As part of the Kelley District Utility Plant project, the building heat and hot water systems will be shut down in Kelley Engineering Center starting Tuesday, October 29 through Thursday, October 31.  

The building temperature will fluctuate during this shutdown and domestic hot water service will not be available throughout the building, including kitchens and restrooms. The building will be pre-heated on Monday to a higher-than-normal temperature in anticipation of the Tues-Thurs shutdown.

Temporary heating units will be placed in the atrium area. Other heat-preserving measures will be implemented to help stabilize the building temperature.

Multiple members of Facilities Services staff and all Kelley building managers will be coordinating and monitoring throughout the duration of the shutdown.

For questions or comments on this closure, contact Project Manager Ryan Wilson at (503) 779-3488.