Primary construction activities for the week of 01/13 thru 01/17 will consist of the following:  

|   * = Activity delayed    |

  • ROOFING
  • Penthouse Framing and Sheathing:
    • Start installing electrical in soffit
    • Finish framing soffit
  • CANOPIESWest Canopy V0102:Installing soffit and wall panels
  • INTERIOR BUILDOUT
  • Lab Wing –  Level 2 – Bathrooms and Hard Lid Rooms:
    • Finish installing tiling
  • Commons Wing – Level 1 – Bathrooms & A/V Hard Lid Rooms:
    • Start gyping walls and lids
  • Lab Wing –  Level 1 – Bathrooms and Hard Lid Rooms:
    • Start gyping walls and lids
  • Lab Wing –  Level 3 – Bathrooms and Hard Lid Rooms:
    • Installing top out and fire tape
  • Commons Wing – Auditorium:
    • Continue installing electrical
  • Commons Wing – Innovation Lab:
    • Finish installing MEP in ACT ceiling *
    • Inspecting MEP in ACT ceiling
    • Start installing ACT tiles
    • Start installing Gantry Crane
  • Commons Wing – Level 2 – Design 3D & Art Studio:
    • Installing base *
    • Installing finish electrical *
    • Andersen Punch
  • Lab Wing – Level 1 – Commons Spaces, Café, & Fireplace:
    • Gyping all remaining walls at Café and VEST V0102 ceilings
    • Start finishing walls
  • Lab Wing – Level 2 – Rough-in:
    • Continue installing cable tray at OTS and Commons
  • Lab Wing – Level 2 – Commons Spaces:
    • Installing casework and windowsills *
    • Start installing carpet *
    • Start installing base
  • Lab Wing – Level 2 – Labs:
    • Finishing overhead electrical in Lab Area
    • Finish applying moisture mitigation
  • Lab Wing –  Level 2 – Offices and Conference Rooms:
    • Finishing MEP in grid *
  • Lab Wing –  Level 3 Rough-in – South:
    • Finish installing mechanical hangers, seismic, and piping – then test
    • Start insulating mechanical
  • Lab Wing –  Level 3 Rough-in – East:
    • Finish painting
    • Start installing mechanical hangers, seismic, and piping
  • Lab Wing –  Level 3 Rough-in – West:
    • Finish taping and finishing gyp
    • Start painting
  • Lab Wing –  Level 3 Rough-in – Core Area Labs:
    • Finish installing backing and gyp
    • Start taping and finish gyp
  • Lab Wing –  Level 3 Rough-in – Commons Spaces
    • Continue polishing floors
  • Roof – West Penthouse ELEV Equip Room:
  • Finish installing shaft frame, gyp, and finish
  • Start installing disconnects
  • Roof – East Penthouse Stor, Elev Lobby & Staging:
    • Start framing walls
  • INTERIOR BUILDOUT
  • Elevator 2:
    • Continue installing elevator
  • Stair 1:
    • Start cleaning and patching walls and landings *
  • Stair 3:
    • Installing precast treads
  • Stair 4:
    • Installing down rods and landings
    • Installing treads and risers

Primary construction activities for the week of 01/06 thru 01/10 will consist of the following:  

