Primary construction activities for this week will include:

Deep Soil Mixing test panels to begin Tuesday transitioning into production panels by the end of the week

Vac-excavation and trenching near Guinn Librar for fiber optic lines to vault to take place starting Monday. This will impact East access road between project and Guinn Library.