Primary construction activities for the week of 03/23 thru 03/27 will consist of the following:  

|   * = Activity delayed    |

  • ROOFING
  • Lab High Roof East:
    • Continue Installing Roof*
  • INTERIOR BUILDOUT
  • Lab Wing – Level 1 – Commons Spaces, Café, & Fireplace:
    • Continue Installing Tile and Grout at Fireplace
  • Common Spaces All Levels – Stair Three Finish Work:
    • Fab Wood Panels
  • Commons Wing – Level 1 – Bathrooms & A/V Hard Lid Rooms:
    • Finish Installing Toilet Accessories*
    • Andersen Punch
    • Complete Punch
  • Lab Wing – Level 1 – Bathrooms and Hard Lid Rooms:
    • Install Grab Rails and Toilet Partitions*
    • Start Installing Toilet Accessories
    • Andersen Punch
    • Complete Punch
  • Lab Wing – Level 2 – Bathrooms and Hard Lid Rooms:
    • Install Grab Rails and Toilet Partitions
    • Install Toilet Accessories
  • Lab Wing – Level 3 – Bathrooms and Hard Lid Rooms:
    • Paint
    • Install Tile
  • Commons Wing – Auditorium:
    • Finish Electrical in Stair Framing
  • Commons Wing – Innovation Lab:
    • Install Lights and MEP Finishes
    • Install Wood Paneling
    • Andersen Punch
  • Commons Wing – Level 2 – Design 3D & Art Studio:
    • No Activities this Upcoming Week.
  • Commons Wing – Level 2 – Sound Control & Vestibules:
    • No Activities this Upcoming Week.
  • Commons Wing – Level 2 – Perforated Drywall Sound Control:
    • Install Expansion Joints
  • Lab Wing – Level 1 – Classrooms:
    • Install Base
    • Install Finish MEP
  • Lab Wing – Level 2 – Common Spaces:
    • No Activities this Upcoming Week.
  • Lab Wing – Level 2 – Lab Area:
    • Install Balance of Tiles and Clouds
  • Lab Wing – Level 2 – Offices and Conference Rooms:
    • Continue Installing Windowsills and Casework*
  • Lab Wing – Level 3 Rough-in – Orange South:
    • No Activities this Upcoming Week.
  • Lab Wing – Level 3 Rough-in – Blue Northeast:
    • No Activities this Upcoming Week.
  • Lab Wing – Level 3 Rough-in – Green Northwest:
    • No activities this upcoming week.
  • Lab Wing – Level 3 Rough-in – Purple Core Area Labs:
    • No Activities this Upcoming Week.
  • Common Spaces – Level 3
    • Continue Installing Carpet
    • Install Base
  • Lab Wing – Level 3
    • Start Installing Rubber Flooring
  • Offices and Conference Rooms – Level 3
    • Finish Installing Windowsills and Casework
    • Install Ceiling Tiles
  • Roof Level – East Penthouse, Lobby and Staging
    • Stuff and Spray Top of Wall
    • Install Ceiling OTS Insulation
    • Paint Room
  • INTERIOR BUILDOUT
  • Elevator 1:
    • Continue Workman’s Service Use
  • Elevator 2:
    • Continue Installing elevator
  • Stair 1:
    • No activities this week.
  • Stair 2:
    • No Activities this Upcoming Week.
  • Stair 4:
    • No Activities this Upcoming Week.
  • SITE IMPROVEMENTS
  • Phase 3 West Site Improvements:
    • Continue Installing Plants
    • Start Seeding Areas

Primary construction activities for the week of 03/16 thru 03/20 will consist of the following:  