|   * = Activity delayed    |

  • ROOFING
  • Penthouse Framing and Sheathing:
    • Continue framing soffit
  • CANOPIESWest Canopy V0102:Start installing roof panels
  • WINDOWS & SIDING
  • Commons Wing – East Elevation:
    • Finish installing beauty cap and flashing
  • Commons Wing – North Elevation:
    • Installing beauty cap and flashing
  • Commons Wing – South Elevation:
    • Installing beauty cap and flashing
  • Commons Wing – West Elevation:
    • Installing beauty cap and flashing
  • INTERIOR BUILDOUT
  • Lab Wing –  Level 2 – Bathrooms and Hard Lid Rooms:
    • Start installing tiling
  • Commons Wing – Level 1 – Bathrooms & A/V Hard Lid Rooms:
    • Finish grinding floors
    • Installing floor protection
  • Lab Wing –  Level 1 – Bathrooms and Hard Lid Rooms:
    • Finish installing MEP in hard lids
    • MEP inspection for hard lids
  • Lab Wing –  Level 3 – Bathrooms and Hard Lid Rooms:
    • Finish framing hard lids
    • Start installing MEP in hard lids
  • Commons Wing – Auditorium:
    • Start installing electrical *
    • Balance of walls pushed out to 1st week of February
  • Commons Wing – Innovation Lab:
    • Finish installing MEP in ACT ceiling *
  • Commons Wing – Level 2 – Design 3D & Art Studio:
    • Finish installing MEP in ceilings and inspection for MEP ceilings *
    • Installing ceiling tiles *
    • Installing base
    • Installing electrical *
  • Commons Wing – Level 2 – Sound Control and Vestibules:
    • Finish installing lids and walls
    • Start painting
  • Lab Wing – Level 1 – Mechanical & Back of House:
  • Finish installing panels and feeders in electric rooms *
  • Finish all MEP in 1st floor mechanical spaces *
  • Lab Wing – Level 1 – Commons Spaces, Café, & Fireplace:
    • Grinding floors
    • Framing hard lid at Café and VEST V0102
    • Finishing MEP in hard lids at Café and VEST V0102
  • Lab Wing – Level 2 – Rough-in:
    • Continue installing cable tray at OTS and Commons
  • Lab Wing – Level 2 – Commons Spaces:
    • Installing casework and windowsills
    • Start installing carpet
  • Lab Wing – Level 2 – Labs:
    • Finishing overhead electrical in Lab Area
    • Continue applying moisture mitigation
  • Lab Wing –  Level 2 – Offices and Conference Rooms:
    • Continue finishing MEP in grid *
  • Lab Wing –  Level 3 Rough-in – South:
    • Start installing mechanical hangers, seismic, and piping
  • Lab Wing –  Level 3 Rough-in – East:
    • Finish taping and finishing gyp
    • Start paint
  • Lab Wing –  Level 3 Rough-in – West:
    • Start taping and finishing gyp
  • Lab Wing –  Level 3 Rough-in – Core Area Labs:
    • Start installing backing and gyp
  • Lab Wing –  Level 3 Rough-in – Core Area Labs:
    • Start polishing floors
  • Roof – West Penthouse ELEV Equip Room:
  • Continue installing shaft frame, gyp, and finish
  • Installing disconnects and elevator equipment pushed out until 01/14
  • INTERIOR BUILDOUT
  • Elevator 2:
    • Continue installing elevator
  • Stair 1:
    • Start cleaning and patching walls and landings *
  • Stair 3:
    • Installing stair stringers and risers

Primary construction activities for the week of 12/23 thru 12/27 will consist of the following:  

