Kelley Engineering Center will be readdressed to 2461 SW Campus Way beginning December 15, 2023. Emergency services and campus operations have been notified of this address change. Please update records accordingly.
Category Archives: Kelley Engineering Center
UPDATED: Campus Way Closure 26th St. to Memorial Pl. Extended Through 11/27
This is an update to a previous notification.
Please note: this closure has been extended. As part of the Kelley District Utility Plant project, SW Campus Way will be closed between SW 26th Street and SW Memorial Place starting Monday, November 6 through Monday, November 27 to allow for crane activity.
11/6 – 11/15: Closure on Campus Way Between 26th St. and Memorial Place
As part of the Kelley District Utility Plant project, SW Campus Way will be closed between SW 26th Street and SW Memorial Place starting Monday, November 6 through Wednesday, November 15 to allow for crane activity. The south entrance at Kelley Engineering Center will also be closed.
The north sidewalk in this section of Campus Way will be closed. The south sidewalk will remain open for pedestrians.
The bike lanes in this section of Campus Way will also be closed. Bicyclists may detour around the closure using the walkway on the south side of Milam Hall.


For questions or comments on this closure, contact Construction Manager Justin Fuszek at (541) 740-5260.
10/11 – Kelley Engineering Center Steam Shutdown
As part of the Kelley District Utility Plant project, the steam system will be shut down in Kelley Engineering Center on Wednesday, October 11 from 9 A.M. to 9 P.M. to allow for repairs and necessary modifications. The building will be without hot water during the shutdown and may experience temperature fluctuations. The 4th floor women’s restroom will also be closed during the shutdown.
For questions or comments on this closure, contact Construction Manager Justin Fuszek at (541) 740-5260.
9/18 – 9/22: Sidewalk Closure at East Entrance of Kelley Engineering Center
As part of the Kelley District Utility Plant project, construction activity will impact the east entrance of Kelley Engineering Center starting on Monday, September 18. The east entrance area will be part of an active work site through mid-October but will remain open.
In addition, a section of the sidewalk along SW Memorial Place, directly in front of the east entrance, will be closed from Monday, September 18 through Friday, September 22. Pedestrians will be directed across Memorial Place to the east sidewalk.
Other possible impacts include noise and dust near the work site.

For questions or comments on this closure, contact Construction Manager Justin Fuszek at (541) 740-5260.
9/7-9/8: Campus Way CLOSED Between 26th St. & Memorial Place
As part of the Kelley District Utility Plant project, SW Campus Way will be closed between SW 26th St. and SW Memorial Place on Thursday, September 7 and Friday, September 8 to allow for crane activity. The south entrance to Kelley Engineering Center will also be closed.
The north sidewalk on Campus Way will be closed between 26th St. and Memorial Place. The south sidewalk will remain open.
Other possible impacts include noise near the work site.

For questions or comments on this closure, contact Construction Manager Justin Fuszek at (541) 740-5260.
8/26 – Tree Trimming Work & Traffic Impacts on Campus Way
As part of the Kelley District Utility Plant project, there will be intermittent traffic impacts on SW Campus Way due to tree trimming activity on Saturday, August 26 from 8 A.M. to 10 A.M. The location of the work will be between SW Memorial Place and SW 26th Street., near Milam Hall and Kelley Engineering Center. The equipment blocking the roadway will move to accommodate vehicle traffic and allow for emergency access to the area.
Both the north and the south sidewalks on Campus Way will remain open for pedestrians. Other possible impacts include noise near the work site.

For questions or comments on this closure, contact Construction Manager Justin Fuszek at (541) 740 – 5260.
8/28/23-9/1/23: Scheduled: Fire Alarm & Sprinkler Testing
Convergint will be conducting annual fire alarm & sprinkler testing. Testing will take place in the buildings listed below. The testing will be brief and include both sounding of alarms and strobes. As part of the testing building occupants may notice occasional beeping coming from the fire panel and horns and strobe lights activating throughout the building. Signage will be posted on exterior doors while testing is being conducted.
August 28th
- Gymnastic Practice Facility
- Coast Range Building
- Research Way Building
August 29th
- Crew Facility
- JL Fryer Aquatic Animal Health Lab
- Ocean Observing Center
August 30th
- Magruder Hall
- Kelley Engineering Center
August 31st
- Kelley Engineering Center
September 1st
- Kelley Engineering Center
For questions or comments on this notice contact, Facilities Services at 541-737-2969.
8/11-8/30: Air Conditioning Shutdown Kelley Engineering & Johnson Hall
As part of the Kelley Engineering District Utility Plant project, the air conditioning system will be shut down in Kelley Engineering Center and Johnson Hall from Friday, August 11 through Wednesday, August 30.
For questions or comments on this project, contact Project Manager Ryan Wilson at (503) 779-3488.
7/27/23-TBD: Kelley Engineering Center Emergency Generator Shutdown
8/1/23 Update: Kelley generator has been repaired and is back in service.
7/27/23 Update: A temporary backup generator has been connected to the building.
Due to a mechanical failure, the Kelley Engineering Center backup generator has been taken offline. This will affect any system in the building requiring backup power only if there is an actual power outage. Crews are working on locating a temporary backup generator large enough for the building until repairs can be completed. An additional notice will be sent out when a temporary backup generator is located and connected to the building.
For questions or comments on this notice contact, Facilities Services at 541-737-2969.