|   * = Activity delayed    |

  • ROOFING
  • Penthouse Framing and Sheathing:
    • Continue Installing Metal Siding
    • Finish Installing Z Girt Insulation and Hat Channels*
  • Lab High Roof East:
    • Start Installing Roof*
  • INTERIOR BUILDOUT
  • Lab Wing – Level 1 – Commons Spaces, Café, & Fireplace:
    • Continue Installing Tile and Grout at Fireplace
  • Common Spaces All Levels – Stair Three Finish Work:
    • Fab Wood Panels
  • Commons Wing – Level 1 – Bathrooms & A/V Hard Lid Rooms:
    • Install Electrical Trim Out
    • Install Grab Rails and Toilet Partitions*
    • Install Toilet Accessories*
  • Lab Wing – Level 1 – Bathrooms and Hard Lid Rooms:
    • Install Grab Rails and Toilet Partitions*
    • Start Installing Toilet Accessories
  • Lab Wing – Level 2 – Bathrooms and Hard Lid Rooms:
    • No activities this upcoming week.
  • Lab Wing – Level 3 – Bathrooms and Hard Lid Rooms:
    • Finishing Gyp
  • Commons Wing – Auditorium:
    • Finishing Seat Framing
  • Commons Wing – Innovation Lab:
    • Install Crane
  • Commons Wing – Level 2 – Design 3D & Art Studio:
    • Correct Andersen Punch*
  • Commons Wing – Level 2 – Sound Control & Vestibules:
    • No activities this upcoming week.
  • Commons Wing – Level 2 – Perforated Drywall Sound Control:
    • Finish Perforated Drywall*
  • Lab Wing – Level 1 – Classrooms:
    • Start Installing Casework Fume Hoods and Counter tops*
  • Lab Wing – Level 2 – Common Spaces:
    • Finish Installing Ceiling and Sound Baffles
  • Lab Wing – Level 2 – Lab Area:
    • Install Grid and Necessary Tiles*
  • Lab Wing – Level 2 – Offices and Conference Rooms:
    • Start Installing Windowsills and Casework*
  • Lab Wing – Level 3 Rough-in – Orange South:
    • Finish Pipe ID*
  • Lab Wing – Level 3 Rough-in – Blue Northeast:
    • Finish Pipe ID
  • Lab Wing – Level 3 Rough-in – Green Northwest:
    • No activities this upcoming week.
  • Lab Wing – Level 3 Rough-in – Purple Core Area Labs:
    • Finish Pipe ID
  • Common Spaces – Level 3
    • Install Casework and Windowsills
    • Start Installing Carpet
  • Lab Wing – Level 3
    • Install Grid and Necessary Tiles
  • Offices and Conference Rooms – Level 3
    • Continue Installing Door Frames
    • Finish MEP in Grid
    • Install Windowsills and Casework
  • Roof Level – East Penthouse, Lobby and Staging
    • Continue Finishing Gyp
  • INTERIOR BUILDOUT
  • Elevator 1:
    • Continue Workman’s Service Use
  • Elevator 2:
    • Continue Installing elevator
  • Stair 1:
    • No activities this week.
  • Stair 2:
    • Paint Walls Lower Landings.
  • Stair 4:
    • Reinstall Handrail at Siding.
  • SITE IMPROVEMENTS
  • Phase 3 West Site Improvements:
    • Install Plants

Primary construction activities for the week of 03/09 thru 03/13 will consist of the following:  

|   * = Activity delayed    |

  • ROOFING
  • Penthouse Framing and Sheathing:
    • Continue Installing Metal Siding
    • Continue Installing Soffit Standing Seam
    • Finish Installing Z Girt Insulation and Hat Channels*
  • Lab High Roof East:
    • Start Installing Roof*
  • INTERIOR BUILDOUT
  • Lab Wing – Level 1 – Commons Spaces, Café, & Fireplace:
    • Finish Installing Countertops in Café*
    • Install Finish MEP*
    • Install Tile and Grout at Fireplace*
  • Common Spaces All Levels – Stair Three Finish Work:
    • Fab Wood Panels
  • Commons Wing – Level 1 – Bathrooms & A/V Hard Lid Rooms:
    • Install Grab Rails and Toilet Partitions*
    • Install Toilet Accessories*
    • Andersen Punch
  • Lab Wing – Level 1 – Bathrooms and Hard Lid Rooms:
    • Install Grab Rails and Toilet Partitions*
    • Start Installing Toilet Accessories
  • Lab Wing – Level 2 – Bathrooms and Hard Lid Rooms:
    • Start Installing Grab Rails and Toilet Partitions
  • Lab Wing – Level 3 – Bathrooms and Hard Lid Rooms:
    • Continue Finishing Gyp
    • Install Tile
    • Install Counters
    • Start Painting
    • Start Installing Plumbing Trim Out
  • Commons Wing – Auditorium:
    • Continue Finishing Seat Framing
  • Commons Wing – Innovation Lab:
    • Install ACT Tiles
  • Commons Wing – Level 2 – Design 3D & Art Studio:
    • Correct Andersen Punch*

Commons Wing – Level 2 – Sound Control & Vestibules:

