Primary construction activities for the week of 05/13 thru 05/17 will consist of:

ZONING LEGEND

Z1 = East Commons Wing  |  Z2 = West Commons Wing  |  Z3 = West Lab Wing  |  Z4 = Middle of Lab Wing   |  Z5 = East Lab Wing

  • Roofing
    • Evacuation Ramp
      • Continue Installing handrails
      • Installing expansion joint
    • Lab High Roof West
      • Continue installing roof
  • Framing Sheeting (2nd & 3rd Floor)
    • Lab Wing West & SW Elevation:
      • Finish installing flashing at pop-outs
      • Installing temp window protection as needed
    • Lab Wing North Elevation:
      • Finish installing exterior gyp
      • Continue installing air and water barrier, window steel at pop outs, and flashing at pop outs
    • Lab Wing East Elevation
      • Installing steel studs
    • Penthouses
      • Finish installing framing
  • Framing Sheeting (1st Floor)
    • Auditorium Misc. Steel and Wind Girts
      • Finish setting Auditorium mezzanine steel
    • Auditorium East Elevation
      • Finish installing steel stud floor clips
    • Auditorium South Elevation
      • Installing steel stud floor clips
    • Auditorium West Elevation
      • Installing steel stud floor clips
    • Lab Wing West Elevation
      • Installing top / bottom track and studs
    • Lab Wing North Elevation
      • Installing top / bottom track
  • Windows and Siding
    • West Elevation
      • Finish installing vertical Z Girt and windows
      • Finish installing backer rods and caulking
      • Start installing flashing and trim
  • Site Improvements
    • Mechanical Enclosure M0101
      • Start installing electrical and chilled water
    • Ramp
      • Installing Bentonite and fluid applied waterproofing, foundation drain, back fill and grade for foam
      • Finish installing foam

Primary construction activities for the week of 05/06 thru 05/10 will consist of:

ZONING LEGEND

Z1 = East Commons Wing  |  Z2 = West Commons Wing  |  Z3 = West Lab Wing  |  Z4 = Middle of Lab Wing   |  Z5 = East Lab Wing

  • Ramp
    • Northeast Wall (Pour 6):
      • Finish closing wall formwork, pouring, and stripping.
  • Structural Steel
    • Zone 1:
      • Finish installing metal decking and closure strips by EOW.
  • Slab on Grade
    • Zone 3 (South ½ of Z3 & Z4 and 65% of Z5):
      • Installing top embeds and pouring.
    • Zone 4 (North ½ of Z3 & Z4):
      • Finish installing blockouts and edge form.
      • Installing rebar, top embeds, and pouring.
    • Zone 5:
      • Installing top embeds and pouring.
  • Roofing
    • Evacuation Ramp
      • Installing 4 x 4 angle at Eyebrow.
      • Start installing handrails.
    • East Penthouse:
      • Pouring Slab-on Foam.
  • Framing Sheeting (2nd & 3rd Floor)
    • Lab Wing West & SW Elevation:
      • Finish installing window steel at pop-outs.
      • Start installing flashings at pop-outs.
    • Lab Wing North Elevation:
      • Finish installing exterior gyp.
      • Start installing air and water barrier, window steel at pop outs, and flashings at pop outs.
    • Lab Wing South Elevation
      • Finish installing steel stud floor clips.
  • Penthouses
    • Start installing framing
  • Framing Sheeting (1st Floor)
    • Auditorium Misc. Steel and Wind Girts
      • Finish setting Auditorium mezzanine steel.
    • Auditorium North Elevation
      • Finish installing steel stud floor clips.
    • Auditorium East Elevation
      • Finish installing steel stud floor clips.
    • Windows and Siding
      • West Elevation
        • Finish installing vertical Z Girt and windows.
        • Start installing backer rods and caulking.
  • Site Improvements
    • Mechanical Enclosure M0101
      • Excavating for electrical and chilled water.
    • Ramp
      • Installing Bentonite and fluid applied waterproofing, foundation drain, back fill and grade for foam.
      • Start installing foam at EOW.

