Due to tree work in the memorial Union quad the yellow marked entrances and sidewalks will be closed for access (see map) beginning Tuesday, September 10, 2024 from 8:00 am to 4:00 pm.
For questions or comments on this closure, contact Chris Trine at 541-737-3488.
Construction zones will be set up in several locations around campus for sewer work. The work will be ongoing through Friday, September 13. No closures of roads or sidewalks are expected, but pedestrians should be aware that some sidewalks may be partially obstructed. Safe pathways around the work zones will be available at all times. See below for locations.
Other possible impacts include noise, dust and mud near the work areas.
9/9 – 9/13: Clark Meat Lab (east side of the building)
9/9 – 9/13: SW Stadium Ave. (sidewalk west of Finley Hall)
9/9 – 9/13: SW Campus Way (between Cordley Hall and the ALS Building)
For questions or comments on this closure, contact Construction Manager Derek Bennett at (541) 609-6111.