  • No activities this upcoming week.
  • Commons Wing – Level 2 – Perforated Drywall Sound Control:
    • Finish Perforated Drywall*
  • Lab Wing – Level 1 – Classrooms:
    • Finish Installing MEP in Ceiling
    • Inspect MEP in Ceiling
    • Start Installing Casework Fume Hoods and Countertops
  • Lab Wing – Level 2 – Common Spaces:
    • Install Ceiling and Sound Baffles
  • Lab Wing – Level 2 – Lab Area:
    • Install Grid and Necessary Tiles
    • Install Base
  • Lab Wing – Level 2 – Offices and Conference Rooms:
    • Start Installing Windowsills and Casework*
  • Lab Wing – Level 3 Rough-in – Orange South:
    • Finish Painting MEPFP in OTS*
    • Start Pipe ID*
  • Lab Wing – Level 3 Rough-in – Blue Northeast:
    • Finish Painting MEPFP in OTS*
    • Start Pipe ID*
  • Lab Wing – Level 3 Rough-in – Green Northwest:
    • Finish Electrical in OTS*
    • Paint MEPFP in OTS*
  • Lab Wing – Level 3 Rough-in – Purple Core Area Labs:
    • Start Electrical in OTS
    • Continue Insulating*
  • Common Spaces – Level 3
    • Continue Polish Floors*
  • Roof Level – East Penthouse, Lobby and Staging
    • Install Gyp
    • Start Finishing Gyp
  • INTERIOR BUILDOUT
  • Elevator 1:
    • Continue Workman’s Service Use
  • Elevator 2:
    • Continue Installing elevator
  • Stair 1:
    • Paint Rails
  • Stair 2:
    • No activities this week.
  • Stair 4:
    • No activities this week.
  • SITE IMPROVEMENTS
  • Phase 3 West Site Improvements:
    • Install Topsoil
    • Install Plants

Primary construction activities for the week of 03/02 thru 03/06 will consist of the following:  

|   * = Activity delayed    |

  • ROOFING
  • Penthouse Framing and Sheathing:
    • Continue Installing Metal Siding
    • Continue Installing Soffit Standing Seam
    • Finish Installing Z Girt Insulation and Hat Channels
  • Lab High Roof East:
    • Start Installing Roof
  • INTERIOR BUILDOUT
  • Lab Wing – Level 1 – Commons Spaces, Café, & Fireplace:
    • Finish Installing Counter tops in Café
    • Install Finish MEP
  • Common Spaces All Levels – Stair Three Finish Work:
    • Continue Installing Wood Panels*
    • Fab Wood Panels
  • Commons Wing – Level 1 – Bathrooms & A/V Hard Lid Rooms:
    • Install Electrical Trim Out*
    • Install Grab Rails and Toilet Partitions*
    • Start Installing Toilet Accessories
  • Lab Wing – Level 1 – Bathrooms and Hard Lid Rooms:
    • Install Electrical Trim Out
    • Start Grab Rails and Toilet Partitions
  • Lab Wing – Level 2 – Bathrooms and Hard Lid Rooms:
    • No Activities this upcoming Week.
  • Lab Wing – Level 3 – Bathrooms and Hard Lid Rooms:
    • Finish MEP Hard Lids*
    • MEP Inspection for Hard Lids*
    • Start Gyp Walls and Lids
  • Commons Wing – Auditorium:
    • Start Finishing Seat Framing
  • Commons Wing – Innovation Lab:
    • Finish installing ACT tiles*
    • Inspect ACT MEP Ceiling
  • Commons Wing – Level 2 – Design 3D & Art Studio:
    • Install Base
    • Install Finish Electrical
    • Third Coat Delay
    • Andersen Punch
    • Correct Andersen Punch

Commons Wing – Level 2 – Sound Control & Vestibules:

