This is an update on a water pipeline and road improvement project led by the city of Corvallis. Work is expected to continue through September 2025.
Impacts on SW 35th St. for 8/4 – 8/22
- Full closure of SW 35th St. at the Oak Creek bridge starts Monday, August 4th through Friday, August 22.
- The bridge will remain fully closed to ALL traffic, including emergency vehicles.
- Drivers may use SW 30th or SW 15th St. as a north-south detour route.
- SW 35th St. will remain open to traffic on both the north and south sides of the bridge, with local access for OSU facilities and private residences, but no traffic will be allowed to cross. The bridge will remain closed overnight and through weekends.
- Bike lanes on SW 35th St. will be closed. Sidewalks will remain open.

Impacts on SW Western Blvd. for 8/4 – 8/7
Paving work will also occur on Western Blvd. during this time frame and traffic impacts in this area are expected.
- 8/4 – 8/5: Western Blvd. closed between Hwy 20/Philomath Blvd. and the intersection with SW West Hills Rd.
- Drivers should plan to use Hwy 20 to SW 35th St. as a detour.
- 8/6 – 8/7: Western Blvd. fully closed between SW 26th and SW 15th St.
- Drivers should plan to use Hwy 20 as a detour route. (see map below)
- Sidewalk ADA ramp work will be completed at the Western Blvd./SW 15th St. intersection.

Impacts to bus service
- Changes to CTS stops will be in effect . Changes will be posted at the bus stops and will be noted on the City’s website. https://www.corvallisoregon.gov/cts
- To check Beaver Bus route changes, please visit https://transportation.oregonstate.edu/beaver-bus/beaver-bus-route-changes.
For questions or comments on this closure, contact Josh.Bjornstedt@corvallisoregon.gov.