Primary construction activities for the week of 04/29 thru 05/03 will consist of:

ZONING LEGEND

Z1 = East Commons Wing  |  Z2 = West Commons Wing  |  Z3 = West Lab Wing  |  Z4 = Middle of Lab Wing   |  Z5 = East Lab Wing

  • Ramp
    • Northeast Wall (Pour 6):
      • Finish closing wall formwork, pouring, and stripping.
  • Structural Steel
    • Zone 1:
      • Finish installing metal decking and closure strips by EOW.
  • Slab on Grade
    • Zone 3 (South ½ of Z3 & Z4 and 65% of Z5):
      • Installing blockouts, edge form, electrical, and importing rock & grade.
      • Installing vapor barrier and rebar.
    • Zone 4 (North ½ of Z3 & Z4):
      • Installing electrical and final grading of native.
      • Importing rock & grade, installing blockouts, edge form, and vapor barrier.
    • Zone 5:
      • Importing rock & grade, installing blockouts, edge form, vapor barrier, and rebar.
  • Roofing
    • Evacuation Ramp
      • Cleaning embeds and roof area.
      • Installing framing on GL-8 above and North of ramp.
    • Lab Wing Main Roof:
      • West Penthouse:
        • Forming, installing rebar, and pouring curbs
        • Pouring Slab-on-Foam.
      • East Penthouse:
        • Finish welding, bolting, and decking.
        • Installing formwork, rebar, and pouring curbs.
  • Framing Sheeting
    • Lab Wing West & SW Elevation:
      • Start installing exterior gyp board, flashings at pop-outs, window steel at pop-outs, and air & water barrier.
    • Lab Wing North Elevation:
      • Continue installing steel studs.
    • Lab Wing East Elevation:
      • Finish installing steel stud floor clips.
    • Lab Wing South Elevation
      • Start installing steel stud floor clips.

 

  • Sitework & Utilities
    • Installing Potable and Fire water laterals.

Primary construction activities for the week of 04/22/19 thru 04/26/19 will consist of:

ZONING LEGEND

Z1 = East Commons Wing  |  Z2 = West Commons Wing  |  Z3 = West Lab Wing  |  Z4 = Middle of Lab Wing   |  Z5 = East Lab Wing

  • Ramp
    • Northeast Wall (Pour 6):
      • Setting wall formwork and installing wall rebar.
  • Structural Steel
    • Zone 1:
      • Finish installing metal decking and closure strips by EOW
  • Slab on Metal Deck
    • Zone 5 Level 2:
      • Curing deck for reshore removal
  • Slab on Grade
    • Zone 2:
      • Pouring slab
    • Zone 3:
      • Installing potable water, sanitary sewer & storm, and electrical
    • Zone 4:
      • Installing sanitary sewer & storm and potable water
    • Zone 5:
      • Installing potable water, sanitary sewer & storm, and electrical
  • Roofing
    • High Roof Auditorium:
      • Start installing roofing
    • Lab Wing Main Roof:
      • Forming and installing rebar at West curbs
      • West Penthouse:
        • Forming, installing rebar, and pouring curbs
      • East Penthouse:
        • Welding, bolting, and decking
        • Forming curbs
      • Lab High Roof East:
        • Continue installing roofing
    • Lab High Roof West:
      • Continue installing roofing
    •  Canopies:
      • Start installing roofing
  • Framing Sheeting
    • Lab Wing West & SW Elevation:
      • Continue installing steel studs
    • Lab Wing North Elevation:
      • Continue installing steel stud floor clips
    • Lab Wing East Elevation:
      • Continue installing steel stud floor clips
    • Miscellaneous Steel & Wind Girts
      • Auditorium:
        • Setting mezzanine steel

Primary construction activities for the week of 04/15 thru 04/19 will consist of:

ZONING LEGEND

Z1 = East Commons Wing  |  Z2 = West Commons Wing  |  Z3 = West Lab Wing  |  Z4 = Middle of Lab Wing   |  Z5 = East Lab Wing

