Primary construction activities for the week of 05/27 thru 05/31 will consist of:

ZONING LEGEND

Z1 = East Commons Wing  |  Z2 = West Commons Wing  |  Z3 = West Lab Wing  |  Z4 = Middle of Lab Wing   |  Z5 = East Lab Wing

  • ROOFING
    • High Roof Auditorium:
      • Continue installing roof
    • Evacuation Ramp:
      • Finish installing handrails
      • Finish installing expansion joint
      • Hot rubber roofing postponed to following week
    • Penthouses:
      • Continue installing framing
    • Lab High Roof West:
      • Continue installing roof
  • FRAMING SHEATING (2nd & 3rd Floor)
    • Lab Wing – North Elevation:
      • Finish installing air and water barrier
      • Continue installing flashings at pop outs
      • Start installing temp window protection
    • Lab Wing – East Elevation:
      • Finish installing window steel at pop outs
      • Continue installing flashings at pop outs and air & water barrier
    • Lab Wing – South Elevation:
      • Continue installing steel studs
  • FRAMING SHEATING (1st Floor)
    • Lab Wing – West Elevation:
      • Finish installing exterior gyp
      • Continue installing window steel at window head & sill, flashings, and air & water barrier
    • Lab Wing – North Elevation:
      • Finish installing steel studs
      • Start installing exterior gyp
    • Lab Wing – East Elevation:
      • Start installing steel studs
    • Lab Wing – South Elevation:
      • Finish installing top / bottom track and studs
    • Auditorium – South Elevation:
      • Finish installing steel stud floor clips
      • Start installing steel studs
    • Auditorium – West Elevation:
      • Start installing steel stud floor clips
  • WINDOWS & SIDING
    • Lab Wing – West Elevation:
      • Finish installing flashings, and trim
    • Lab Wing – North Elevation:
      • Start installing vertical Z girt and windows
  • INTERIOR BUILDOUT
    • Mechanical & Back of House:
      • Finish installing hollow metal doors
      • Continue framing walls
    • Lab Wing Level 2 – Rough-in:
      • Continue installing MEP in Labs
      • Start installing hollow metal doors
    • Mechanical & Back of House:
      • Finish installing hollow metal doors
    • Stair 1:
      • Continue finishing interior
  • SITE IMPROVEMENTS
    • Mechanical Enclosure M0101:
      • Layout and excavate for Generator Pad and footings and forming generator pad and footings
    • ODF&W Parking and Sidewalks:
      • Finish installing erosion control and site fencing
      • Excavating Rain Garden #2
      • Excavating public rain garden
      • Installing storm at Manhole #1 and storm chambers
    • Ramp:
      • Forming, installing rebar, pouring, and stripping lower corbel
  • ROOFING
    • High Roof Auditorium
      • Continue installing roof
    • Evacuation Ramp
      • Continue installing handrails
      • Finish installing expansion joint
      • Start installing hot rubber roofing
    • Lab High Roof West
      • Continue installing roof
    • Penthouse
      • Installing framing
  • FRAMING SHEETING (2nd & 3rd Floor)
    • Lab Wing West & SW Elevation:
      • Installing temp window protection (if needed)
    • Lab Wing North Elevation:
      • Finish installing air and water barrier
      • Continue installing window steel at pop outs and flashing at pop outs
    • Lab Wing East Elevation:
      • Installing exterior gyp and window steel at pop outs
      • Start installing flashing at pop outs and air & water barrier
    • Lab Wing South Elevation:
      • Start installing steel studs
    • Penthouses:
      • Finish installing framing
  • FRAMING SHEETING (1st Floor)
    • Lab Wing West Elevation
      • Installing exterior gyp
      • Start installing window steel at window head & sill, flashing, and air & water barrier
    • Lab Wing North Elevation
      • Installing steel studs
      • Start installing exterior gyp
    • Lab Wing East Elevation
      • Finish installing top / bottom track and studs
      • Start installing steel studs
    • Lab Wing South Elevation:
      • installing top / bottom track and studs
    • Auditorium Misc. Steel and Wind Girts:
      • Setting Innovation Lab window steel, S&W wind girts, and overhead door steel
    • Auditorium South Elevation:
      • Finish installing steel stud floor clips
      • Start installing steel studs
  • WINDOWS & SIDING
    • West Elevation
      • Finish installing backer rods & caulking, flashing, and trim
      • Start installing glass, pressure bar, and siding horizontal cleat
  • INTERIOR BUILD OUT
    • Mechanical & Back of House
      • Placing all housekeeping pads and installing hollow metal doors
      • Start framing walls
    • Rough In 2nd Floor
      • Laying out walls and wall penetrations
      • Start installing MEP in Labs
  • SITE IMPROVEMENTS
    • Mechanical Enclosure M0101
      • Finish installing electrical and chilled water
      • Backfilling for electrical and chilled water
    • ODF&W Parking and Sidewalks
      • Installing erosion control and site fencing at EOW

