Primary construction activities for the week of December 3rd through December 7th:
Forming and pouring of:
- Core wall Zone 1 Level 2
- Shear walls Zone 2 and 4 Level 3
- Shear wall Zone 3 level 2
- Shear wall Zone 1 and 5 Level 2
Backfilling continuous footings and East mat.