkway west of the Dixon Recreation Center sand volleyball courts.

Other possible impacts include noise, dust and mud near the work area.

For questions or comments on this closure, contact Construction Manager Derek Bennett at (541) 609-6111.

This is an update on the Washington Way Improvement project. Multiple changes are expected to begin on Monday, January 13 and continue for the next several months. Please see below for details and locations, including a new road closure.

Update – road reopening

  • Washington Way between 30th – 35th St. will be reopening to all traffic starting January 13.

Upcoming road closure on Washington Way

  • 1/13 – 2/28: Washington Way closed between 17th and 26th St. to allow for new steam line installation.
    • The 17th St. intersection will be closed; vehicles traveling north-south through campus should use 15th St. as a detour.  
    • SW Benton Place will remain open.
    • May Way closed to through traffic; delivery truck traffic will be permitted.
    • Pedestrians – the crosswalk at 17th St. will be closed; cross Washington Way at 15th St. or Dixon/Goss driveway crosswalk. Multi-use path (south side) closed from Goss Stadium to 15th St. Use north sidewalk as a detour.
A map showing a road closure on Washington Way between SW 17th and SW 26th St.

Sidewalk/multi-use path access through approx. March 15

  • 30th – 35th St.: multi-use path (south) and sidewalk (north) both fully open.
  • 26th – 30th St.: multi-use path closed; sidewalk open.
  • 15th – 26th St.: multi-use path closed from Goss Stadium to 15th St.; sidewalk on the north side will be open.

For questions or comments on this closure, contact Construction Manager Derek Bennett at (541) 609-6111.

As part of Jen-Hsun Huang and Lori Mills Huang Collaborative Innovation Complex project, a crane will be working within the established construction site along SW 26th St. between NW Orchard Ave. and NW Monroe Ave. This work will take place starting Saturday, January 11 through Saturday, January 18.

The east sidewalk and bike lane on SW 26th St. will be closed. Flaggers will be present to direct vehicles, bicyclists and pedestrians through the work zone.

A map showing the location of crane activity on SW 26th St. between NW Orchard Ave. and NW Monroe Ave.

For questions or comments on this closure, contact Construction Manager Jason Lundy at (541) 270-0193.