  • No activities this upcoming week.
  • Commons Wing – Level 2 – Perforated Drywall Sound Control:
    • Finish Perforated Drywall*
  • Lab Wing – Level 1 – Classrooms:
    • Continue Installing MEP in Ceiling
  • Lab Wing – Level 2 – Common Spaces:
    • Finish Installing Ceiling Tectum Panels and Sound Baffles
  • Lab Wing – Level 2 – Lab Area:
    • Continue Installing MEP in Cabinets and Counters
    • Install Grid and Necessary Tiles
  • Lab Wing – Level 2 – Offices and Conference Rooms:
    • Finish Installing Doors and Hardware
    • Finish MEP Trim Walls and Lids
    • Start Installing Windowsills and Casework
  • Lab Wing – Level 3 Rough-in – Orange South:
    • Finish Painting MEPFP in OTS
    • Start Pipe ID*
  • Lab Wing – Level 3 Rough-in – Blue Northeast:
    • Finish Painting MEPFP in OTS
    • Start Pipe ID
  • Lab Wing – Level 3 Rough-in – Green Northwest:
    • Finish Electrical in OTS
    • Paint MEPFP in OTS
  • Lab Wing – Level 3 Rough-in – Purple Core Area Labs:
    • Finish TU Test*
    • Continue Insulating*
  • Common Spaces – Level 3
    • Start Polish Floors*
  • Roof Level – East Penthouse, Lobby and Staging
    • MEP in Walls
  • INTERIOR BUILDOUT
  • Elevator 1:
    • Continue Workman’s Service Use
  • Elevator 2:
    • Continue Installing elevator
  • Stair 1:
    • Finish Prepping Handrails
    • Paint Rails
  • Stair 2:
    • Finish Prepping Handrails
    • Paint Rails
  • Stair 4:
    • No activities this week.
  • SITE IMPROVEMENTS
  • Phase 3 West Site Improvements:
    • Finish Install Concrete Walks Building*
    • Start Finishing the Irrigation Piping
    • Finish Curbs South End
    • Start the Rough Grade Parking Lot Install Balance of Rock
  • MECHANICAL START-UP AND COMMISSIONING
  • Start-Up:
    • Commissioning Water System

Primary construction activities for the week of 02/24 thru 02/28 will consist of the following:  

|   * = Activity delayed    |

  • ROOFING
  • Penthouse Framing and Sheathing:
    • Continue Installing Metal Siding
  • INTERIOR BUILDOUT
  • Lab Wing – Level 1 – Commons Spaces, Café, & Fireplace:
    • Finish Painting Walls
    • Paint Open to Structure *
    • Install Tile and Grout at Café Back Wall
    • Install Cabinets in Café
    • Start Installing Tile and Grout at Fireplace
  • Common Spaces All Levels – Stair Three Finish Work:
    • Continue Installing Wood Panels*
  • Commons Wing – Level 1 – Bathrooms & A/V Hard Lid Rooms:
    • Install Plumbing Trim Out
    • Install Electrical Trim Out
    • Install Grab Rails and Toilet Partitions
  • Lab Wing – Level 1 – Bathrooms and Hard Lid Rooms:
    • Install Plumbing Trim Out
    • Install Electrical Trim Out
  • Lab Wing – Level 2 – Bathrooms and Hard Lid Rooms:
    • No Activities this upcoming Week.
  • Lab Wing – Level 3 – Bathrooms and Hard Lid Rooms:
    • Finish MEP Hard Lids
    • MEP Inspection for Hard Lids
  • Commons Wing – Auditorium:
    • Continue Installing Acoustical Panels
  • Commons Wing – Innovation Lab:
    • Finish installing ACT tiles
    • Finish Crane Install
    • Start Installing Wood Paneling
    • Start Installing Lights and MEP Finishes
    •  
  • Commons Wing – Level 2 – Design 3D & Art Studio:
    • Correct Andersen Punch

Commons Wing – Level 2 – Sound Control & Vestibules:

  • No activities this upcoming week.
  • Commons Wing – Level 2 – Perforated Drywall Sound Control:
    • Finish Perforated Drywall*
  • Lab Wing – Level 1 – Classrooms:
    • Finish Installing Casework, Fume hoods, and Counter tops
    • Install Base
  • Lab Wing – Level 2 – Common Spaces:
    • Finish Third Coat Delay
    • Start Andersen Punch
  • Lab Wing – Level 2 – Lab Area:
    • Continue Installing Lab Casework and Fume hoods
  • Lab Wing – Level 2 – Offices and Conference Rooms:
    • Andersen Punch
    • MEP Cover Inspection
    • Start Installing Ceiling Tiles
  • Lab Wing – Level 3 Rough-in – Orange South:
    • Electrical in OTS
    • Paint MEPFP in OTS
    • Start Pipe ID
  • Lab Wing – Level 3 Rough-in – Blue Northeast:
    • Finish Insulating
    • Electrical in OTS
  • Lab Wing – Level 3 Rough-in – Green Northwest:
    • Finish TU Test
    • Finish Insulating
  • Lab Wing – Level 3 Rough-in – Purple Core Area Labs:
    • Finish TU Test*
    • Finish Insulating
  • Common Spaces – Level 3
    • Start Polish Floors*
  • Roof Level – East Penthouse, Lobby and Staging
    • Install Gyp
    • Start Finishing Gyp
  • INTERIOR BUILDOUT
  • Elevator 1:
    • Workman’s Inspection*
    • Workman’s Service Use
  • Elevator 2:
    • Continue Installing elevator
  • Stair 1:
    • Paint Walls Lower Landings
    • Start to Prep Handrails
  • Stair 2:
    • Start Cleaning and Patching Walls and Landings
  • Stair 4:
    • No activities this week.
  • SITE IMPROVEMENTS
  • Phase 3 West Site Improvements:
    • Finish Installing Electrical Conduits OEG*
    • Finish Install Concrete Walks Building*
    • Start to Dig RG#1 and Clean up South Side Bank

