As part of the North District Utility Plant (NDUP) and Cordley Hall Renewal projects, crews will be performing additional chiller start up procedures on three new chillers within the NDUP. Functional testing will again include integration with the existing chilled water loop beginning at 7 a.m. on Monday, October 25 through 5 p.m. on Friday, October 29, 2021. Ag Life Sciences, Nash Hall, Cordley Hall, Wilkinson Hall and the Burt Complex could see chilled water flow and temperature fluctuations as a result of the testing procedures.
For questions or comments on this closure, contact Construction Manager Jason Lundy at 541-270-0193 or Project Manager Dustin Sievers at 541-760-6240.
Discover more from OSU Corvallis Campus Closures, Shutdowns and Detours
Subscribe to get the latest posts sent to your email.