|   * = Activity delayed    |

  • ROOFING
  • Penthouse Framing and Sheathing:
    • Continue framing soffit
    • Installing electrical in soffit start delayed to after New Year
  • CANOPIESCommons Wing Soffit: Finish installing trim and metal soffit panels
  • WINDOWS & SIDING
  • Commons Wing – South Elevation:
    • Continue installing siding
  • Commons Wing – West Elevation:
    • Finish installing beauty cap and flashing
  • INTERIOR BUILDOUT
  • Commons Wing – Level 1 – Bathrooms & A/V Hard Lid Rooms:
    • Finish install electrical in hard lids *
    • MEP inspection for hard lids *
    • Start gyping walls and lids *
  • Lab Wing –  Level 1 – Bathrooms and Hard Lid Rooms Labs:
    • Finish installing electrical in hard lids
  • Lab Wing –  Level 3 – Bathrooms and Hard Lid Rooms Labs:
    • Start installing electrical in hard lids
  • Commons Wing – Auditorium:
    • Finish installing electrical
    • Start finishing balance of walls
  • Commons Wing – Innovation Lab:
    • Finish installing ACT grid *
    • Start installing electrical in ACT ceiling *
  • Commons Wing – Level 2 – Design 3D & Art Studio:
    • Finish installing ACT tiles
    • Finish installing electrical
  • Commons Wing – Level 2 – Sound Control and Vestibules:
    • Finish installing lids and walls
    • Start painting
  • Lab Wing – Level 1 – Mechanical & Back of House:
  • Finish installing panels and feeders in electric rooms *
  • Lab Wing – Level 1 – Commons Spaces, Café, & Fireplace:
    • Finish installing wall electrical
    • Framing hard lid at Café and VEST V0102
    • Start finishing MEP in hard lids at Café and VEST V0102
  • Lab Wing – Level 2 – Rough-in:
    • Continue installing cable tray at OTS and Commons *
  • Lab Wing – Level 2 – Labs:
    • Finishing overhead electrical in Lab Area
  • Lab Wing –  Level 2 – Offices and Conference Rooms:
    • Continue finishing MEP in grid *
  • Lab Wing –  Level 3 Rough-in – South:
    • Finish taping and finishing gyp
    • Painting
  • Lab Wing –  Level 3 Rough-in – East:
    • Start taping and finishing gyp
  • Lab Wing –  Level 3 Rough-in – West:
    • Start installing backing and gyp
  • Lab Wing –  Level 3 Rough-in – Core Area Labs:
    • Installing wall electrical rough-in
  • Roof – West Penthouse ELEV Equip Room:
  • Continue installing shaft frame, gyp, and finish
  • Installing disconnects and elevator equipment delayed until after the New Year *
  • Lab Wing –  Elevator 2:
    • Continue installing elevator
  • Lab Wing – Stair 1:
    • Start cleaning and patching walls and landings

Primary construction activities for the week of 12/16 thru 12/20 will consist of the following:  

|   * = Activity delayed    |

  • ROOFING
  • Penthouse Framing and Sheathing:
    • Installing electrical in soffit
  • CANOPIESCommons Wing Soffit:Continue installing trim and metal soffit panels
  • Lab Wing Soffit:Finish installing trim and wood soffit
  • WINDOWS & SIDING
  • Auditorium – South Elevation:
    • Finishing siding
  • INTERIOR BUILD-OUT
  • Commons Wing – Auditorium:
    • Start finishing balance of walls
  • Commons Wing – Innovation Lab:
    • Installing MEP in ACT ceilings
  • Commons Wing – Level 1 – Bathrooms & A/V Hard Lid Rooms:
    • Finish gyping walls and lids
    • Start finishing gyp
  • Commons Wing – Level 2 – Design 3D & Art Studio:
    • Installing ceiling tiles and finishing electrical
  • Commons Wing – Level 2 – Sound Control and Vestibules:
    • Installing MEP in Sound Control ceiling
    • Inspecting MEP in Sound Control ceiling
    • Start installing ACT tiles
  • Lab Wing – Level 1 – Mechanical & Back of House:
  • Finish installing panels and feeders in electric rooms
  • Lab Wing – Level 1 – Commons Spaces (Café & Fireplace):
    • Installing wall electrical
    • Starting gyp and spray of top out for duct work
  • Lab Wing –  Level 1 – Bathrooms and Hard Lid Rooms:
    • Finish gyping walls and lids
    • Start finishing gyp
  • Lab Wing –  Level 1 – Classrooms:
    • Start finishing walls
  • Lab Wing – Level 2 – Rough-in:
    • Finish installing cable tray at OTS and Commons
  • Lab Wing – Level 2 – Labs:
    • Installing grid and necessary tiles
  • Lab Wing –  Level 2 – Offices and Conference Rooms:
    • MEP cover inspection
    • Installing ceiling tiles
  • Lab Wing –  Level 3 Rough-in:
    • Finish gyping North walls
    • Finish installing electrical on North and West
    • Continue installing MEP in OTS, offices, and SE area
    • Start finishing walls, OTS insulation, and TOW in North area
    • Start gyping North and West walls
  • Roof – West Penthouse ELEV Equip Room:
  • Finish installing disconnects
  • Start installing elevator equipment
  • Roof – East Penthouse Storage, ELEV Lobby, & Staging:
    • Start framing walls