Primary construction activities for the week of 02/17 thru 02/21 will consist of the following:  

|   * = Activity delayed    |

  • ROOFING
  • Penthouse Framing and Sheathing:
    • Install Z Girt Insulation and Hat Channels*
    • Install Metal Siding
  • INTERIOR BUILDOUT
  • Lab Wing – Level 1 – Commons Spaces, Café, & Fireplace:
    • Finishing walls *
    • Paint Walls
    • Paint Open to Structure
  • Common Spaces All Levels – Stair Three Finish Work:
    • Fab Wood Panels
    • Install Wood Panels*
  • Commons Wing – Level 1 – Bathrooms & A/V Hard Lid Rooms:
    • Install Counters
    • Finish Install Tile
  • Lab Wing – Level 1 – Bathrooms and Hard Lid Rooms:
    • Install Counters
    • Finish Install Tile
  • Lab Wing – Level 2 – Bathrooms and Hard Lid Rooms:
    • No Activities this upcoming Week.
  • Lab Wing – Level 3 – Bathrooms and Hard Lid Rooms:
    • Finish Framing Hard Lids
    • Start MEP Hard Lids
  • Commons Wing – Auditorium:
    • Finish Install 1.5” Metal Deck*
    • Paint all Walls
    • Start Install Acoustical Panels
  • Commons Wing – Innovation Lab:
    • Finish installing MEP in ACT ceiling *
    • Inspect MEP in ACT ceiling *
    • Start installing ACT tiles *
    • Start Crane Install*
  • Commons Wing – Level 2 – Design 3D & Art Studio:
    • Install ceiling tiles*
    • Install Base*
    • Install Finish Electrical*
    • Third Coat Delay*
    • Andersen Punch*
  • Commons Wing – Level 2 – Sound Control & Vestibules:
    • No activities this upcoming week.
  • Commons Wing – Level 2 – Perforated Drywall Sound Control:
    • Finish the Install Perforated Drywall
    • Finish Perforated Drywall
  • Lab Wing – Level 1 – Classrooms:
    • Install MEP in Ceiling*
    • Inspect MEP in Ceiling*
  • Lab Wing – Level 2 – Common Spaces:
    • Finish the Install Base
    • Start and Finish Install Floor Boxes
    • Start Install Ceiling Tectum Panels and Sound Baffles
  • Lab Wing – Level 2 – Offices and Conference Rooms:
    • Finishing MEP in grid *
    • Finish Install Base
    • Start Install Doors and Hardware*
  • Lab Wing – Level 3 Rough-in – Orange South:
    • Finish Insulate
    • Electrical in OTS
  • Lab Wing – Level 3 Rough-in – Blue Northeast:
    • TU Test
    • Start Insulate
  • Lab Wing – Level 3 Rough-in – Green Northwest:
    • Finish Duct and TU Install
    • Start TU Test
    •  
  • Lab Wing – Level 3 Rough-in – Purple Core Area Labs:
    • Finish Duct and TU Install*
    • Start TU Test*
  • Common Spaces – Level 3
    • Start Polish Floors
  • Roof Level – East Penthouse, Lobby and Staging
    • Finish MEP in Walls*
  • INTERIOR BUILDOUT
  • Elevator 1:
    • MEP and Cap Screw
    • Workmans Inspection
  • Elevator 2:
    • Installing elevator
  • Stair 1:
    • Finish cleaning and patching walls and landings*
  • Stair 4:
    • No activities this week.
  • SITE IMPROVEMENTS
  • Phase 3 West Site Improvements:
    • Install Electrical Conduits OEG*
    • Finish Install Light Pole Foundations*
    • Start Install Concrete Walks Building*
    • Seat Wall
    • Prep Grade ADA Stalls
    • ADA Parking Stalls

