The steam system will be shut down in the Agricultural & Life Sciences Building starting Tuesday, August 22 at 4:30 P.M. The system is expected to resume normal operations on Friday, August 25 at 10:00 A.M.

The shutdown will allow for necessary steam pipe repairs and equipment replacement. This shutdown will impact all floors in the ALS building. During the shutdown, autoclaves, drying cabinets, humidifiers and hot water in laboratories will be unavailable.

The hot water in breakrooms and restrooms will not be impacted by this shutdown.

For questions or comments on this closure, contact Construction Manager Justin Fuszek at (541) 740-5260.

The steam will be shut down in Cordley Hall East, Ag. Life Sciences Building, Linus Pauling, Nash Hall, West Greenhouse & Crop Sciences August 24, 2023 12:01 am – 8:00 am to repair distribution isolation valve gasket on the steam line along Campus Way (200 ft east of the north bound lane of SW 30th st.) This process affects hot water supply, heating, and all equipment that uses steam, building wide. 

For questions or comments on this closure, contact Facilities Services at 541-737-2969.

Convergint will be conducting annual fire alarm & sprinkler testing.  Testing will take place in the buildings listed below.  The testing will be brief and include both sounding of alarms and strobes. As part of the testing building occupants may notice occasional beeping coming from the fire panel and horns and strobe lights activating throughout the building.  Signage will be posted on exterior doors while testing is being conducted.

August 28th 

  • Gymnastic Practice Facility
  • Coast Range Building
  • Research Way Building

August 29th

  • Crew Facility
  • JL Fryer Aquatic Animal Health Lab
  • Ocean Observing Center

August 30th

  • Magruder Hall
  • Kelley Engineering Center 

August 31st

  • Kelley Engineering Center   

September 1st

  • Kelley Engineering Center 

For questions or comments on this notice contact, Facilities Services at 541-737-2969.