As part of the Jen-Hsun & Lori Huang Collaborative Innovation Complex project, the intersection at SW 26th Street and NW Orchard Avenue will be closed to vehicle traffic on Friday, January 5 to allow for construction activity.

The north-south crosswalk on Orchard Ave. will be closed for pedestrians. The sidewalks in the area will remain open, except for a section of sidewalk on the east side of the intersection, directly in front of Johnson Hall. The loading dock north of Johnson Hall will be closed except for pre-arranged deliveries.

Bike lanes in the area will be closed.

The map shows an intersection closure at NW Orchard Ave. and SW 26th St.

For questions or comments on this closure, contact Project Manager Dustin Sievers at (541) 760-6240.

This is an update to a previous notification.

The intersection at SW 26th St. and NW Orchard Ave. will remain closed through Wednesday, December 20.

The map shows an intersection and crosswalk closure at NW Orchard Ave. and SW 26th St., near Johnson Hall.

For questions or comments on this closure, contact Construction Manager Jason Lundy at (541) 270-0193.

As part of early work for the Jen-Hsun & Lori Huang Collaborative Innovation Complex project, sidewalks on the north, south and east sides of Johnson Hall will be closed to pedestrians from Monday, December 18 through January 5, 2024.

Sidewalks closed on the south, north and east side of Johnson Hall from December 18 until January 5.

For questions or comments on this closure, contact Construction Manager  Jason Lundy at (541) 270-0193.

As part of the Jen-Hsun & Lori Huang Collaborative Innovation Complex project, the intersection at SW 26th Street and NW Orchard Avenue will be closed to vehicle traffic on Monday, December 18 and Tuesday, December 19 to allow for construction activity.

The north-south crosswalk on Orchard Ave. will be closed for pedestrians. The sidewalks in the area will remain open, except for a section of sidewalk on the east side of the intersection, directly in front of Johnson Hall. The loading dock north of Johnson Hall will be closed except for pre-arranged deliveries. The concrete walkway on the south side of Johnson Hall will also be closed.

Bike lanes in the area will be closed.

The map shows an intersection and crosswalk closure at NW Orchard Ave. and SW 26th St., near Johnson Hall.

For questions or comments on this closure, contact Construction Manager Jason Lundy at (541) 270-0193.

As part of the Jen-Hsun & Lori Huang Collaborative Innovation Complex project, a section of the west sidewalk along SW Park Terrace Place will be permanently closed to allow for ongoing construction activities. The closure will begin Thursday, November 30. The impacted sidewalk section is located just north of Johnson Hall. This will be a permanent closure as the area undergoes construction related to the Huang Collaborative Innovation Complex.

The east sidewalk will be open for pedestrians. Other possible impacts include noise, dust and mud near the work site.

The map shows a sidewalk closure on the west side of SW Park Terrace Place, just north of Johnson Hall. The east sidewalk is marked as open.

For questions or comments on this closure, contact Project Manager Dustin Sievers at (541) 760-6240.

As part of the Jen-Hsun & Lori Huang Collaborative Innovation Complex project, soil sampling work will occur around and near the Lonnie B. Harris Black Cultural Center from Monday, June 26 through Wednesday, June 28. Multiple parking spaces on the north end of the A2 parking lot west of the building will be closed. The rest of the parking lot will remain open. The work will require periodic closures to the Center’s patio area. The sidewalks bordering NW Monroe Avenue to the north and SW Memorial Place to the east will not be impacted. The sidewalks on the west and south sides of the Center may be temporarily unavailable due to equipment needs. Other possible impacts include noise near the work site.

The image shows the area surrounding the Lonnie B. Harris Black Cultural Center. Potential impacts to sidewalks are marked on the west and south sides of the building. Parking space closures are marked on the north side of the parking lot to the west of the Center. Locations for drilling sites are marked throughout the lawn and patio area. A text box states the drilling locations will be taped off while work is being done. A text box states that the patio will experience periodic closures and will be taped off during work.

For questions or comments on this closure, contact Construction Manager Scylise Little.