The elevators will be shut down in the following buildings on the days listed below from 8:00 am to 4:30 pm while the annual category five full load testing is performed.

Tuesday November 10, 2020

  • Austin Hall Elevator #1 & #2

Thursday November 12, 2020

  • Learning Innovation Center Elevator #1 & #2
  • Cordley East Elevator (Time Permitting)

Friday November 13, 2020

  • Learning Innovation Center Elevator #3 & #4
  • Cordley East Elevator (Time Permitting)

For questions or comments on this notice contact, Facilities Services at 541-737-2969.

For work related to the Weatherford Place ADA Upgrade, both lanes of SW Weatherford Place will be closed for the installation of new lights. The closure is scheduled to start on Monday, Nov. 9, 2020 through Tuesday, Nov. 10, 2020, with work occurring from 10 a.m. to 6 p.m., daily.

For questions or comments on this closure, contact Construction Manager Lindsey Austin at (541) 990-7720.

SW Weatherford Place area map

As part of the Magruder Hall Renovation and Addition, chiller 4 at Magruder Hall is scheduled to be shut down for wiring work (view map). The shutdown is scheduled to start on Thursday, Nov. 5 through Saturday, Nov. 7, 2020. The chiller will be off for a total of three days. The main panel will be turned off and a planned electrical shutdown for the building will occur for approximately two hours on Saturday, Nov. 7.

For questions or comments on this closure, contact Project Manager John Doty at 541-740-8302.

Magruder Hall area map

As part of the Nash Hall Elevator Project, a crane pick will be set up outside of Nash Hall (view map). This will require caution in the surrounding area and the contractor will provide caution tape around critical areas. Work is scheduled to occur on Monday, Nov. 2, 2020.

For questions or comments on this closure, contact OSU Infrastructure Project Manager Aaron Collett at 541-207-2780 or Ausland Group contractor Tom Jordan at 541-228-5197.

Nash Hall area map

All steam services will be shutdown to these buildings beginning Sunday, November 1st until the afternoon of Wednesday, November 4th.  This critical shutdown is necessary to repair a leaking steam line in the vault behind Johnson Hall and to replace failed pumps.  This will affect all steam services in these buildings including heating, autoclaves and hot water.  Building temperatures will be lower than normal during this time.

For questions or comments on this closure, contact Les Walton at 541-737-8812.

As part of the North District Utility Plant (NDUP) project, NW Orchard Avenue will be closed to complete utility work associated with the NDUP. Please view the map for erinoutdoors closure area information. The road closure and utility work started on Monday, Oct. 26, 2020. The closure has been extended through Monday, Nov. 30, 2020.

For questions or comments on this closure, contact Construction Manager Jason Lundy at 541-270-0193.

NW Orchard Avenue closure area map