Primary construction activities for the week of 12/09 thru 12/13 will consist of the following:  

|   * = Activity delayed    |

  • ROOFING
  • Penthouse Framing and Sheathing:
    • Continue framing soffit
  • CANOPIESWest Canopy V102:Finish installing electrical and gyping lids *Installing WRB
  • Commons Wing Soffit:Continue installing trim and metal soffit panels
  • Lab Wing Soffit:Continue installing trim and wood soffit
  • WINDOWS & SIDING
  • Auditorium – South Elevation:
    • Continue finishing siding *
  • INTERIOR BUILDOUT
  • Commons Wing – Auditorium:
    • Start installing electrical
  • Commons Wing – Innovation Lab:
    • Painting
    • Installing ACT grid
  • Commons Wing – Level 1 – Bathrooms & A/V Hard Lid Rooms:
    • Finish installing MEP in hard lids
    • MEP inspection
    • Start gyping walls and lids
  • Commons Wing – Level 2 – Design 3D & Art Studio:
    • Installing ceiling grid and MEP in ceilings
    • Inspection for MEP in ceilings
  • Commons Wing – Level 2 – Sound Control and Vestibules:
    • Finishing lids and walls
    • Painting and installing ceiling grid in Sound Control
  • Lab Wing – Level 1 – Mechanical & Back of House:
  • Continue installing panels and feeders in electric rooms
  • Lab Wing – Level 1 – Commons Spaces (Café & Fireplace):
    • Installing transformer and panels
    • Start grinding floors and install electrical in walls
  • Lab Wing –  Level 1 – Bathrooms and Hard Lid Rooms:
    • Finish installing MEP at hard lids *
    • MEP inspection for hard lids *
    • Start gyping walls and lids
  • Lab Wing – Level 2 – Rough-in:
    • Continue installing cable tray at OTS and Commons
  • Lab Wing – Level 2 – Commons Spaces:
    • Installing casework and windowsills
  • Lab Wing – Level 2 – Labs:
    • Finish overhead electrical in lab area
    • Completing floor moisture mitigation
  • Lab Wing –  Level 2 – Offices and Conference Rooms:
    • Finishing MEP in grid
  • Lab Wing –  Level 3 Rough-in:
    • Gyping South and East walls
    • Finishing walls, OTS insulation, and top-of-wall at SE area
    • Start gyping North walls
    • Installing electrical on North and West
    • Start installing MEP in OTS, offices, and SE area
  • Roof – West Penthouse ELEV Equip Room:
  • Finish installing shaft frame, gyp, and finish *
  • Start installing disconnects

Primary construction activities for the week of 11/25 thru 11/29 will consist of the following:  

