Primary construction activities this week include continued installation of underground utilities and final mobilization of DSM equipment.

Deep Soil Mixing test columns will begin Thursday July 5th, with this expect to hear noise and some possible vibrations.

Print Friendly, PDF & Email

Leave a reply

<a href="" title=""> <abbr title=""> <acronym title=""> <b> <blockquote cite=""> <cite> <code> <del datetime=""> <em> <i> <q cite=""> <s> <strike> <strong> 

required