11/10/22 @ 11:15am Operation to the freight elevator has been restored.

The freight elevator at Linus Pauling Science Center is currently shut down for emergency repairs. A restoral date is unknown at this time, replacement parts are on order. Updates will be provided when they are available. For questions contact Facilities Services at 737-2969.

A planned shutdown for the elevator located in Rogers Hall is scheduled to start on Wednesday, January 5, 2022 through Friday, February 25, 2022. Renovation work will be performed during the shutdown. Impacted buildings include Rogers Hall, Graf Hall and Dearborn Hall.

For questions or comments on this closure, contact Project Manager David Amundson at 541-737-2760.

Rogers Hall area map

For work related to the Community Hall Slope Project, a series of planned power outages are scheduled. The planned power outages will impact multiple buildings located along or near SW Jefferson Way in the Community Hall Slope Project work area. Planned outages are scheduled from Thursday, December 30, 2021 through Saturday, January 1, 2022.

The following buildings will be without power from 6-8 a.m. on Thursday, December 30, 2021: 

•          Buxton Hall 

•          Callahan Hall 

•          Cauthorn Hall

•          Gladys Valley Gymnastics Center

•          Hattie Redmond Women and Gender Center

•          Hawley Hall 

•          Heckart Lodge

•          Joyce Collin Furman Hall

•          Kerr Administration Building

•          McAlexander Field House

•          McNary Dining Hall 

•          McNary Hall

•          Pharmacy Building – Will not have access to existing generator

•          Poling Hall 

•          Reed Lodge

•          Snell Hall

•          West Dining Hall 

•          Wilson Hall 

The following buildings will be without power starting at 8 a.m. on Thursday, December 30, 2021 through 6 p.m. on Friday, December 31, 2021:

•          Gladys Valley Gymnastics Center

•          Hattie Redmond Women and Gender Center

•          Joyce Collin Furman Hall

•          Pharmacy Building  – Will not have access to existing generator

*Please note that Joyce Collin Furman Hall may be without power through midday on Saturday, January 1, 2022.

What do you need to do to prepare for this outage? Please make sure that all computers, printers, copiers, and other electronic devices are turned off prior to Thursday, December 30, 2021. If you have an Uninterruptable Power Supply (UPS), also known as a battery back-up, please be sure to turn it off as well. As necessary, be prepared to have someone report to campus following the planned outages to turn computers, printers and other electronic devices back on.

For questions or comments on this work, contact Construction Manager Ryan Wilson at 503-779-3488.

As part of the Owen Hall Renovation Project, a temporary elevator shutdown is scheduled from 7 to 9 a.m. on Thursday, October 14, 2021 to upgrade the fire alarm system in the building. The first and second floors of Owen Hall can be accessed by using Kearney Hall and the sky bridge.

For questions or comments on the elevator shutdown, contact Project Manager John Doty at 541-740-8302.

A temporary sidewalk closure in the area around the Owen Hall loading dock is scheduled from 7 a.m. to 3:30 p.m. daily starting Thursday, October 14 through Friday, October 15, 2021. A crew will be working on the roof of the building to install antenna locations for a DAS system.

For questions or comments on the DAS antenna work and temporary sidewalk closure, contact Project Manager David Amundson at 541-737-2760.

Owen Hall area map

As part of the Nash Hall Elevator project, the southwest elevator in Nash Hall will be out of service starting on Monday, Aug. 9 through Thursday, Aug. 12, 2021. The northeast elevator in Nash Hall will remain in service during this work. Work includes code-required modifications to fire sprinkler heads and associated electrical systems, which necessitates the temporary shutdown of the water to the fire suppression system and temporary disabling of associated alarms. A final elevator inspection is scheduled for Wednesday, Aug. 11, 2021. 

For questions or comments on this closure, contact Infrastructure Project Manager Aaron Collett at 541-207-2780 or contractor Jonathan Fisher, with Ausland Group, at 541-450-2774.

Nash Hall area map