As part of the Kelley District Utility Plant project, there will be intermittent traffic impacts on SW Campus Way due to tree trimming activity on Saturday, August 26 from 8 A.M. to 10 A.M. The location of the work will be between SW Memorial Place and SW 26th Street., near Milam Hall and Kelley Engineering Center. The equipment blocking the roadway will move to accommodate vehicle traffic and allow for emergency access to the area.

Both the north and the south sidewalks on Campus Way will remain open for pedestrians. Other possible impacts include noise near the work site.

The map shows an area marked for tree trimming activity on SW Campus Way between SW Memorial Place and SW 26th St.

For questions or comments on this closure, contact Construction Manager Justin Fuszek at (541) 740 – 5260.

As part of the LaSells Stewart Center Mechanical & Roof Renewal Project, a section of SW Stadium Ave. located directly behind The LaSells Stewart Center and just south of Bloss Hall will be closed to allow for crane activity on Friday, August 25 from 7 A.M. to 3:30 P.M. The B2 parking lot east of The LaSells Stewart Center will also be closed. The entrance to SW Stadium Ave. from SW Western Blvd. will be closed. Both the east and west sidewalks on Stadium Ave. directly behind The LaSells Stewart Center will be closed. A vehicle detour will be available from Western Blvd. along the east and north side of the LaSells Stewart Center East parking lot. 

The map shows a road closure on SW Stadium Ave. directly behind The LaSells Stewart Center. The east and west sidewalks on Stadium Ave., behind The LaSells Stewart Center, are also marked as closed. The LaSells Stewart Center East parking lot is marked as closed. A vehicle detour is marked from SW Western Blvd. along the east and north side of the LaSells Stewart Center East parking lot.

For questions or comments on this closure, contact Construction Manager Justin Fuszek at (541) 740-5260.  

The steam system will be shut down in the Agricultural & Life Sciences Building starting Tuesday, August 22 at 4:30 P.M. The system is expected to resume normal operations on Friday, August 25 at 10:00 A.M.

The shutdown will allow for necessary steam pipe repairs and equipment replacement. This shutdown will impact all floors in the ALS building. During the shutdown, autoclaves, drying cabinets, humidifiers and hot water in laboratories will be unavailable.

The hot water in breakrooms and restrooms will not be impacted by this shutdown.

For questions or comments on this closure, contact Construction Manager Justin Fuszek at (541) 740-5260.

The steam will be shut down in Cordley Hall East, Ag. Life Sciences Building, Linus Pauling, Nash Hall, West Greenhouse & Crop Sciences August 24, 2023 12:01 am – 8:00 am to repair distribution isolation valve gasket on the steam line along Campus Way (200 ft east of the north bound lane of SW 30th st.) This process affects hot water supply, heating, and all equipment that uses steam, building wide. 

For questions or comments on this closure, contact Facilities Services at 541-737-2969.

Convergint will be conducting annual fire alarm & sprinkler testing.  Testing will take place in the buildings listed below.  The testing will be brief and include both sounding of alarms and strobes. As part of the testing building occupants may notice occasional beeping coming from the fire panel and horns and strobe lights activating throughout the building.  Signage will be posted on exterior doors while testing is being conducted.

August 28th 

  • Gymnastic Practice Facility
  • Coast Range Building
  • Research Way Building

August 29th

  • Crew Facility
  • JL Fryer Aquatic Animal Health Lab
  • Ocean Observing Center

August 30th

  • Magruder Hall
  • Kelley Engineering Center 

August 31st

  • Kelley Engineering Center   

September 1st

  • Kelley Engineering Center 

For questions or comments on this notice contact, Facilities Services at 541-737-2969.

The Richardson Hall chiller and chilled water system will be shut down Monday August 21, 5:00 am – Tuesday August 22, 2023 9:00 am for time sensitive repairs to keep the system operational for the duration of the cooling season. Building occupants will notice warmer than normal air temperatures during this time. This will not affect temperatures in the server rooms.

For questions or comments on this closure contact Sean Olsen at 541-737-2969.

Pacific Power is scheduling a power outage on August 29th, 2023. Their substation operations team needs to perform routine maintenance on the transformers in the 35th Street Substation. The outage will begin Tuesday morning at 3:00 am with an estimated completion time of 7:00 am.  Please see the list of impacted buildings below.

 Affected buildings:

  • RAIL Complex and Lagoon Pump
  • Swine Barn/Center
  • Irrigation Pump
  • Dairy Parlor
  • Dairy Barn
  • Turkey Office
  • Turkey Barn
  • Turkey House
  • West Irrigation Pumps
  • Dairy House
  • Rabbit Research Labs I &II
  • Farm Service and Storage
  • Animal Physiology
  • Beef Barn/Sheep Barn
  • Small Animal Lab
  • Hogg Animal Metabolism Laboratory
  • James E. Oldfield Animal Teaching Facility
  • Seed Lab
  • Motor Pool
  • Clark Laboratory
  • Sackett Hall
  • West Greenhouse
  • Wiegand Hall
  • East Greenhouse
  • Radiation Center (Reactor Room C136)
  • Cordley East Temporary Power
  • Withycombe Temporary Power

What do you need to do to prepare for this outage? Please make sure that all computers, printers, copiers, and other electronic devices are turned off prior to August 29th , 2023. If you have an Uninterruptable Power Supply (UPS), also known as a battery back-up, please be sure to turn it off as well.

As part of the Kerr South Parking Lot project, SW 15th St. will be closed in both directions between SW Washington Ave. and SW Jefferson Way. This closure will be in effect from Tuesday, August 22 until Tuesday, September 5.

The crosswalk at 15th St. and Washington Ave. will also be closed along with the east sidewalk between Washington Ave. and SW Adams Ave. Please refer to the pedestrian detour information below.

Please note: SW Washington Way is currently closed between SW 15th St. and SW 26th St., which means that SW Benton Place will not be accessible as a north-south detour option.

Vehicle detour: SW Washington Ave., to SW 11th St. to SW Jefferson Way.

The map shows a closure on SW 15th St. between SW Washington Ave. and SW Jefferson Way. It shows a vehicle detour along Washington Ave. to SW 11th St. to Jefferson Way.

Pedestrian detour: take the north sidewalk on Washington Ave. to the walkway along SW 14th St. Proceed across Adams Ave. to the north sidewalk and continue along the east sidewalk on SW 15th St.

The map shows road closure on SW 15th St. between SW Washington Ave. and SW Jefferson Way. A pedestrian detour route is marked along the north side of Washington Ave. to the walkway on SW 14th St. to the north sidewalk on SW Adams Ave. to the east sidewalk along 15th St.

Please note: the west sidewalk along SW 15th St. is currently unavailable due to a separate closure related to this project.

For questions or comments on this closure, contact Construction Manager Derek Bennett at (541) 609-6111.