The medium pressure steam will be shut down in Ag. Life Sciences Building December 28, 3:00 pm – December 29, 2020 5:00 pm to tie it into the system. This will affect autoclaves in the building.
For questions or comments on this closure, contact Facilities Services at 541-737-2969.
As part of the Research Way Building Library Archives project, work will occur in the basement of the Research Way Building. Insulation mock-up work at the ceiling will happen starting around the first part of January 2021. The Research Way Building is located at 4700 SW Research Way in Corvallis. We are providing this early notification to the building users, and to those who visit from campus, that this activity may have the possibility of fumes and smells during the installation time. The mock-up work will occur during the first or second week of January 2021 and is anticipated to take three days to complete. Our general contractor will post signs at entry points into the basement to warn users of the insulation activity during this installation.
Road closures are scheduled around West Campus residence halls to support work related to the Buxton, Hawley and West roof replacement projects. Work is scheduled to take place from 8 a.m. to 5 p.m., on Friday, Dec. 18, 2020. Work will start at 8 a.m. at SW Intramural Lane south of West Hall. Once complete, work will transition to the west end of Hawley Hall and obstruct SW Sackett Place and the east sidewalk. Then, work will shift to the north of Hawley Hall and Buxton Hall, and one lane of SW Jefferson Way will be closed along with the south sidewalk. Next, work will shift to SW Weatherford Place and will close the road as well as the west sidewalk. Each portion of work is anticipated to take approximately two hours to stage and pick the supplies to the roofs of the buildings. Intramural parking lot #3294 will also be impacted while work takes place.
For questions or comments on this closure, contact Patrick Robinson with University Housing and Dining Services at 541-737-2428.
The steam will be shut down in Dryden Hall December 10th, 2020 from 10:00am – 12pm to repair a leaking steam line. This will affect all steam services including heating, hot water and any equipment utilizing steam.
For questions or comments on this closure, contact Jack Jenkins at 541-737-2969.
All steam services for Weniger Hall will be shut down Thursday, December 10th from 1pm to 3pm, in order to replace a failed steam valve. This will affect hot water and heating throughout the building.
For questions or comments on this closure, contact Jack Jenkins at 541-737-2969.
As part of the Motor Pool Canopy Construction project, drilling and geotechnical boring work will occur to investigate soils adjacent to the Motor Pool Canopy located on SW Campus Way. There could be some restrictions to access to the fuel island at the Motor Pool. One side of the fuel island should still be accessible for careful fueling.
For questions or comments on this closure, contact OSU Infrastructure Project Manager Aaron Collett at 541-207-2780.
As part of the Cordley Hall Renovation project, NW Orchard Avenue will change to one-way traffic eastbound, between NW 30th Street and NW 27th Street, beginning on Thursday, Dec. 3, 2020. This change will be in place for the duration of the Cordley Hall Renovation through 2024.
For questions or comments on this closure, contact Construction Manager Jason Lundy at 541-270-0193.