  • Ramp
    • East Storage Room & Northeast Wall (Pour 4):
      • Closing formwork, pouring, and stripping wall
    • South Wall East Portion (Pour 5):
      • Setting wall formwork
  • Structural Steel
    • Zone 1:
      • Finish installing metal decking and closure strips early next week
  • Slab on Metal Deck
    • Zone 5 Level 3:
      • Curing deck for reshore removal
    • Zone 4 Level 2:
      • Finish installing rebar; installing top embeds and pouring deck
    • Zone 5 Level 2
      • Installing rebar, top embeds, and pouring deck
  • Slab on Grade
    • Zone 1:
      • Installing top embeds and pouring slab
    • Zone 2:
      • Installing rebar, top embeds, and pouring slab
  • Roofing
    • Lab Wing Main Roof:
      • Forming and installing rebar at West curbs
      • West Penthouse:
        • Welding, bolting, and decking
      • East Penthouse:
        • Welding, bolting, and decking
      • Lab High Roof East:
        • Continue installing roof
      • Lab High Roof West:
        • Continue installing roof
  • Framing Sheeting
    • Lab Wing West & SW Elevation:
      • Installing steel studs
    • Lab Wing North Elevation:
      • Installing steel stud floor clips
    • Lab Wing East Elevation:
      • Installing steel stud floor clips

Primary construction activities for the week of 04/08/19 thru 04/12/19 will consist of:

ZONING LEGEND

Z1 = East Commons Wing  |  Z2 = West Commons Wing  |  Z3 = West Lab Wing  |  Z4 = Middle of Lab Wing   |  Z5 = East Lab Wing

  • Ramp
    • East Storage Rm & Northeast Wall (Pour 4):
      • Closing formwork, pouring, and stripping wall
    • South Wall East Portion (Pour 5):
      • Setting wall formwork
    • Structural Steel
      • Zone 1:
        • Finish installing metal decking and closure strips
      • Slab on Metal Deck
        • Zone 4 Level 3:
          • Pouring deck and curing deck for Reshore removal
        • Zone 3 Level 2:
          • Finish installing rebar, top embeds, pouring deck, and curing deck for Reshore removal
        • Zone 5 Level 3:
          • Finish installing rebar, top embeds and QA/QC deck
        • Zone 4 Level 2:
          • Installing rebar
        • Slab on Grade
          • Zone 1:
            • Installing top embeds and pouring slab
          • Zone 2:
            • Installing vapor barrier, stripping at GL-N, and back filling at GL-N
            • Installing rebar, top embeds, and QA/QC pour
          • Roofing
            • Lab Wing High Roof:
              • Set West and East Penthouse steel
              • Set Elevator spreader tubes
              • Weld bolt and deck at West Penthouse
            • Lab High Roof East
              • Continue installing roof
            • Framing Sheeting
              • Lab Wing West & SW Elevation:
                • Installing steel stud floor clips
              • Lab Wing North Elevation
                • Installing steel stud floor clips

Primary construction activities for the week of 04/01/2019 thru 04/05/2019 will consist of the following:

ZONING LEGEND

Z1 = East Commons Wing  |  Z2 = West Commons Wing  |  Z3 = West Lab Wing  |  Z4 = Middle of Lab Wing   |  Z5 = East Lab Wing