Primary construction activities for the week of 05/13 thru 05/17 will consist of:

ZONING LEGEND

Z1 = East Commons Wing  |  Z2 = West Commons Wing  |  Z3 = West Lab Wing  |  Z4 = Middle of Lab Wing   |  Z5 = East Lab Wing

  • Roofing
    • Evacuation Ramp
      • Continue Installing handrails
      • Installing expansion joint
    • Lab High Roof West
      • Continue installing roof
  • Framing Sheeting (2nd & 3rd Floor)
    • Lab Wing West & SW Elevation:
      • Finish installing flashing at pop-outs
      • Installing temp window protection as needed
    • Lab Wing North Elevation:
      • Finish installing exterior gyp
      • Continue installing air and water barrier, window steel at pop outs, and flashing at pop outs
    • Lab Wing East Elevation
      • Installing steel studs
    • Penthouses
      • Finish installing framing
  • Framing Sheeting (1st Floor)
    • Auditorium Misc. Steel and Wind Girts
      • Finish setting Auditorium mezzanine steel
    • Auditorium East Elevation
      • Finish installing steel stud floor clips
    • Auditorium South Elevation
      • Installing steel stud floor clips
    • Auditorium West Elevation
      • Installing steel stud floor clips
    • Lab Wing West Elevation
      • Installing top / bottom track and studs
    • Lab Wing North Elevation
      • Installing top / bottom track
  • Windows and Siding
    • West Elevation
      • Finish installing vertical Z Girt and windows
      • Finish installing backer rods and caulking
      • Start installing flashing and trim
  • Site Improvements
    • Mechanical Enclosure M0101
      • Start installing electrical and chilled water
    • Ramp
      • Installing Bentonite and fluid applied waterproofing, foundation drain, back fill and grade for foam
      • Finish installing foam

Primary construction activities for the week of 05/06 thru 05/10 will consist of:

ZONING LEGEND

Z1 = East Commons Wing  |  Z2 = West Commons Wing  |  Z3 = West Lab Wing  |  Z4 = Middle of Lab Wing   |  Z5 = East Lab Wing

  • Ramp
    • Northeast Wall (Pour 6):
      • Finish closing wall formwork, pouring, and stripping.
  • Structural Steel
    • Zone 1:
      • Finish installing metal decking and closure strips by EOW.
  • Slab on Grade
    • Zone 3 (South ½ of Z3 & Z4 and 65% of Z5):
      • Installing top embeds and pouring.
    • Zone 4 (North ½ of Z3 & Z4):
      • Finish installing blockouts and edge form.
      • Installing rebar, top embeds, and pouring.
    • Zone 5:
      • Installing top embeds and pouring.
  • Roofing
    • Evacuation Ramp
      • Installing 4 x 4 angle at Eyebrow.
      • Start installing handrails.
    • East Penthouse:
      • Pouring Slab-on Foam.
  • Framing Sheeting (2nd & 3rd Floor)
    • Lab Wing West & SW Elevation:
      • Finish installing window steel at pop-outs.
      • Start installing flashings at pop-outs.
    • Lab Wing North Elevation:
      • Finish installing exterior gyp.
      • Start installing air and water barrier, window steel at pop outs, and flashings at pop outs.
    • Lab Wing South Elevation
      • Finish installing steel stud floor clips.
  • Penthouses
    • Start installing framing
  • Framing Sheeting (1st Floor)
    • Auditorium Misc. Steel and Wind Girts
      • Finish setting Auditorium mezzanine steel.
    • Auditorium North Elevation
      • Finish installing steel stud floor clips.
    • Auditorium East Elevation
      • Finish installing steel stud floor clips.
    • Windows and Siding
      • West Elevation
        • Finish installing vertical Z Girt and windows.
        • Start installing backer rods and caulking.
  • Site Improvements
    • Mechanical Enclosure M0101
      • Excavating for electrical and chilled water.
    • Ramp
      • Installing Bentonite and fluid applied waterproofing, foundation drain, back fill and grade for foam.
      • Start installing foam at EOW.

