As part of the Rogers Hall fume hood replacement project, a crane will be placed in the Graf Hall parking lot to lift equipment onto the roof of Rogers Hall. The work is scheduled for Monday, March 13 from 6:30 – 9 a.m. Limited parking spaces will remain available.

The image shows where a crane will be placed in the northwest corner of the Graff Hall parking lot. A block of parking spaces in the middle of the parking lot is shown as closed between 6 - 9 a.m. on March 13, 2023.

For questions or comments on this closure, contact Project Manager Dave Amundson at (541) 737-2760

As part of the Whyte Track & Softball Scoreboard project, three streetlights on the north side of the Whyte Track and Softball parking lot will be removed to allow for sidewalk construction and site work. New lights will be installed later this spring. Other possible impacts include noise and dust near the construction site.

Map showing the position of three street lights at the north side of the Whyte Track and Softball parking lot.

For questions or comments on this closure, contact Construction Manager Derek Bennett at (541) 609-6111 .

As part of the Pride Center Renovation project, SW May Ave. between the Pride Center and Adams Hall will be closed from 8:00AM – 2:00PM on Tuesday, February 7th. Access to the parking lots on the corners of SW A Ave./SW 17th St. and SW May Ave. /SW A Ave. will be maintained. Please refer to the map below for alternate routes.

For questions or comments on this closure, contact Construction Manager Scylise Little.

As part of the Pride Center Renovation project, the SW May Ave. and SW 16th St. entrances to the parking lot located at SW 17th and SW A Ave will be closed on Monday, Feb. 6th from 7:00 AM – 11:00 AM. The parking lot will remain open with access maintained at several other entrances. See map for alternate routes.

For questions or comments on this closure, contact Construction Manager Syclise Little.

As part of the Graf Hall Renovation project, a crane will be placed in the Graf Hall parking lot on Friday, Jan. 6th from 6:30 AM to 10:00 AM. The crane will be located within the fenced construction area. This may disrupt traffic patterns at the north end of the parking lot.

For questions or comments on this closure, contact Project Manager David Amundson at (541) 737-4551.

As part of the Graf Hall Renovation project, a crane will be placed in the Graf parking lot within the fenced construction area. Because the crane will remain within the established construction site, any additional impacts to campus residents, visitors and the surrounding neighborhood are expected to be minimal.  

For questions or comments on this project, contact Marty Waldo with Fortis Construction at (503) 894-4092.

As part of the Cascade Hall exterior stair replacement project, crane work to place exterior stairs on the south side of Cascade Hall will occur on Wednesday, September 14, 2022. A section of parking in this area will be closed while work takes place. The exterior stairs to the second floor of the building will re-open on Thursday, September 15, 2022.

For questions or comments about this closure, contact Project Manager Christina Vinson at 503-420-1031.

Cascade Hall area map

For work related to the Withycombe Hall renovation project, a closure is scheduled for parking lot #3316 (Orchard Ave. South Lot), located just north of Withycombe Hall along Orchard Ave., to allow for a construction trailer move in. The closure is scheduled from 6 a.m. to 5 p.m. on Wednesday, September 14, 2022.

For questions or comments on this closure, contact Construction Manager Rick Freeman at 541-231-5368.

Withycombe Hall area map

For work related to the 2022 Summer Parking Lot Renewal Project, multiple parking lot and roadway closures along SW Intramural Lane are scheduled.

  • The Intramural lot (lot #3294) will be closed from August 18-September 9, 2022.
  • The N 16th St East lot (lot #3224) will be closed from August 18-August 31, 2022.
  • The N 16th St West lot (lot #3223) will be closed from August 18-September 14, 2022.
  • SW Intramural Lane will be closed between SW 30th Street and SW 26th Street for the duration of the project.

For questions or comments on this closure, contact Infrastructure Project Manager Aaron Amoth at 541-737-5064.

Summer Parking Lot Renewal Project area map

As part of the Cascade Hall exterior stair replacement project, crane work to remove exterior stairs on the south side of Cascade Hall will occur from Monday, July 11, 20022 through Tuesday, July 12, 2022. Parking in this area will be closed while work takes place. The exterior stairs to the second floor of the building will be closed until Monday, August 1, 2022.

For questions or comments about this closure, contact Project Manager Christina Vinson at 503-420-1031.

Cascade Hall area map