Primary construction activities for the week of 03/23 thru 03/27 will consist of the following:
| * = Activity delayed |
- ROOFING
 - Lab High Roof East:
- Continue Installing Roof*
 
 
- INTERIOR BUILDOUT
 - Lab Wing – Level 1 – Commons Spaces,
Café, & Fireplace:
- Continue Installing Tile and Grout at Fireplace
 
 
- Common Spaces All Levels – Stair Three
Finish Work:
- Fab Wood Panels
 
 
- Commons Wing – Level 1 – Bathrooms &
A/V Hard Lid Rooms:
- Finish Installing Toilet Accessories*
 
- Andersen Punch
 
- Complete Punch
 
 
- Lab
Wing – Level 1 – Bathrooms and Hard Lid
Rooms:
- Install Grab Rails and Toilet Partitions*
 
- Start Installing Toilet Accessories
 
- Andersen Punch
 
- Complete Punch
 
 
- Lab Wing – Level 2 – Bathrooms and Hard Lid Rooms:
- Install Grab Rails and Toilet Partitions
 
- Install Toilet Accessories
 
 
- Lab
Wing – Level 3 – Bathrooms and Hard Lid
Rooms:
- Paint
 
- Install Tile
 
 
- Commons Wing – Auditorium:
- Finish Electrical in Stair Framing
 
 
- Commons Wing – Innovation Lab:
- Install Lights and MEP Finishes
 
- Install Wood Paneling
 
- Andersen Punch
 
 
- Commons Wing – Level 2 – Design 3D &
Art Studio:
- No Activities this Upcoming Week.
 
 
- Commons Wing – Level 2 – Sound Control
& Vestibules:
- No Activities this Upcoming Week.
 
 
- Commons Wing – Level 2 – Perforated
Drywall Sound Control:
- Install Expansion Joints
 
 
- Lab
Wing – Level 1 – Classrooms:
- Install Base
 
- Install Finish MEP
 
 
- Lab
Wing – Level 2 – Common Spaces:
- No Activities this Upcoming Week.
 
 
- Lab
Wing – Level 2 – Lab Area:
- Install Balance of Tiles and Clouds
 
 
- Lab
Wing – Level 2 – Offices and Conference
Rooms:
- Continue Installing Windowsills and Casework*
 
 
- Lab Wing – Level 3 Rough-in – Orange South:
- No Activities this Upcoming Week.
 
 
- Lab Wing – Level 3 Rough-in – Blue Northeast:
- No Activities this Upcoming Week.
 
 
- Lab Wing – Level 3 Rough-in – Green Northwest:
- No activities this upcoming week.
 
 
- Lab Wing – Level 3 Rough-in – Purple Core
Area Labs:
- No Activities this Upcoming Week.
 
 
- Common Spaces – Level 3
- Continue Installing Carpet
 
- Install Base
 
 
- Lab Wing – Level 3
- Start Installing Rubber Flooring
 
 
- Offices and Conference Rooms – Level 3
- Finish Installing Windowsills and Casework
 
- Install Ceiling Tiles
 
 
- Roof Level – East Penthouse, Lobby and
Staging
- Stuff and Spray Top of Wall
 
- Install Ceiling OTS Insulation
 
- Paint Room
 
 
- INTERIOR BUILDOUT
 - Elevator 1:
- Continue Workman’s Service Use
 
 
- Elevator 2:
- Continue Installing elevator
 
 
- Stair 1:
- No activities this week.
 
 
- Stair 2:
- No Activities this Upcoming Week.
 
 
- Stair 4:
- No Activities this Upcoming Week.
 
 
- SITE IMPROVEMENTS
 - Phase 3 West Site Improvements:
- Continue Installing Plants
 
- Start Seeding Areas