|   * = Activity delayed    |

  • ROOFING
  • Penthouse Framing and Sheathing:
    • Continue framing soffit *
    • Continue installing metal siding
  • CANOPIES West Canopy V102:Finish installing electrical and gyping lids *WRB start delayed
  • Commons Wing Soffit:Continue installing trim and metal soffit panels
  • Lab Wing Soffit:Start installing trim and metal soffit panels *
  • WINDOWS & SIDING
  • Auditorium – East Elevation:
    • Installing beauty cap and flashing
  • Auditorium – North Elevation:
    • Continue finishing siding in Armpit
  • Auditorium – South Elevation:
    • Continue finishing siding
  • INTERIOR BUILDOUT
  • Commons Wing – Level 1 – Rough-in:
  • Finish MEP in walls
  • Finish installing balance of drywall
  • Continue installing MEP in 1st floor corridors *
  • Start installing 1.5” metal deck *
  • Commons Wing – Level 2 – Sound Control and Vestibules:
    • Continue finishing lids and walls *
  • Lab Wing – Level 1 – Rough-in:
  • Continue installing overhead MEP work in OTS
  • Lab Wing – Level 1 – Commons Spaces:
    • Finish installing MEP in fireplace cavity *
    • Starting gyping walls *
  • Lab Wing –  Level 1 – Bathrooms and Hard Lid Rooms:
    • Finish installing MEP at hard lids *
    • MEP inspection for hard lids
  • Lab Wing –  Level 2 – Rough-in:
    • Continue installing cable tray at OTS and Commons
  • Lab Wing –  Level 2 – Offices and Conference Rooms:
    • Continue finishing MEP in grid
  • Lab Wing –  Level 2 – Commons Spaces:
    • Finish polishing floors
  • Lab Wing –  Level 2 – Bathrooms and Hard Lid Rooms:
    • Grinding floors
  • Lab Wing –  Level 3 Rough-in:
    • Finish installing gyp top-out at Donut
    • Start completing balance of MEP in walls
  • Roof – West Penthouse ELEV Equip Room:
  • Finish installing shaft frame, gyp, and finish *
  • Disconnects install delayed
  • Elevator 2:
    • Continue installing elevator

Primary construction activities for the week of 11/18 thru 11/22 will consist of the following:  

|   * = Start or Finish was delayed    |   ** Activity taking longer than projected   |

  • ROOFING
  • Low Roof Auditorium:
  • Penthouse Framing and Sheathing:
    • Finish framing soffit
    • Continue installing metal siding
  • CANOPIESEast Canopy V103:Finish installing frames and glass **
  • South Canopy V101:Finish installing frames and glass **
  • West Canopy V102:Finish installing electrical and gyping lidsFinish installing WRB *
  • Commons Wing Soffit:Continue installing trim and metal soffit panels
  • Lab Wing Soffit:Start installing trim and metal soffit panels *
  • WINDOWS & SIDING
  • Auditorium – South Elevation:
    • Continue finishing siding after soffit is complete
  • Auditorium – West Elevation:
    • Installing beauty cap and flashing
  • Auditorium – North Elevation:
    • Finish installing glass and pressure bar
    • Start installing beauty cap and flashing *
  • Auditorium – East Elevation:
    • Finish finishing siding *
  • INTERIOR BUILDOUT
  • Commons Wing – Level 1 – Rough-in:
  • Finish installing MEP in 1st floor corridors *
  • Start installing 1.5” metal deck *
  • Commons Wing – Level 2 – Designs 3D & Art Studio:
    • Start installing MEP in ceiling, inspecting MEP in ceilings, and installing ceiling tiles *
  • Commons Wing – Level 2 – Sound Control and Vestibules:
    • Finish finishing lids and walls *
  • Lab Wing – Level 1 – Rough-in:
  • Finish painting top out and OTS **
  • Start installing overhead MEP work in OTS *
  • Lab Wing – Level 1 – Commons Spaces:
    • Finish installing fireplace and MEP in fireplace cavity **
    • Starting gyping walls *
  • Lab Wing –  Level 1 – Bathrooms and Hard Lid Rooms:
    • Finish framing hard lids **
    • Start installing MEP at hard lids *
  • Lab Wing –  Level 2 – Rough-in:
    • Continue installing cable tray at OTS and Commons
  • Lab Wing –  Level 2 – Offices and Conference Rooms:
    • Start finishing MEP in grid *
  • Lab Wing –  Level 2 – Bathrooms and Hard Lid Rooms:
    • Finish finishing gyp *
    • Painting
  • Lab Wing –  Level 3 Rough-in:
    • Finish installing MEP in walls at Doughnut
  • Roof – West Penthouse ELEV Equip Room:
  • Finish installing shaft frame, gyp, and finish *
  • Start installing disconnects *
  • Elevator 2:
    • Continue installing elevator

