Primary construction activities for the week of 11/18 thru 11/22 will consist of the following:  

|   * = Start or Finish was delayed    |   ** Activity taking longer than projected   |

  • ROOFING
  • Low Roof Auditorium:
  • Penthouse Framing and Sheathing:
    • Finish framing soffit
    • Continue installing metal siding
  • CANOPIESEast Canopy V103:Finish installing frames and glass **
  • South Canopy V101:Finish installing frames and glass **
  • West Canopy V102:Finish installing electrical and gyping lidsFinish installing WRB *
  • Commons Wing Soffit:Continue installing trim and metal soffit panels
  • Lab Wing Soffit:Start installing trim and metal soffit panels *
  • WINDOWS & SIDING
  • Auditorium – South Elevation:
    • Continue finishing siding after soffit is complete
  • Auditorium – West Elevation:
    • Installing beauty cap and flashing
  • Auditorium – North Elevation:
    • Finish installing glass and pressure bar
    • Start installing beauty cap and flashing *
  • Auditorium – East Elevation:
    • Finish finishing siding *
  • INTERIOR BUILDOUT
  • Commons Wing – Level 1 – Rough-in:
  • Finish installing MEP in 1st floor corridors *
  • Start installing 1.5” metal deck *
  • Commons Wing – Level 2 – Designs 3D & Art Studio:
    • Start installing MEP in ceiling, inspecting MEP in ceilings, and installing ceiling tiles *
  • Commons Wing – Level 2 – Sound Control and Vestibules:
    • Finish finishing lids and walls *
  • Lab Wing – Level 1 – Rough-in:
  • Finish painting top out and OTS **
  • Start installing overhead MEP work in OTS *
  • Lab Wing – Level 1 – Commons Spaces:
    • Finish installing fireplace and MEP in fireplace cavity **
    • Starting gyping walls *
  • Lab Wing –  Level 1 – Bathrooms and Hard Lid Rooms:
    • Finish framing hard lids **
    • Start installing MEP at hard lids *
  • Lab Wing –  Level 2 – Rough-in:
    • Continue installing cable tray at OTS and Commons
  • Lab Wing –  Level 2 – Offices and Conference Rooms:
    • Start finishing MEP in grid *
  • Lab Wing –  Level 2 – Bathrooms and Hard Lid Rooms:
    • Finish finishing gyp *
    • Painting
  • Lab Wing –  Level 3 Rough-in:
    • Finish installing MEP in walls at Doughnut
  • Roof – West Penthouse ELEV Equip Room:
  • Finish installing shaft frame, gyp, and finish *
  • Start installing disconnects *
  • Elevator 2:
    • Continue installing elevator