Primary construction activities for the week of 02/10 thru 02/14 will consist of the following:  

|   * = Activity delayed    |

  • ROOFING
  • Penthouse Framing and Sheathing:
    • Paint Soffit
    • Install Z Girt Insulation and Hat Channels
    • Install Metal Siding
  • INTERIOR BUILDOUT
  • Lab Wing – Level 1 – Commons Spaces, Café, & Fireplace:
    • Finishing walls *
  • Common Spaces All Levels – Stair Three Finish Work:
    • Measure for Wood Panels
    • Fab Wood Panels
    • Install Wood Panels
  • Lab Wing – Level 2 – Bathrooms and Hard Lid Rooms:
    • Start & Finish installing toilet accessories *
    • Start Andersen Punch
    • Start Complete Punch
  • Commons Wing – Level 1 – Bathrooms & A/V Hard Lid Rooms:
    • Paint
    • Start Install Tile
  • Lab Wing – Level 1 – Bathrooms and Hard Lid Rooms:
    • Paint
    • Start Install Tile
  • Lab Wing – Level 3 – Bathrooms and Hard Lid Rooms:
    • Start Framing Hard Lids
  • Commons Wing – Auditorium:
    • Start & Finish Install 1.5” Metal Deck*
    • Finish Balance of Walls
  • Commons Wing – Innovation Lab:
    • Finish installing MEP in ACT ceiling *
    • Inspect MEP in ACT ceiling *
    • Start installing ACT tiles *
    • Start Crane Install
  • Commons Wing – Level 2 – Design 3D & Art Studio:
    • Install ceiling tiles*
    • Install Base
    • Install Finish Electrical
    • Third Coat Delay
    • Andersen Punch
  • Commons Wing – Level 2 – Sound Control & Vestibules:
    • Install Ceiling Grid in Sound Control
    • Install MEP in Sound Control Ceiling
    • Inspect MEP in Sound Control Ceiling
  • Commons Wing – Level 2 – Perforated Drywall Sound Control:
    • Install Perforated Drywall
    • Finish Perforated Drywall
  • Lab Wing – Level 1 – Classrooms:
    • Pain Walls
    • Install Ceiling Grid
    • Install MEP in Ceiling
    • Inspect MEP in Ceiling
  • Lab Wing – Level 2 – Common Spaces:
    • Finish Installing Carpet
    • Install Base
    • Install Floor Boxes
  • Lab Wing –  Level 2 – Offices and Conference Rooms:
    • Finishing MEP in grid *
    • Finish Installing Carpet
    • Install Base
    • Install Doors and Hardware
  • Lab Wing – Level 3 Rough-in – Orange South:
    • Finish Duct and TU Install*
    • Start TU Test*
  • Lab Wing – Level 3 Rough-in – Blue Northeast:
    • Finish Duct and TU Install*
    • Start TU Test*
  • Lab Wing – Level 3 Rough-in – Green Northwest:
    • Start Duct and TU Install
  • Lab Wing – Level 3 Rough-in – Purple Core Area Labs:
    • Finish Duct and TU Install
    • Start TU Test
  • Roof Level – East Penthouse, Lobby and Staging
    • Start and Finish MEP in Walls
  • INTERIOR BUILDOUT
  • Elevator 1:
    • Continue installing elevator
    • MEP and Cap Screw
  • Elevator 2:
    • Start installing elevator
  • Stair 1:
    • Finish cleaning and patching walls and landings
  • Stair 4:
    • Reinstall Handrail at Siding
  • SITE IMPROVEMENTS
  • Phase 3 West Site Improvements:
    • Install Electrical Conduits OEG*
    • Install Storm Water Planters and West Curbs & ADA
    • Install Light Pole Foundations
    • Install Irrigation Sleeves
    • Start Install Concrete Walks Building

