Most work from last week at the clinic will be continuing through this week, the storefront windows and glass glazing will be installed and the 2nd floor framing and sheetrock will also continue. New at the clinic this week, the new resilient flooring will start to go in.
The lecture hall also has several activities from last week continuing, including the casework and light fixture installation. However crews will also start sidewalk preparations and installing tile in the restrooms and carpet in the conference room.
LINAC continues to have the mechanical, electrical and plumbing lines roughed-in and wall finishing and painting have been added to the “to do” list this week.
Finally, around the overall site, there will be landscaping, irrigation and curb/sidewalk work going on.