Primary construction activities for the week of 03/23 thru 03/27 will consist of the following:  

|   * = Activity delayed    |

  • ROOFING
  • Lab High Roof East:
    • Continue Installing Roof*
  • INTERIOR BUILDOUT
  • Lab Wing – Level 1 – Commons Spaces, Café, & Fireplace:
    • Continue Installing Tile and Grout at Fireplace
  • Common Spaces All Levels – Stair Three Finish Work:
    • Fab Wood Panels
  • Commons Wing – Level 1 – Bathrooms & A/V Hard Lid Rooms:
    • Finish Installing Toilet Accessories*
    • Andersen Punch
    • Complete Punch
  • Lab Wing – Level 1 – Bathrooms and Hard Lid Rooms:
    • Install Grab Rails and Toilet Partitions*
    • Start Installing Toilet Accessories
    • Andersen Punch
    • Complete Punch
  • Lab Wing – Level 2 – Bathrooms and Hard Lid Rooms:
    • Install Grab Rails and Toilet Partitions
    • Install Toilet Accessories
  • Lab Wing – Level 3 – Bathrooms and Hard Lid Rooms:
    • Paint
    • Install Tile
  • Commons Wing – Auditorium:
    • Finish Electrical in Stair Framing
  • Commons Wing – Innovation Lab:
    • Install Lights and MEP Finishes
    • Install Wood Paneling
    • Andersen Punch
  • Commons Wing – Level 2 – Design 3D & Art Studio:
    • No Activities this Upcoming Week.
  • Commons Wing – Level 2 – Sound Control & Vestibules:
    • No Activities this Upcoming Week.
  • Commons Wing – Level 2 – Perforated Drywall Sound Control:
    • Install Expansion Joints
  • Lab Wing – Level 1 – Classrooms:
    • Install Base
    • Install Finish MEP
  • Lab Wing – Level 2 – Common Spaces:
    • No Activities this Upcoming Week.
  • Lab Wing – Level 2 – Lab Area:
    • Install Balance of Tiles and Clouds
  • Lab Wing – Level 2 – Offices and Conference Rooms:
    • Continue Installing Windowsills and Casework*
  • Lab Wing – Level 3 Rough-in – Orange South:
    • No Activities this Upcoming Week.
  • Lab Wing – Level 3 Rough-in – Blue Northeast:
    • No Activities this Upcoming Week.
  • Lab Wing – Level 3 Rough-in – Green Northwest:
    • No activities this upcoming week.
  • Lab Wing – Level 3 Rough-in – Purple Core Area Labs:
    • No Activities this Upcoming Week.
  • Common Spaces – Level 3
    • Continue Installing Carpet
    • Install Base
  • Lab Wing – Level 3
    • Start Installing Rubber Flooring
  • Offices and Conference Rooms – Level 3
    • Finish Installing Windowsills and Casework
    • Install Ceiling Tiles
  • Roof Level – East Penthouse, Lobby and Staging
    • Stuff and Spray Top of Wall
    • Install Ceiling OTS Insulation
    • Paint Room
  • INTERIOR BUILDOUT
  • Elevator 1:
    • Continue Workman’s Service Use
  • Elevator 2:
    • Continue Installing elevator
  • Stair 1:
    • No activities this week.
  • Stair 2:
    • No Activities this Upcoming Week.
  • Stair 4:
    • No Activities this Upcoming Week.
  • SITE IMPROVEMENTS
  • Phase 3 West Site Improvements:
    • Continue Installing Plants
    • Start Seeding Areas