Primary construction activities for the week of 11/11 thru 11/15 will consist of the following:  

|   * = Start or Finish was delayed    |   ** Activity taking longer than projected   |

  • ROOFING
  • Low Roof Auditorium:
  • Penthouse Framing and Sheathing:
    • Continue framing soffit *
    • Start installing metal siding
  • CANOPIESEast Canopy V103:Installing frames and glass
  • South Canopy V101:Installing frames and glass
  • West Canopy V102:Installing electrical and gyping lidsFinish installing WRB *
  • Commons Wing Soffit:Continue installing trim and metal soffit panels
  • Lab Wing Soffit:Start installing trim and metal soffit panels
  • WINDOWS & SIDING
  • Auditorium – South Elevation:
    • Continue finishing siding after soffit is complete
  • Auditorium – West Elevation:
    • Finish installing vertical siding MWC
  • Auditorium – North Elevation:
    • Installing glass and pressure bar
    • Start installing beauty cap and flashing *
  • Auditorium – East Elevation:
    • Continue finishing siding *
  • INTERIOR BUILDOUT
  • Commons Wing – Level 1 – Rough-in:
  • Finish installing MEP in 1st floor corridors
  • Start installing 1.5” metal deck
  • Commons Wing – Level 2 – Designs 3D & Art Studio:
    • Start installing MEP in ceiling, inspecting MEP in ceilings, and installing ceiling tiles
  • Commons Wing – Level 2 – Sound Control and Vestibules:
    • Finishing lids and walls
  • Lab Wing – Level 1 – Rough-in:
  • Start installing overhead MEP work in OTS *
  • Painting top out and OTS
  • Lab Wing – Level 1 – Commons Spaces:
    • Installing fireplace and MEP in fireplace cavity
    • Starting gyping walls
  • Lab Wing –  Level 1 – Bathrooms and Hard Lid Rooms:
    • Framing hard lids
    • Start installing MEP at hard lids
  • Lab Wing –  Level 2 – Rough-in:
    • Continue installing cable tray at OTS and Commons
  • Lab Wing –  Level 2 – Offices and Conference Rooms:
    • Continue finishing MEP in grid
  • Lab Wing –  Level 2 – Bathrooms and Hard Lid Rooms:
    • Start finishing gyp *
  • Lab Wing –  Level 3 Rough-in:
    • Continue installing MEP in walls at Doughnut
  • Roof – West Penthouse ELEV Equip Room:
  • Installing disconnects *
  • Finish installing shaft frame, gyp, and finish
  • Elevator 2:
    • Continue installing elevator

Primary construction activities for the week of 11/04 thru 11/08 will consist of the following:  

|   * = Start or Finish was delayed    |   ** Activity taking longer than projected   |

