Please note: this closure has been extended. As part of the Kelley District Utility Plant project, SW Campus Way will be closed between SW 26th Street and SW Memorial Place starting Monday, November 6 through Monday, November 27 to allow for crane activity.
Please note that this shut down has been revised with extended dates. As part of the Nash Hall Process Water Tower Replacement project, the process water loop at Nash Hall will be shut down from Thursday, November 9 through Monday, November 13 at noon.
Correction: The west sidewalk on SW 15th St. near the Kerr Administration Building is closed under a previous notification and will remain closed through December 4. The east sidewalk will be open for pedestrians during the work occurring on November 9 and November 10.
As part of the Kerr South Parking Lot project, there will be intermittent delays on SW 15th St. due to construction activities on Thursday, November 9 and Friday, November 10. A single lane will be closed at a time, with traffic being allowed to pass through the opposite lane. Flaggers will be present to direct traffic.
The impacted area will be between SW Washington Ave. and SW Adams Ave. near the Kerr Administration Building and Callahan Hall. Drivers should expect delays between 9 A.M. and 3 P.M. on both days.
The west sidewalk will be closed along with the crosswalk at SW Adams Ave. The east sidewalk will remain open for pedestrians. Other possible impacts include noise near the work site.
For questions or comments on this closure, contact Construction Manager Derek Bennett (541) 609-6111.
The steam will be shut down in Magruder Hall November 9, 2023 7:00 am – 1:00 am to enable the contractor to raise the condensate line. This will affect all steam services, which includes autoclaves, washers, hot water, heating water as well as cooler temps may be noticed building wide.
For questions or comments on this closure contact Facilities Services at 541-737-2969.
As part of the Pride Center Renovation project, a section of SW May Ave. will be closed from Monday, November 6 through Wednesday, November 8. The impacted section is located between SW 15th and SW 16th Streets, directly behind the Pride Center. Several parking spaces along May Ave. will also be closed.
Other possible impacts include dust and mud near the work site.
For questions or comments on this closure, contact Construction Manager Scylise Little.
As part of the Nash Hall Cooling Tower Replacement project, the Sackett Hall North parking lot (#3303) will be partially closed on Monday, November 6 to allow for crane activity. The closure will impact parking spaces on the east side of the lot, closest to Nash Hall. The south-west basement and south first floor entrances to Nash Hall will also be closed. The north-east entrance and the loading dock will remain open.
In addition, the walkway that runs along the west side of Nash Hall will also be closed. Pedestrians may detour around the area via walkways on the south, east and north sides of the building.
Other possible impacts include noise near the work site.
For questions or comments on this closure, contact Project Manager Ryan Wilson at (503) 779-3488.
As part of the Kelley District Utility Plant project, SW Campus Way will be closed between SW 26th Street and SW Memorial Place starting Monday, November 6 through Wednesday, November 15 to allow for crane activity. The south entrance at Kelley Engineering Center will also be closed.
The north sidewalk in this section of Campus Way will be closed. The south sidewalk will remain open for pedestrians.
The bike lanes in this section of Campus Way will also be closed. Bicyclists may detour around the closure using the walkway on the south side of Milam Hall.
For questions or comments on this closure, contact Construction Manager Justin Fuszek at (541) 740-5260.
As part of the Nash Hall Process Water Tower Replacement project, the process water loop at Nash Hall will be shut down on Thursday, November 9 and Friday, November 10.
This shutdown will only impact the building’s freezers and cold rooms. A portable freezer trailer will be provided for temporary storage of frozen materials.
For questions or comments on this closure, contact Project Manager Ryan Wilson at (503) 779-3488.
As part of the Kerr Administration South Parking Lot Improvement project, the Kerr South parking lot closure has been extended until December 4, 2023, to finish construction activities, including lighting installation, paving and striping. This includes the closure of the west sidewalk. ADA access is available on the east side of the building.
For questions or comments on this closure, contact Project Manager Christina Vinson at (503) 420-1031.