As part of the Washington Way Improvement project, intersection work will occur along SW Washington Way at SW 17th, SW 26th and SW 30th Streets starting Monday, October 16 through Friday, October 20th. Please see the schedule below for details.
10/16 – 10/17: The intersection at 17th St. will be closed to vehicle traffic. Crosswalks and sidewalks will remain open for pedestrians.
10/17 & 10/19: Work will occur at the 26th St. intersection, but the intersection will remain open for vehicles and pedestrians. Flaggers will be present to direct traffic.
10/19 – 10/20: Work will occur at the 30th St. intersection, but the intersection will remain open for vehicles and pedestrians. Flaggers will be present to direct traffic.
For questions or comments on this closure, contact Construction Manager Derek Bennett at (541) 609-6111.