The location of this closure has been changed. The SW Jefferson Way closure scheduled for Monday, December 18 – Friday, December 22 has been moved to the west and will now begin at the Student Experience Center and extend to SW 26th St. This will open up SW Waldo Place for northbound vehicle traffic. The sidewalk closure will remain unchanged. See updated map below.
For questions or comments on this closure, contact Construction Manager Trevor Richie.
Please note that multiple projects will be starting and ending in the area over the next few weeks and months. See below for details.
Washington Way Closed Between 26th – 30th St. Starting Dec. 18
Washington Way between 26th and 30th St. will be closed for construction starting on Monday, December 18 and continuing through the winter and spring 2024 terms.
Washington Way 17th – 26th St. Reopening Jan. 5
Construction activity between 17th and 26th St. will be finishing up over the next few weeks, depending on the weather. This section of Washington Way is expected to reopen by Friday, January 5. The two-way cycle track will also be opening and a separate Campus Notification will follow regarding the traffic pattern change in the area.
Washington Way & 26th Street Construction During Winter Break
During the period between December 18 and January 5, Washington Way will be closed all the way from 17th to 30th St. The north sidewalk will be closed. The multi-use path on the south side of Washington Way will be open for pedestrians.
In addition, the intersection at 26th St. and Washington Way will be closed from December 18 through December 29. The intersection will be closed in ALL DIRECTIONS.This is a significant change to the notification sent on 12/14 regarding this closure. The sidewalks will be closed on both sides of 26th Street from Washington Way to Dixon Recreation Center.
For questions or comments on these closures, contact Construction Manager Derek Bennett at (541) 609-6111.
As part of the LaSells Stewart Center Mechanical & Roof Renewal project, the northbound lane of SW 26th St. will be closed on Monday, December 18 to allow for crane activity. The closure will extend from SW Western Blvd to SW Washington Way. Flaggers will be present in the area to direct southbound traffic on 26th St.
A section of the east sidewalk on 26th St. will be closed from Western Blvd. to CH2M Hill Alumni Center. Pedestrians may use the west sidewalk as a detour.
PLEASE NOTE: this notification is one of four road closures or construction zones will be impacting travel on 26th St. between Western Blvd. and Orchard Ave. during the period of December 18 – January 5. See locations and dates below:
As part of early construction work related to the Jen-Hsun & Lori Huang Collaborative Innovation Complex project, there will be intermittent flagging operations along SW 26th St. between SW Campus Way and NW Monroe Ave from Wednesday, December 20 through Friday, January 5. Flaggers will direct drivers, bicyclists and pedestrians through the construction zone.
For questions or comments on this closure, contact Construction Manager Jason Lundy at (541) 270-0193.
As part of the Washington Way Improvement project, the north side of the intersection at SW Washington Way and SW 26th Street will be closed from Monday, December 18 – Friday, December 29. A section of 26th St. will be closed between Washington Way and Dixon Recreation Center.
As part of the Jen-Hsun & Lori Huang Collaborative Innovation Complex project, the intersection at SW 26th Street and NW Orchard Avenue will be closed to vehicle traffic on Monday, December 18 and Tuesday, December 19 to allow for construction activity.
The north-south crosswalk on Orchard Ave. will be closed for pedestrians. The sidewalks in the area will remain open, except for a section of sidewalk on the east side of the intersection, directly in front of Johnson Hall. The loading dock north of Johnson Hall will be closed except for pre-arranged deliveries. The concrete walkway on the south side of Johnson Hall will also be closed.
Bike lanes in the area will be closed.
For questions or comments on this closure, contact Construction Manager Jason Lundy at (541) 270-0193.
As part of the Washington Way Improvement project, SW Washington Way will be closed between SW 15th and SW 17th Streets on Friday, December 15 to allow for pavement striping. The intersections at SW 17th and SW Benton Place will be closed to all vehicle and pedestrian traffic.
The north sidewalk on Washington Way will be closed. The multi-use path on the south side of Washington Way will remain open for pedestrians.
Washington Way remains closed between 17th and 26th Streets under a previous notification.
For questions or comments on this closure, contact Project Manager Aaron Amoth at (541) 207-5084.
As part of the Washington Way Improvement project, SW Washington Way between SW 17th & SW 26th Streets will remain closed through Friday, January 5.
In addition to the road closure, the sidewalk on the north side of Washington Way between 17th & 26th Streets will be closed. Pedestrians may use the multi-use path on the south side of Washington Way as a detour.
For questions or comments on this closure, contact Project Manager Aaron Amoth at (541) 207-5084.
As part of the Pride Center Renovation project, a section of SW May Ave. will be closed on Wednesday, December 13 and Thursday, December 14 from 7:30 A.M. to 3:30 P.M. on both days. The closed section will be located directly behind the Pride Center. In addition, several parking spaces bordering SW May Ave. will also be closed.
Other possible impacts include mud near the work site.
For questions or comments on this closure, contact Construction Manager Scylise Little.