Primary construction activities for the week of 11/18 thru 11/22 will consist of the following:
| * = Start or Finish was delayed | ** Activity taking longer than projected |
- ROOFING
- Low Roof Auditorium:
- Penthouse Framing and Sheathing:
- Finish framing soffit
- Continue installing metal siding
- CANOPIESEast Canopy V103:Finish installing frames and glass **
- South Canopy V101:Finish installing frames and glass **
- West Canopy V102:Finish installing electrical and gyping lidsFinish installing WRB *
- Commons Wing Soffit:Continue installing trim and metal soffit panels
- Lab Wing Soffit:Start installing trim and metal soffit panels *
- WINDOWS & SIDING
- Auditorium – South Elevation:
- Continue finishing siding after soffit is complete
- Auditorium – West Elevation:
- Installing beauty cap and flashing
- Auditorium – North Elevation:
- Finish installing glass and pressure bar
- Start installing beauty cap and flashing *
- Auditorium – East Elevation:
- Finish finishing siding *
- INTERIOR BUILDOUT
- Commons Wing – Level 1 – Rough-in:
- Finish installing MEP in 1st floor corridors *
- Start installing 1.5” metal deck *
- Commons Wing – Level 2 – Designs 3D
& Art Studio:
- Start installing MEP in ceiling, inspecting MEP in ceilings, and installing ceiling tiles *
- Commons Wing – Level 2 – Sound Control
and Vestibules:
- Finish finishing lids and walls *
- Lab Wing – Level 1 – Rough-in:
- Finish painting top out and OTS **
- Start installing overhead MEP work in OTS *
- Lab Wing – Level 1 – Commons Spaces:
- Finish installing fireplace and MEP in fireplace cavity **
- Starting gyping walls *
- Lab
Wing – Level 1 – Bathrooms and Hard Lid Rooms:
- Finish framing hard lids **
- Start installing MEP at hard lids *
- Lab Wing – Level 2 – Rough-in:
- Continue installing cable tray at OTS and Commons
- Lab
Wing – Level 2 – Offices and Conference Rooms:
- Start finishing MEP in grid *
- Lab
Wing – Level 2 – Bathrooms and Hard Lid Rooms:
- Finish finishing gyp *
- Painting
- Lab Wing – Level 3 Rough-in:
- Finish installing MEP in walls at Doughnut
- Roof – West Penthouse ELEV Equip Room:
- Finish installing shaft frame, gyp, and finish *
- Start installing disconnects *
- Elevator 2:
- Continue installing elevator