Weekly Update 6/24-6/28

The clinic will be shaping up this week as crews work on installing the metal panels and window frames. The second floor will have additional work going on, as the sheetrock also gets installed this week.

The lecture hall will continue to have the installation of the glass glazing, which is a continuation from last week. New this week, fixtures for the lecture hall will be installed beginning this week.

In what will be the new parking parking lot by the clinic and new entrance to the small animal hospital, underground utilities will be put down into place.

Wrapping up with the progress at LINAC, crews are still continuing with electrical, mechanical and plumbing rough in.

More photos can be found under the photos tab!

Magruder Update 6/18

Currently at the addition of the clinic, the second floor is having the ducting installed for the heating and cooling system and the clinic overall will start to see paint go up on the walls. The latter half of the week, crews will start to install fixtures and the ceiling and the second floor will have the door frames set. In connecting the Clinic to the lobby, the plumbing under the concrete will be completed. As well as the heating demo and electrical rough in, the week will finish up with the concrete slab will be poured back.

The new lecture hall will have the taping of the drywall complete and will start have paint applied at the end of the week, moving into next week. The glass glazing of the building will be installed as well as the glass storefront windows.

Things will be pretty simple this week at the LINAC addition with the plumbing and electrical rough ins will start at the end of the week.

Major prep will be happening for the parking lots will be going on this week. Overall parking lot prep will be occurring, as well as, putting in the new sewer line and prepping the east side of the clinic parking.

 

5/20 Weekly Update

This week at the new clinic, the weest wall will have its brick cladding installed, which will be finished by the end of the week. Also happening at the clinic, crews will get started on the interior epoxy floors. This work will continue through this week and to the end of next week.

Now that sheetrock is up at the lecture hall, crews are working at taping and mudding so paint can go up the middle of next week. The panel installation will be continue through this week, so it can be finished up by early next week.

The structural street is going up at the LINAC addition, as well as at the lobby. Rough-ins for mechanical, electrical and plumbing is also happening in the lobby this week.

On the outside, the new parking lot is being prepped for new curbs and sidewalks.

April Showers bring May Buildings: Weekly Update 4/29-5/3

As we jump into the month of May, Construction continues on at the new Clinic and Lecture hall at the Magruder Hall Expansion Project. As everyone is able to enjoy this beautiful weather, the first floor of the clinic will see the sheet rock go up and the outer brick veneer continues to be installed. As the new clinic become incorporated into the existing Magruder Hall, the existing lobby will be going through work roughing in for new electrical.

The focus at the new Lecture hall will also center around the electrical rough in this week and the demo’d parking lot will be going through excavation to make room for more parking to service the new clinic.

Demo-ing the Lobby: Weekly update 4/8-4/12

This week the existing lobby for the animal hospital as well as the small animal hospital parking lot, which closed the beginning of last week. With the parking lot demo, the tree removal will finish up and existing brush will come out too.

As the clinic gets incorporated with the existing animal hospital, crews will push through the rain to complete the exterior waterproofing and begin the brick veneer.

Things will be short and sweet at the lecture hall this week as crews continue  with roofing, which is the only major project taking place at the lecture hall this week.

Remember to check out the schedule and photos to stay up to date with the Magruder Expansion.

The amount of work getting done this week is NO joke: Weekly Update 4/1-4/5

This weeks work will take place solely around the lecture hall and the clinic.

If you haven’t already noticed, the main parking lot of the small animal hospital is now closed and will remain closed through the end of August. For those trying to access the small animal hospital, designated parking has been added across the street in the B1 section of lot 3284 (Truax Indoor Performance Center).  

At the Lecture Hall, the interior framing will go up and be completed by the end of the week. Waterproofing for the roof installation is planned to continue this week, but will be dependent of the rain holding off. Also the interior utility rough-ins for mechanical, electrical and plumbing will get started.

The major work at the clinic starts with the continuation of the exterior waterproofing and starting to sheet rock the first floor. It’s on the schedule to finish out the utility rough-ins and insulating piping and ductwork by the end of the week. As well as finishing up the installation of the flashing.

Readjusting after Snow: Weekly Update 3/4-3/8

After last weeks snow postponed construction for several days, the crew are getting back out there and working hard to get caught up with last weeks schedule.

It will be a busy week at the clinic, the exterior stub walls will continue to go up as a continuation from late week and will carry over into the following week. Also over the course of this week crews will be working on the concrete pour for the stairs. This wonder sunny spring weather that we are starting out the week with will be perfect for the weather dependent roofing. We are keeping our fingers crossed that the snow is done for the season! Finally, the electrical rough in will begin on the second floor at the beginning of this week and is anticipated to take a couple of weeks.

Things will also be busy at the lecture hall building as we come out of our snow days. the framing of the lecture hall will continue into this week and next, as will the installing of the piping for the fire suppression system. Though it is plan to be wrapped up by the end of the week. The current weather will also be helpful at the lecture hall as they plan to start the weather dependent roofing this week. After all of this, the lecture hall will start to look more like a building than its current black-boxy form. That’s because the exterior brick veneer will start to go up and the new lecture hall will blend seamlessly in with the existing Magruder Hall.

With all the major working happening at the clinic and lecture hall this week, things will be a little quieter at the LINAC addition. The only major activity over the next couple of weeks will be the framing.

A Presidential Weekly Update: 2/18-2/22

As we kick this week off with Presidents Day, our crew continues to blast through construction, like the blasts that created our founding fathers on Mt. Rushmore.

Once again, the majority of the work this week will be happening at the clinic. The exterior stub walls are still going up and the footings for the entry vestibule (two door system entry) will be started and completed by the end of the week. The second floor will see the framing be finished out and plumbing, mechanical, and electrical rough-ins will be completed but the end of the week.

Weather dependent, both the clinic and lecture hall could be some roofing action starting to take place.

Also at the lecture hall, the exterior stub walls will continue to go up through the beginning of next week. Framing inside the lecture hall will begin early this week and carry through the beginning of March. The piping for the fire suppression system will be closed out by end of day, Wednesday.

The slab edge form at LINAC as been pushed over into this week, the concrete pour is now expected to happen next week.

Starting to look like a building, Weekly Update 2/11-2/15

If you have been by Magruder Hall, you’ve seen the major changes taking place with the new expansion. Over the upcoming weeks, this expansion will start taking shape as actually buildings and becoming an integrated foundation to Magruder Hall and the Veterinary College Community.

In the terms of major milestones, the roofing for the clinic will start today, Monday the 11th.  The installation of the exterior stub walls will also start this morning. Then, the clinic will also continue the interior framing from last week, which will also continue over to next week. HVAC will also start on the first floor of the clinic with the installation of the supply and return ductwork.

There will be fewer activities taking place in the lecture hall with only the continuation of the framing installation on the schedule.

LINAC will see a multitude of activities with continuing the plumbing and electrical slab rough ins from last week. Starting mid week will be the preparation under the slab overhang and rounding out the week with setting the slab edge form to prepare for the slab pour early next week.

Make sure to check out the photos for a SNEAK PEEK at the interior of the clinic and LINAC addition!

Weekly Update 2/4-2/8

The majority of the site work will take place around the clinic this week. Continuing on from last week, the crews will be prepping for the vestibule footing prep and the interior framing. New this week, the fire suppression system will begin to be installed.

The lecture hall framing will also continue and the slab on grade mechanical, electrical, and plumbing rough in at LINAC.

While the to-do list is short this week, these are major components of the Magruder Expansion and we’ll start noticing more physical changes in the project.