Primary construction activities for the week of 02/03 thru 02/07 will consist of the following:  

|   * = Activity delayed    |

  • ROOFING
  • Penthouse Framing and Sheathing:
    • Finish installing electrical in soffit *
  • INTERIOR BUILDOUT
  • Lab Wing –  Level 2 – Bathrooms and Hard Lid Rooms:
    • Start & Finish installing toilet accessories *
    • Start Andersen Punch
    • Start Complete Punch
  • Commons Wing – Level 1 – Bathrooms & A/V Hard Lid Rooms:
    • Start finishing gyp *
  • Lab Wing –  Level 1 – Bathrooms and Hard Lid Rooms:
    • Start finishing gyp *
  • Commons Wing – Auditorium:
    • Start & Finish Install 1.5” Metal Deck
    • Finish Balance of Walls
  • Commons Wing – Innovation Lab:
    • Finish installing MEP in ACT ceiling *
    • Inspect MEP in ACT ceiling *
    • Start installing ACT tiles *
  • Commons Wing – Level 2 – Design 3D & Art Studio:
    • Finish Install MEP in ceilings
    • Inspect MEP in ceilings*
    • Install ceiling tiles*
  • Lab Wing – Level 1 – Commons Spaces, Café, & Fireplace:
    • Install Wood Ceiling Support and Hangers
    • Finish MEP in Hard Lip Café and Vest 102
    • Finish installing gyp all remaining walls and Café and VEST V0102 ceilings
    • Finishing walls *
  • Lab Wing – Level 2 – Labs:
    • Continue and Finish installing resilient flooring
  • Lab Wing –  Level 2 – Offices and Conference Rooms:
    • Finishing MEP in grid *
  • Lab Wing –  Level 3 Rough-in – South:
    • Finish Duct and TU Install
    • Start TU Test
  • Lab Wing – Level 3 Rough-in – Northeast:
    • Finish Duct and TU Install
  • Lab Wing –  Level 3 Rough-in – Northwest:
    • Finish Mechanical Insulate
    • Start Duct and TU Install
  • Lab Wing – Level 3 Rough-in – Core Area Labs:
    • Start and Finish Mechanical Insulate
    • Start Duct and TU Install
  • Lab Wing –  Level 3 Rough-in – Commons Spaces
    • Continue polishing floors
  • INTERIOR BUILDOUT
  • Elevator 1 (mistakenly had 2 on previous reports):
    • Continue installing elevator
  • Stair 1:
    • Continue cleaning and patching walls and landings
  • SITE IMPROVEMENTS
  • Phase 3 West Site Improvements:
    • Finish Install Electrical Conduits OEG
    • Finish Install Fire Hydrant, Backflow and Spin Pipe for Irrigation
    • Start and Finish Rough Grade Site South and West
    • Start and Finish Excavate RG#2 & Adjust OFCB#2

Primary construction activities for the week of 01/27 thru 01/31 will consist of the following:  

|   * = Activity delayed    |

  • ROOFING
  • Penthouse Framing and Sheathing:
    • Finish installing electrical in soffit *
    • Start gyping soffit *
  • INTERIOR BUILDOUT
  • Lab Wing –  Level 2 – Bathrooms and Hard Lid Rooms:
    • Installing electrical trim out *
    • Installing grab rails and toilet portions *
    • Start installing toilet accessories *
  • Commons Wing – Level 1 – Bathrooms & A/V Hard Lid Rooms:
    • Start finishing gyp *
  • Lab Wing –  Level 1 – Bathrooms and Hard Lid Rooms:
    • Start finishing gyp *
  • Commons Wing – Auditorium:
    • Continue installing electrical
  • Commons Wing – Innovation Lab:
    • Finish installing MEP in ACT ceiling *
    • Inspect MEP in ACT ceiling
    • Start installing gantry crane
    • Start installing ACT tiles
  • Commons Wing – Level 2 – Design 3D & Art Studio:
    • Moving MEP down per RFI_0736
    • Inspect MEP in ceilings
    • Installing ceiling tiles, base, and electrical
  • Lab Wing – Level 1 – Commons Spaces, Café, & Fireplace:
    • Installing gyp all remaining walls and Café and VEST V0102 ceilings
    • Finishing walls
  • Lab Wing – Level 1 – Classrooms:
    • Finish painting walls
    • Installing ceiling grid
  • Lab Wing – Level 2 – Rough-in:
    • Finish installing cable tray at OTS and Commons
  • Lab Wing – Level 2 – Commons Spaces:
    • Start installing base *
    • Installing floor boxes
  • Lab Wing – Level 2 – Labs:
    • Start installing resilient flooring
  • Lab Wing –  Level 2 – Offices and Conference Rooms:
    • Finishing MEP in grid *
  • Lab Wing –  Level 3 Rough-in – South:
    • Finish installing mechanical hangers, seismic, and piping – then test *
    • Continue insulating mechanical
  • Lab Wing –  Level 3 Rough-in – Northeast:
    • Finish installing mechanical hangers, seismic, and piping – then test
  • Lab Wing –  Level 3 Rough-in – Northwest:
    • Continue installing mechanical hangers, seismic, and pipe
  • Lab Wing –  Level 3 Rough-in – Core Area Labs:
    • Finish taping and finish gyp
    • Painting
    • Start installing mechanical hangers, seismic, and pipe
  • Lab Wing –  Level 3 Rough-in – Commons Spaces
    • Continue polishing floors
  • INTERIOR BUILDOUT
  • Elevator 1 (mistakenly had 2 on previous reports):
    • Continue installing elevator
  • Stair 1:
    • Continue cleaning and patching walls and landings
  • Stair 3:
    • Start installing wood railings
  • Stair 4:
    • Grinding and finishing welding
  • SITE IMPROVEMENTS
  • Phase 3 West Site Improvements:
    • Installing West storm chamber
    • Start installing storm water planters
  • Stair 1:
    • Continue cleaning and patching walls and landings

