Primary construction activities for the week of 11/11 thru 11/15 will consist of the following:
| * = Start or Finish was delayed | ** Activity taking longer than projected |
- ROOFING
- Low Roof Auditorium:
- Penthouse Framing and Sheathing:
- Continue framing soffit *
- Start installing metal siding
- CANOPIESEast Canopy V103:Installing frames and glass
- South Canopy V101:Installing frames and glass
- West Canopy V102:Installing electrical and gyping lidsFinish installing WRB *
- Commons Wing Soffit:Continue installing trim and metal soffit panels
- Lab Wing Soffit:Start installing trim and metal soffit panels
- WINDOWS & SIDING
- Auditorium – South Elevation:
- Continue finishing siding after soffit is complete
- Auditorium – West Elevation:
- Finish installing vertical siding MWC
- Auditorium – North Elevation:
- Installing glass and pressure bar
- Start installing beauty cap and flashing *
- Auditorium – East Elevation:
- Continue finishing siding *
- INTERIOR BUILDOUT
- Commons Wing – Level 1 – Rough-in:
- Finish installing MEP in 1st floor corridors
- Start installing 1.5” metal deck
- Commons Wing – Level 2 – Designs 3D
& Art Studio:
- Start installing MEP in ceiling, inspecting MEP in ceilings, and installing ceiling tiles
- Commons Wing – Level 2 – Sound Control
and Vestibules:
- Finishing lids and walls
- Lab Wing – Level 1 – Rough-in:
- Start installing overhead MEP work in OTS *
- Painting top out and OTS
- Lab Wing – Level 1 – Commons Spaces:
- Installing fireplace and MEP in fireplace cavity
- Starting gyping walls
- Lab
Wing – Level 1 – Bathrooms and Hard Lid Rooms:
- Framing hard lids
- Start installing MEP at hard lids
- Lab Wing – Level 2 – Rough-in:
- Continue installing cable tray at OTS and Commons
- Lab
Wing – Level 2 – Offices and Conference Rooms:
- Continue finishing MEP in grid
- Lab
Wing – Level 2 – Bathrooms and Hard Lid Rooms:
- Start finishing gyp *
- Lab Wing – Level 3 Rough-in:
- Continue installing MEP in walls at Doughnut
- Roof – West Penthouse ELEV Equip Room:
- Installing disconnects *
- Finish installing shaft frame, gyp, and finish
- Elevator 2:
- Continue installing elevator