As part of the North District Utility Plant (NDUP) and Cordley Hall Renewal projects, crews will be performing chiller start up procedures and functional testing on three new chillers within the North District Utility Plant. Functional testing will include integration with the existing chilled water loop beginning at 7 a.m. on Monday, October 11, 2021 through 5 p.m. on Friday, October 15, 2021. The Agricultural & Life Sciences Building, Nash Hall, Cordley Hall, Wilkinson Hall and the Burt Complex could see chilled water flow and temperature fluctuations as a result of the testing procedures. The NDUP is located along NW Orchard Avenue next to Cordley Hall.

For questions or comments on this closure, contact Construction Manager Jason Lundy at 541-270-0193 or Project Manager Dustin Sievers at 541-760-6240.