Primary construction activities for the week of 08/12 thru 08/16 will consist of the following:  

|   * = Start or Finish was delayed    |   ** Activity taking longer than projected   |

  • ROOFING
  • High Roof Auditorium:
  • Low Roof Auditorium:
    • Continue framing and sheeting at truss
    • Finish installing green gert and foam
    • Install furring
    • Begin installing window
  • Lab Wing Main Roof:
    • Conduct water test
    • Begin installing drain matt foam and rock ballast
  • Penthouses:
  • Lab High Roof West:
  • FRAMING SHEATING
    • – South Elevation:
    • Finish installing window steel
  • Commons Wing – North Elevation:
    • Finish installing temp window protection (if needed) *
  • Commons Wing – East Elevation:
  • Commons Wing – West Elevation:
    • Finish installing temp window protection if needed
  • WINDOWS & SIDING
  • Lab Wing – West Elevation:
    • Finish installing vertical siding MWC
  • Lab Wing – North Elevation:
    • Finish installing vertical siding MWC
    • Begin installing beauty cap and flashing
  • Lab Wing – East Elevation:
  • Lab Wing – South Elevation:
    • Begin installing horizontal cleat
    • Finish Installing beauty cap and flashing
  • Auditorium – East Elevation:
    • Finish installing windows
    • Install flashings and trim
    • Install backer rod and caulk
    • Begin installing insulation and horizontal cleat
  • Auditorium – South Elevation:
  • Auditorium – West Elevation:
    • Finish installing vertical Z girt and install windows
    • Begin installing flashings and trim
    • Begin backer rod and caulk
  • Auditorium – North Elevation:
    • Finish installing vertical Z girt
    • Finish Installing windows
    • Begin to install flashings and trim
    • Install backer rod and caulk
  • INTERIOR BUILDOUT
  • Rough in Framing Commons Wing
  • Begin to frame auditorium fire walls and concrete furring
  • Mechanical & Back of House:
    • Install panels/feeders in electric rooms
    • Continue to install all MEP in Mechanical spaces on the first floor
  • Rough in Remaining First Floor:
  • Finishing Framing
  • QC all MEP openings in the walls
  • Begin installing MEP in walls
  • Lab Wing Level 2 – Rough-in:
    • Finish complete balance of MEP in walls
    • Install drywall on the East and Southwest
    • Stuff and Spray STC’s Donut
  • Roof Level:
  • Install Gyp
  • Stuff and Spray Top of Wall
  • Install Ceiling OTS Insulation
  • Begin to Paint Room
  • Elevators:
  • Procure Elevator
  • Stairs:
    • Continue to finish stair interiors
  • SITE IMPROVEMENTS
  • ODF&W Parking and Sidewalks:
    • Install Irrigation
    • Finish Final Grade West and North around swales
    • Begin Installing top soil
    • Begin Installing light Poles
  • Ramp:
    • Finish backfilling up to -42”
    • Install temporary handrail posts and railing
    • Begin backfilling to elevation

Primary construction activities for the week of 08/05 thru 08/09 will consist of the following:  

|   * = Start or Finish was delayed    |   ** Activity taking longer than projected   |

  • ROOFING
  • High Roof Auditorium:
  • Low Roof Auditorium:
    • Continue installing roof
  • Lab Wing Main Roof:
    • Continue installing hot fluid-applied rubber asphalt
  • Penthouses:
  • Lab High Roof West:
  • FRAMING SHEATING
    • Lab Wing – South Elevation:
    • Finish installing flashings and window steel
  • Auditorium – North Elevation:
    • Finish installing temp window protection (if needed) *
  • Auditorium – East Elevation:Auditorium – South Elevation:
    • Finish installing Window Steel
  • Auditorium – West Elevation:
    • Finish installing temp window protection if needed
  • WINDOWS & SIDING
  • Lab Wing – West Elevation:
    • finish installing vertical siding MWC
  • Lab Wing – North Elevation:
    • Finish installing vertical siding MWC
    • Begin installing beauty cap and flashing
  • Lab Wing – East Elevation:
  • Lab Wing – South Elevation:
    • Begin installing horizontal cleat
  • Auditorium – East Elevation:
    • Install flashings and trim
    • Install backer rod and caulk
    • Begin installing insulation and horizontal cleat
  • Auditorium – South Elevation:
  • Auditorium – West Elevation:
    • Finish installing vertical Z girt and install windows
    • Begin installing flashings and trim
    • Begin back rod and caulk
  • Auditorium – North Elevation:
    • Finish installing vertical Z girt
    • Finish Installing windows
    • Begin to install flashings and trim
  • INTERIOR BUILDOUT
  • Mechanical & Back of House:
    • Install panels/feeders in electric rooms
  • Lab Wing Level 2 – Rough-in:
    • Finish Stuff and spray for STC’s
  • Roof Level:
  • Finish MEP in Walls
  • Install Gyp
  • Elevators:
  • Procure Elevator
  • Stairs:
    • Continue to finish stair interiors
  • SITE IMPROVEMENTS
  • ODFW Parking and Sidewalks:
    • Pave Parking first lift
    • Pave parking 2nd lift
    • Excavate Public Rain Garden after Paving
  • