Primary construction activities for the week of 03/18/2019 – 03/22/2019:
- Ramp:
- South Wall West (Pour 3):
- Finish setting wall and installing rebar. Start closing formwork.
- South Wall West (Pour 3):
- Structural Steel:
- West Lab Wing (Z3):
- Finish installing headed studs.
- Center Lab Wing (Z4):
- Continue installing metal decking and closure strips.
- East Lab Wing (Z5):
- Continue bolting, plumbing, and welding.
- West Lab Wing (Z3):
- Slab on Metal Deck
- West Commons Wing Roof (Z2):
- Installing rebar and shoring.
- Installing top embeds.
- Pouring deck at EOW.
- West Commons Wing L2 (Z2):
- Pouring deck Mid-Week.
- Curing deck.
- West Lab Wing Roof (Z3):
- Installing blockouts, down embeds, and shoring.
- Start installing rebar.
- West Lab Wing L3 (Z3):
- Installing blockouts, down embeds, and shoring.
- Mockup:
- QED performing Water Test.
- West Commons Wing Roof (Z2):