Primary construction activities for the week of 01/20 thru 01/24 will consist of the following:  

|   * = Activity delayed    |

  • ROOFING
  • Penthouse Framing and Sheathing:
    • Finish installing electrical in soffit
    • Finish framing soffit and start gyping soffit
  • CANOPIESWest Canopy V0102:Finish installing soffit and wall panels
  • INTERIOR BUILDOUT
  • Lab Wing –  Level 2 – Bathrooms and Hard Lid Rooms:
    • Installing electrical trim out
    • Installing grab rails and toilet portions
    • Start installing toilet accessories
  • Commons Wing – Level 1 – Bathrooms & A/V Hard Lid Rooms:
    • Finish gyping walls and lids
    • Start finishing gyp
  • Lab Wing –  Level 1 – Bathrooms and Hard Lid Rooms:
    • Finish gyping walls and lids
    • Start finishing gyp
  • Commons Wing – Auditorium:
    • Continue installing electrical
  • Commons Wing – Innovation Lab:
    • Start installing MEP in ACT ceiling *
  • Commons Wing – Level 2 – Design 3D & Art Studio:
    • Installing base pushed out until end of month *
    • Installing finish electrical pushed out until end of month *
    • Andersen Punch pushed out until first week of February *
    • Finish finishing drywall and paint below window
    • Installing ceiling grid and MEP in ceiling
  • Commons Wing – Level 2 – Sound Control and Vestibules:
    • Painting
  • Lab Wing – Level 1 – Commons Spaces, Café, & Fireplace:
    • Framing hard lid at Café and VEST V01012
    • Finishing MEP in hard lid at Café and VEST V0102
  • Lab Wing – Level 1 – Classrooms:
    • Start painting walls
  • Lab Wing – Level 2 – Rough-in:
    • Continue installing cable tray at OTS and Commons
  • Lab Wing – Level 2 – Commons Spaces:
    • Finishing installing carpet
    • Start installing base *
  • Lab Wing – Level 2 – Labs:
    • Finishing overhead electrical in Lab Area *
    • Finish applying moisture mitigation *
  • Lab Wing –  Level 2 – Offices and Conference Rooms:
    • Finishing MEP in grid *
  • Lab Wing –  Level 3 Rough-in – South:
    • Finish installing mechanical hangers, seismic, and piping – then test *
    • Start insulating mechanical *
  • Lab Wing –  Level 3 Rough-in – Northeast:
    • Continue installing mechanical hangers, seismic, and piping
  • Lab Wing –  Level 3 Rough-in – Northwest:
    • Finish painting
    • Start installing mechanical hangers, seismic, and pipe
  • Lab Wing –  Level 3 Rough-in – Core Area Labs:
    • Continue taping and finish gyp
  • Lab Wing –  Level 3 Rough-in – Commons Spaces
    • Continue polishing floors
  • Roof – West Penthouse ELEV Equip Room:
  • Finish installing shaft frame, gyp, and finish *
  • Start installing disconnects *
  • Roof – East Penthouse Stor, Elev Lobby & Staging:
    • Continue framing walls
    • Start installing MEP in walls
  • INTERIOR BUILDOUT
  • Elevator 2:
    • Continue installing elevator
  • Stair 1:
    • Start cleaning and patching walls and landings *
  • Stair 3:
    • Installing precast treads *
  • Stair 4:
    • Finish installing treads and risers
    • Start installing handrails