Primary construction activities for the week of 10/01 thru 10/05 will consist of the following:

Excavation for footings, forming for footings begins this week, backfilling and landscaping at ODFW with completion of fiber work, shut down to tie new water lines.

Asphalt patching between ODFW and West Wing will also take place this week.

Two waterline shutdowns Friday 10/5/2018:

First, Guin Library line- 7:00am to 9:00am

Second, Housing and Dining line- 1:00pm to 3:00pm

Primary construction activities for the week of 9/17 thru 9/21 will consist of the following:

JAFEC and the Deep Soil Mixing equipment, will be demobilized 09/19.

Fiber work to ODF&W scheduled for 09/20 – 09/26, Access on foot path closed between OF&W and Ship Ops.

New water service work scheduled for 09/17, Ferry Slip Road will be closed for deliveries.

Coring in Lab Wing finished 09/19.

Attached is an up to date schedule for the project.

MSIB CC 2018.09.16

Primary construction activities for this week will include:

Deep Soil Mixing test panels to begin Tuesday transitioning into production panels by the end of the week

Vac-excavation and trenching near Guinn Librar for fiber optic lines to vault to take place starting Monday. This will impact East access road between project and Guinn Library.