SW 26th St. will be closed to vehicle traffic between NW Orchard Ave. and NW Monroe Ave. starting Monday, July 22 through Friday, August 9. Please see original notification for further details.
For questions or comments on this closure, contact Construction Manager Jason Lundy at (541) 270-0193.
7/8: A section of NW Orchard Ave. between NW 27th and NW 30th St. will be fully closed to all vehicle traffic to allow for street and sewer repair work.
7/9 – 7/12: The westbound lane on NW Orchard Ave. between NW 27th and NW 30th St. will be closed. Vehicles will be limited to one-way, eastbound traffic only.
Access to the North District Utility Plant and the Cordley Hall West loading dock will be available via a detour along SW Campus Way east to the fire lane west of Cordley Hall.
The south sidewalk in this section of Orchard Ave. will be closed July 8 – 12. The north sidewalk will remain open for pedestrians.
Other possible impacts include noise near the work site.
For questions or comments on this closure, contact Construction Manager Jason Lundy at (541) 270-0193.
NW Orchard Ave. will resume two-way traffic between NW 27th and NW 30th Streets starting on Friday, March 15 at 3 P.M. The street was previously limited to one-way traffic due to construction activity related to the Cordley Hall Renewal project.
For questions or comments on this closure, contact Construction Manager Jason Lundy at (541) 270-0193.