Facilities Services will be performing annual load bank testing for the below listed building emergency/ stand-by generators.  Each test will take approximately 3 hours. There may be excessive noise and possible exhaust fume odors associated with testing.  Each generator will be refueled after testing. 

Week of July 1st 

  • Cascade Hall 
  • Reser Stadium East 
  • Merritt Truax Indoor Center 
  • Magruder Hall Onan 
  • Magruder Hall Generac 

Week of July 8th 

  • Lab Animal Resources Center 
  • Dryden Hall 
  • George W. Peavy Forest Science Center 
  • Richardson Hall 

Week of July 15th 

  • Energy Center 
  • Precision Agriculture Systems Center 
  • RAIL 
  • Austin Hall & Learning Innovation Classroom Building 

Saturday July 20th 

  • Nash Hall & Linus Pauling Science Center 
  • Agricultural & Life Sciences Building 

Week of July 22nd 

  • Hallie E. Ford Center 
  • Milam Hall  
  • Burt Hall 
  • Dearborn Hall 

Week of July 29th 

  • Milne Computer Center 
  • The Valley Library 
  • Pharmacy 
  • Western Shops  

For questions or comments on this notice contact, Facilities Services at 541-737-2969. 

Scheduled: Fire Alarm & Sprinkler Testing

Effective Date(s): August 14th-August 18th, 2023

Convergint will be conducting annual fire alarm & sprinkler testing.  Testing will take place in the buildings listed below.  The testing will be brief and include both sounding of alarms and strobes. As part of the testing building occupants may notice occasional beeping coming from the fire panel and horns and strobe lights activating throughout the building.  Signage will be posted on exterior doors while testing is being conducted.

August 14th  

  • Beth Ray
  • Cascade Hall
  • Parking Structure

August 15th

  • Kerr Administration/ Kerr B210 Data Room
  • McAlexander Field House

August 16th

  • Goss Stadium
  • Snell Hall/ MU East

August 17th

  • Ballard Extension Hall
  • Bates Hall
  • Hallie Ford

August 18th

  • Gilmore Annex
  • Gilmore Hall
  • Hovland Hall
  • Nash Hall

For questions or comments on this notice contact, Facilities Services at 541-737-2969.

As part of the Cascade Hall exterior stair replacement project, crane work to place exterior stairs on the south side of Cascade Hall will occur on Wednesday, September 14, 2022. A section of parking in this area will be closed while work takes place. The exterior stairs to the second floor of the building will re-open on Thursday, September 15, 2022.

For questions or comments about this closure, contact Project Manager Christina Vinson at 503-420-1031.

Cascade Hall area map

As part of the Cascade Hall exterior stair replacement project, crane work to remove exterior stairs on the south side of Cascade Hall will occur from Monday, July 11, 20022 through Tuesday, July 12, 2022. Parking in this area will be closed while work takes place. The exterior stairs to the second floor of the building will be closed until Monday, August 1, 2022.

For questions or comments about this closure, contact Project Manager Christina Vinson at 503-420-1031.

Cascade Hall area map

Facilities Services will be performing annual load bank testing for the below listed building emergency/ stand-by generators.  Each test will take approximately 3 hours. There may be excessive noise and possible exhaust fume odors associated with testing.  Each generator will be refueled after testing.

Week of July 4th

  • Reser Stadium
  • Merritt Truax Indoor Center
  • Magruder Hall Onan
  • Magruder Hall Generac

Week of July 11th

  • Cascade Hall
  • Dryden Hall
  • Lab Animal Resources Center
  • George W. Peavy Forest Science Center
  • Richardson Hall

Week of July 18th

  • Energy Center
  • Precision Agricultural Systems Center
  • RAIL

Saturday July 23rd

  • Nash Hall & Linus Pauling Science Center
  • Agricultural & Life Sciences Building

Week of July 25th

  • Hallie E. Ford Center
  • Kelly Engineering Center
  • Johnson Hall
  • Plageman Student Health Center

For questions or comments on this notice contact, Facilities Services at 541-737-2969.

Closures are often subject to changes and delays, so please visit the OSU Campus Closures, Shutdowns, and Detours page for updates on this and other campus closures.

Please forward this notice to anyone who would benefit from this information.

_____________________________

Facilities Services

University Facilities, Infrastructure & Operations

Oregon State University

830 SW 35th Street | Corvallis, OR 97331 | 541-737-2969

Facilities Services will be performing annual load bank testing for the below listed building emergency/ stand-by generators.  Each test will take approximately 3 hours. There may be excessive noise and possible exhaust fume odors associated with testing.  Each generator will be refueled after testing.

Week of July 5th

  • Reser Stadium
  • Merritt Truax Indoor Center
  • Magruder Hall Onan
  • Magruder Hall Generac
  • Dryden Hall

Week of July 12th

  • Cascade Hall
  • Lab Animal Resources Center
  • George W. Peavy Forest Science Center
  • Richardson Hall

Week of July 19th

  • Energy Center
  • Precision Agricultural Systems Center
  • RAIL
  • Austin Hall
  • Learning Innovation Center

Saturday July 24th

  • Nash Hall & Linus Pauling Science Center
  • Agricultural & Life Sciences Building

Week of July 26th

  • Hallie E. Ford Center
  • Kelly Engineering Center
  • Johnson Hall
  • Plageman Student Health Center

For questions or comments on this notice contact, Facilities Services at 541-737-2969.

Steam will be isolated to Cascade Hall and Adams Hall on Friday April 24, 2020 at 3 p.m. to accommodate construction work on the system at Cascade Hall. The system will be returned to service on Monday, April 27, 2020 by 3 p.m. This will only affect building heat in a portion of the building supplied by steam heat.

For questions or comments on this closure, contact Construction Manager Jason Lundy at 541-270-0193.