  • ROOFING
  • High Roof Auditorium:
  • Penthouse Framing and Sheathing:
    • Finish installing Z girts, insulation, and hat channels
    • Finish framing soffit
  • CANOPIESWest Canopy V102:Finish installing WRBStart installing frames and glass
  • Commons Wing Soffit:Finish installing hat channelStart installing trim and metal soffit panels
  • Lab Wing Soffit:Start painting vent in soffit and installing hat channel
  • WINDOWS & SIDING
  • Auditorium – South Elevation:
    • Start finishing siding after soffit is complete
  • Auditorium – West Elevation:
    • Installing beauty cap and flashing
  • Auditorium – North Elevation:
    • Finish installing beauty cap and flashing
  • Auditorium – East Elevation:
    • Finish siding
  • INTERIOR BUILDOUT
  • Commons Wing – Level 1 – Rough-in:
  • Installing scaffolding for MEPFP in Auditorium high ceiling *
  • Finish installing top for MEP to begin on 1st floor
  • Start installing MEPFP in Auditorium High Ceiling
  • Start installing MEP in 1st floor corridors
  • Commons Wing – Level 2 – Designs 3D & Art Studio:
    • Finishing drywall *
    • Painting
  • Commons Wing – Level 2 – Sound Control and Vestibules:
    • Finish installing MEP at hard lids
    • Installing gyp at lids and walls (contingent on passing hard lid inspection)
    • Start finishing lids and walls
  • Lab Wing – Level 1 – Rough-in:
  • Start installing overhead MEP work in OTS
  • Lab Wing –  Level 2 – Rough-in:
    • Continue installing cable tray at OTS and Commons
  • Lab Wing –  Level 2 – Offices and Conference Rooms:
    • Start finishing MEP in grid
  • Lab Wing –  Level 2 – Bathrooms and Hard Lid Rooms
    • Installing gyp at lids and walls
    • Start finishing gyp
  • Lab Wing –  Level 3 Rough-in:
    • Finish installing MEP in Labs overhead
    • Finish framing walls at E/3 then clockwise
    • Finish installing MEP in walls at Doughnut
    • Start topping out gyp at Doughnut
  • Roof – West Penthouse ELEV Equip Room:
  • Installing disconnects
  • Start installing elevator equipment
  • Elevator 2:
    • Start installing elevator

Primary construction activities for the week of 10/28 thru 11/01 will consist of the following:  

|   * = Start or Finish was delayed    |   ** Activity taking longer than projected   |

  • ROOFING
  • High Roof Auditorium:
  • Penthouse Framing and Sheathing:
    • Continue Z girts, insulation, and hat channels
    • Start framing soffit
  • CANOPIESEast Canopy V103:Installing frames and glass
  • South Canopy V101:Installing frames and glass
  • West Canopy V102:Finish framingInstalling electrical, and gyping the lidStart installing WRBCommons Wing Soffit:Painting vent in soffitStart installing hat channelLab Wing Soffit:Installing soffit WRB
  • WINDOWS & SIDING
  • Auditorium – South Elevation:
    • Finish installing glass, pressure bar, and vertical siding MWC
  • Auditorium – West Elevation:
    • Finish installing glass, pressure bar, and siding
  • Auditorium – North Elevation:
    • Finish installing glass and pressure bar
    • Siding in Armpit delayed for concrete to finish
    • Start installing beauty cap and flashing
  • Auditorium – East Elevation:
    • Finish siding, beauty cap, and flashing – delayed for concrete work to finish
  • INTERIOR BUILDOUT
  • Commons Wing – Level 1 – Rough-in:
  • Finish MEP in walls on 1st floor
  • Installing scaffolding for MEPFP in Auditorium high ceiling
  • Start installing top for MEP to begin on 1st floor
  • Commons Wing – Level 2 – Designs 3D & Art Studio:
    • Polishing floors
    • Finishing drywall
  • Commons Wing – Level 2 – Sound Control and Vestibules:
    • Framing hard lids
    • Start installing MEP at hard lids
  • Lab Wing – Level 1 – Rough-in:
  • Finish installing OTS insulation
  • Painting top out and OTS
  • Lab Wing –  Level 2 – Rough-in:
    • Continue installing cable tray at OTS and Commons
  • Lab Wing –  Level 2 – Offices and Conference Rooms:
    • Installing grid *
  • Lab Wing –  Level 2 – Bathrooms and Hard Lid Rooms
    • Finish installing MEP at hard lids *
    • MEP inspection for hard lids
  • Lab Wing –  Level 3 Rough-in:
    • Continue installing MEP in Labs overhead
    • Continue framing walls at E/3 then clockwise
    • Installing MEP in walls at Doughnut
  • Roof – West Penthouse ELEV Equip Room:
  • Finishing shaft framing, gyp, and finish