As part of the Owen Hall chiller replacement, the chiller manufacturer will be installing additional equipment that will require the chiller to be shutdown. This will only impact comfort cooling. The secondary chiller will continue to support the labs. The primary chiller shutdown is scheduled from 7 a.m. to 4 p.m. on Tuesday, October 26, 2021.

For questions or comments on this closure, contact Construction Manager Jason Lundy at 541-270-0193

Owen Hall area map

As part of the North District Utility Plant (NDUP) and Cordley Hall Renewal projects, crews will be performing additional chiller start up procedures on three new chillers within the NDUP. Functional testing will again include integration with the existing chilled water loop beginning at 7 a.m. on Monday, October 25 through 5 p.m. on Friday, October 29, 2021. Ag Life Sciences, Nash Hall, Cordley Hall, Wilkinson Hall and the Burt Complex could see chilled water flow and temperature fluctuations as a result of the testing procedures.

For questions or comments on this closure, contact Construction Manager Jason Lundy at 541-270-0193 or Project Manager Dustin Sievers at 541-760-6240.

North District Utility Plant area map