  • Ramp
    • East Storage Rm & Northeast Wall (Pour 4):
      • Setting wall, placing rebar, and closing formwork
    • Structural Steel
      • Zone 1:
        • Install metal decking and closure strips
      • Slab on Metal Deck
        • Zone 3 Level 3:
          • Pouring and curing deck for shore removal
        • Zone 5 & ½ Zone 4 Roof:
          • Installing rebar, top embeds, and pouring deck
        • Zone 4 Level 3:
          • Installing blockouts, down embeds, shoring, rebar, and top embeds
        • Zone 3 Level 2:
          • Installing rebar
        • Zone 3 Level 2:
          • Installing blockouts, down embeds, and shoring
        • Zone 4 Level 2:
          • Installing blockouts, down embeds, and shoring
        • Zone 5 Level 2:
          • Installing blockouts and down embeds
        • Slab on Grade
          • Zone 1:
            • Installing blockouts, edge form, importing rock / grade, installing rebar, vapor barrier and top embeds
          • Zone 2:
            • Installing blockouts, edge form, importing rock / grade
            • Digging footings and pouring grout at GL-N
            • Forming, placing rebar, and pouring footing at GL-N
            • Installing vapor barrier, stripping at GL-N, and back filling at GL-N
          • Roofing
            • Lab Wing High Roof:
              • Start forming curbs and crickets at beginning of week.

Primary construction activities for the week of 03/25/2019 thru 03/29/2019:

  • Ramp
    • North Radius Wall (Pour 2):
      • Strip formwork.
    • South Wall West (Pour 3):
      • Finish setting wall and installing rebar.
  • Structural Steel
    • East Lab Wing (Z5):
      • Finish bolting, plumbing, and welding.
      • Start installing metal decking and closure strips.
  • Slab on Metal Deck
    • West Commons Wing Roof (Z2):
      • Pouring at beginning of week
    • West Lab Wing Roof (Z3 & ½ Z4):
      • Installing rebar, top embeds, and pouring deck
    • West Lab Wing L3 (Z3):
      • Installing rebar, and top embeds
    • West Lab Wing L2 (Z3)
      • Installing blockouts, down embeds and shoring
  • Slab on Grade
    • East Commons Wing:
      • Installing sanitary sewer and storm, electrical, potable water, blockouts and edge form, and grading.
    • West Commons Wing
      • Installing electrical, potable water, sanitary sewer and storm, installing block outs and edge form, and grading.
  • Roofing
    • Lab Wing High Roof:
      • Start forming curbs and crickets at end of week.

Primary construction activities for the week of 03/18/2019 – 03/22/2019:

  • Ramp:
    • South Wall West (Pour 3):
      • Finish setting wall and installing rebar. Start closing formwork.
  • Structural Steel:
    • West Lab Wing (Z3):
      • Finish installing headed studs.
    • Center Lab Wing (Z4):
      • Continue installing metal decking and closure strips.
    • East Lab Wing (Z5):
      • Continue bolting, plumbing, and welding.
  • Slab on Metal Deck
    • West Commons Wing Roof (Z2):
      • Installing rebar and shoring.
      • Installing top embeds.
      • Pouring deck at EOW.
    • West Commons Wing L2 (Z2):
      • Pouring deck Mid-Week.
      • Curing deck.
    • West Lab Wing Roof (Z3):
      • Installing blockouts, down embeds, and shoring.
      • Start installing rebar.
    • West Lab Wing L3 (Z3):
      • Installing blockouts, down embeds, and shoring.
    • Mockup:
      • QED performing Water Test.

Primary construction activities for the week of 03/11/2019 thru 03/15/2019:

  • Ramp:
    • Pour 2 (North Radius Wall):
      • Finish stripping wall.
    • Pour 3 (South Wall West):
      • Setting wall and installing rebar.
  • Structural Steel:
    • Stair 2:
      • Finish install of handrails.
    • East Commons (Z1):
      • Finish install of metal decking and closure strips.
    • West Lab Wing (Z3):
      • Installing headed studs.
    • Center Lab Wing (Z4):
      • Finish bolting, plumbing, and welding.
      • Install metal decking and closure strips.
    • East Lab Wing (Z5):
      • Bolting, plumbing, and welding
  • Slab on Metal Deck
    • Z2 Roof:
      • Installing blockouts and down embeds
      • Installing rebar
      • Installing top embeds
    • Z2 L2:
      • Installing blockouts and down embeds
      • Installing rebar
  • Sitework & Utilities
    • Install potable and fire water laterals
  • Mockup:
    • Finish installing siding.