Primary construction activities for the week of 04/29 thru 05/03 will consist of:

ZONING LEGEND

Z1 = East Commons Wing  |  Z2 = West Commons Wing  |  Z3 = West Lab Wing  |  Z4 = Middle of Lab Wing   |  Z5 = East Lab Wing

  • Ramp
    • Northeast Wall (Pour 6):
      • Finish closing wall formwork, pouring, and stripping.
  • Structural Steel
    • Zone 1:
      • Finish installing metal decking and closure strips by EOW.
  • Slab on Grade
    • Zone 3 (South ½ of Z3 & Z4 and 65% of Z5):
      • Installing blockouts, edge form, electrical, and importing rock & grade.
      • Installing vapor barrier and rebar.
    • Zone 4 (North ½ of Z3 & Z4):
      • Installing electrical and final grading of native.
      • Importing rock & grade, installing blockouts, edge form, and vapor barrier.
    • Zone 5:
      • Importing rock & grade, installing blockouts, edge form, vapor barrier, and rebar.
  • Roofing
    • Evacuation Ramp
      • Cleaning embeds and roof area.
      • Installing framing on GL-8 above and North of ramp.
    • Lab Wing Main Roof:
      • West Penthouse:
        • Forming, installing rebar, and pouring curbs
        • Pouring Slab-on-Foam.
      • East Penthouse:
        • Finish welding, bolting, and decking.
        • Installing formwork, rebar, and pouring curbs.
  • Framing Sheeting
    • Lab Wing West & SW Elevation:
      • Start installing exterior gyp board, flashings at pop-outs, window steel at pop-outs, and air & water barrier.
    • Lab Wing North Elevation:
      • Continue installing steel studs.
    • Lab Wing East Elevation:
      • Finish installing steel stud floor clips.
    • Lab Wing South Elevation
      • Start installing steel stud floor clips.

 

  • Sitework & Utilities
    • Installing Potable and Fire water laterals.

Primary construction activities for the week of 04/22/19 thru 04/26/19 will consist of:

ZONING LEGEND

Z1 = East Commons Wing  |  Z2 = West Commons Wing  |  Z3 = West Lab Wing  |  Z4 = Middle of Lab Wing   |  Z5 = East Lab Wing

  • Ramp
    • Northeast Wall (Pour 6):
      • Setting wall formwork and installing wall rebar.
  • Structural Steel
    • Zone 1:
      • Finish installing metal decking and closure strips by EOW
  • Slab on Metal Deck
    • Zone 5 Level 2:
      • Curing deck for reshore removal
  • Slab on Grade
    • Zone 2:
      • Pouring slab
    • Zone 3:
      • Installing potable water, sanitary sewer & storm, and electrical
    • Zone 4:
      • Installing sanitary sewer & storm and potable water
    • Zone 5:
      • Installing potable water, sanitary sewer & storm, and electrical
  • Roofing
    • High Roof Auditorium:
      • Start installing roofing
    • Lab Wing Main Roof:
      • Forming and installing rebar at West curbs
      • West Penthouse:
        • Forming, installing rebar, and pouring curbs
      • East Penthouse:
        • Welding, bolting, and decking
        • Forming curbs
      • Lab High Roof East:
        • Continue installing roofing
    • Lab High Roof West:
      • Continue installing roofing
    •  Canopies:
      • Start installing roofing
  • Framing Sheeting
    • Lab Wing West & SW Elevation:
      • Continue installing steel studs
    • Lab Wing North Elevation:
      • Continue installing steel stud floor clips
    • Lab Wing East Elevation:
      • Continue installing steel stud floor clips
    • Miscellaneous Steel & Wind Girts
      • Auditorium:
        • Setting mezzanine steel

Primary construction activities for the week of 04/15 thru 04/19 will consist of:

ZONING LEGEND

Z1 = East Commons Wing  |  Z2 = West Commons Wing  |  Z3 = West Lab Wing  |  Z4 = Middle of Lab Wing   |  Z5 = East Lab Wing

  • Ramp
    • East Storage Room & Northeast Wall (Pour 4):
      • Closing formwork, pouring, and stripping wall
    • South Wall East Portion (Pour 5):
      • Setting wall formwork
  • Structural Steel
    • Zone 1:
      • Finish installing metal decking and closure strips early next week
  • Slab on Metal Deck
    • Zone 5 Level 3:
      • Curing deck for reshore removal
    • Zone 4 Level 2:
      • Finish installing rebar; installing top embeds and pouring deck
    • Zone 5 Level 2
      • Installing rebar, top embeds, and pouring deck
  • Slab on Grade
    • Zone 1:
      • Installing top embeds and pouring slab
    • Zone 2:
      • Installing rebar, top embeds, and pouring slab
  • Roofing
    • Lab Wing Main Roof:
      • Forming and installing rebar at West curbs
      • West Penthouse:
        • Welding, bolting, and decking
      • East Penthouse:
        • Welding, bolting, and decking
      • Lab High Roof East:
        • Continue installing roof
      • Lab High Roof West:
        • Continue installing roof
  • Framing Sheeting
    • Lab Wing West & SW Elevation:
      • Installing steel studs
    • Lab Wing North Elevation:
      • Installing steel stud floor clips
    • Lab Wing East Elevation:
      • Installing steel stud floor clips

