The Fairbanks Hall Renovation Project is now in construction. Due to forecasted windy weather and Fairbanks Hall re-roofing work overhead, the sidewalk between Fairbanks Hall and the Women’s Building will be closed temporarily for safety reasons on Friday September 24, 2021. The south door at the Women’s Building will have signage directing people to use a different door for this short duration. The sidewalk will re-open to pedestrians at 5 p.m. on Friday, September 24, 2021.

For questions or comments on this closure, contact Construction Manager Amy Keene at 541-214-1038.

Fairbanks Hall sidewalk closure area map

Emergency Street Shutdown Westbound lane at the intersection of 30th and Washington Way due to an apparent water main break. The City of Corvallis has been contacted and is en route to repair, unknown time of restoration.  Additional lane closures could occur as the work progresses. Magruder Hall will experience reduced water pressure while this repair is being performed.

As part of the Community Hall Slope Project, tree removal work in the project area is scheduled to start on Wednesday, September 1, 2021 through Friday, September 3, 2021. Additional work associated with the project is scheduled to continue on Tuesday, September 7, 2021, starting at the east side of Furman Hall.

Oregon State University began work in early July 2021 to update the area shown in this map image to provide access through this portion of OSU’s Corvallis campus for all people. ADA improvements related to the project will also require reconstruction of building entrances to Gladys Valley, the Pharmacy Building and Joyce Collin Furman Hall. There will be an open entrance to each building at all times. 

We will work to accommodate the needs of users working within the project area, but there will be disruptions to many day-to-day activities. If you have specific concerns regarding this project and how it may impact you or your work, please contact with Project Manager Lindsey Austin at 541-990-7720, to work through any issues.

Community Hall Slope Project work area

Brick repair work for the International Living-Learning Center (ILLC) is scheduled to start on Monday, August 9, 2021 through Thursday, September 16, 2021. Temporary sidewalk closures around the ILLC building will be in place and a lift will be on-site (view map).

For questions or comments on this closure, contact Joshua Walsh at 541-737-0927 or Patrick Robinson at 541-737-2428.

International Living-Learning Center area map

For work related to the Arts & Education Complex project, sections of the sidewalks along 15th Street and Washington Way will be closed off for several weeks. Pedestrian detours will be in place. Work is scheduled to start on Monday, July 12, 2021 through Friday, July 23, 2021.

For questions or comments on this work, contact Construction Manager Rick Freeman at 541-231-5368.

15th & Washington Way sidewalk closure area map

For work related to Pacific Power system upgrades, Pacific Power will continue to perform electrical trenching and drilling work through the end of August 2021. Electrical trenching and drilling work started at the intersection of 35th Street and SW Washington Way in mid-April 2021. Ongoing work will occur on both sides of SW Washington Way between 35th Street and 30th Street. This work supports Pacific Power’s power infrastructure and prepares for future upgrades to SW Washington Way.

The schedule of work along SW Washington Way includes:

  • Multi-Use Path trenching – July 6-7
  • Boring (north of SW Washington Way) – July 15-16
  • Finish work (north of SW Washington Way) July 26-Aug. 12
  • Temporary fencing by Magruder Hall – Aug. 2
  • Vault set – Aug. 6

For questions or comments on this work, contact Torre Oberg, the project manager with Magnum Power, at 360-703-7432, or OSU Infrastructure Project Manager Aaron Collett at 541-207-2780. Magnum Power is the contractor working with Pacific Power.

SW Washington Way area map

The sidewalk located on the south side of Callahan Hall was temporarily closed for window repair work being done at Callahan Hall. Work started on Tuesday, July 6, 2021. Work finished and the sidewalk was re-opened on Monday, August 9, 2021.

For questions or comments on this closure, contact Lizzet Stone, the UHDS operations manager for building finishes, at 541-737-8085.

Callahan Hall area map

As part of the Community Hall Slope Project, Oregon State University will begin work in early July 2021 to update the area shown in the map image below to provide access through this portion of OSU’s Corvallis campus for all people. ADA improvements related to the project will also require reconstruction of building entrances to Gladys Valley, the Pharmacy Building and Joyce Collin Furman Hall. There will be an open entrance to each building at all times. 

We will work to accommodate the needs of users working within the project area, but there will be disruptions to many day-to-day activities. If you have specific concerns regarding this project and how it may impact you or your work, please contact with Construction Manager Lindsey Austin at 541-990-7720, to work through any issues.

Community Hall Slope Project area map