Primary construction activities for the week of 04/08/19 thru 04/12/19 will consist of:

ZONING LEGEND

Z1 = East Commons Wing  |  Z2 = West Commons Wing  |  Z3 = West Lab Wing  |  Z4 = Middle of Lab Wing   |  Z5 = East Lab Wing

  • Ramp
    • East Storage Rm & Northeast Wall (Pour 4):
      • Closing formwork, pouring, and stripping wall
    • South Wall East Portion (Pour 5):
      • Setting wall formwork
    • Structural Steel
      • Zone 1:
        • Finish installing metal decking and closure strips
      • Slab on Metal Deck
        • Zone 4 Level 3:
          • Pouring deck and curing deck for Reshore removal
        • Zone 3 Level 2:
          • Finish installing rebar, top embeds, pouring deck, and curing deck for Reshore removal
        • Zone 5 Level 3:
          • Finish installing rebar, top embeds and QA/QC deck
        • Zone 4 Level 2:
          • Installing rebar
        • Slab on Grade
          • Zone 1:
            • Installing top embeds and pouring slab
          • Zone 2:
            • Installing vapor barrier, stripping at GL-N, and back filling at GL-N
            • Installing rebar, top embeds, and QA/QC pour
          • Roofing
            • Lab Wing High Roof:
              • Set West and East Penthouse steel
              • Set Elevator spreader tubes
              • Weld bolt and deck at West Penthouse
            • Lab High Roof East
              • Continue installing roof
            • Framing Sheeting
              • Lab Wing West & SW Elevation:
                • Installing steel stud floor clips
              • Lab Wing North Elevation
                • Installing steel stud floor clips

Primary construction activities for the week of 04/01/2019 thru 04/05/2019 will consist of the following:

ZONING LEGEND

Z1 = East Commons Wing  |  Z2 = West Commons Wing  |  Z3 = West Lab Wing  |  Z4 = Middle of Lab Wing   |  Z5 = East Lab Wing

  • Ramp
    • East Storage Rm & Northeast Wall (Pour 4):
      • Setting wall, placing rebar, and closing formwork
    • Structural Steel
      • Zone 1:
        • Install metal decking and closure strips
      • Slab on Metal Deck
        • Zone 3 Level 3:
          • Pouring and curing deck for shore removal
        • Zone 5 & ½ Zone 4 Roof:
          • Installing rebar, top embeds, and pouring deck
        • Zone 4 Level 3:
          • Installing blockouts, down embeds, shoring, rebar, and top embeds
        • Zone 3 Level 2:
          • Installing rebar
        • Zone 3 Level 2:
          • Installing blockouts, down embeds, and shoring
        • Zone 4 Level 2:
          • Installing blockouts, down embeds, and shoring
        • Zone 5 Level 2:
          • Installing blockouts and down embeds
        • Slab on Grade
          • Zone 1:
            • Installing blockouts, edge form, importing rock / grade, installing rebar, vapor barrier and top embeds
          • Zone 2:
            • Installing blockouts, edge form, importing rock / grade
            • Digging footings and pouring grout at GL-N
            • Forming, placing rebar, and pouring footing at GL-N
            • Installing vapor barrier, stripping at GL-N, and back filling at GL-N
          • Roofing
            • Lab Wing High Roof:
              • Start forming curbs and crickets at beginning of week.

Primary construction activities for the week of 03/25/2019 thru 03/29/2019:

  • Ramp
    • North Radius Wall (Pour 2):
      • Strip formwork.
    • South Wall West (Pour 3):
      • Finish setting wall and installing rebar.
  • Structural Steel
    • East Lab Wing (Z5):
      • Finish bolting, plumbing, and welding.
      • Start installing metal decking and closure strips.
  • Slab on Metal Deck
    • West Commons Wing Roof (Z2):
      • Pouring at beginning of week
    • West Lab Wing Roof (Z3 & ½ Z4):
      • Installing rebar, top embeds, and pouring deck
    • West Lab Wing L3 (Z3):
      • Installing rebar, and top embeds
    • West Lab Wing L2 (Z3)
      • Installing blockouts, down embeds and shoring
  • Slab on Grade
    • East Commons Wing:
      • Installing sanitary sewer and storm, electrical, potable water, blockouts and edge form, and grading.
    • West Commons Wing
      • Installing electrical, potable water, sanitary sewer and storm, installing block outs and edge form, and grading.
  • Roofing
    • Lab Wing High Roof:
      • Start forming curbs and crickets at end of week.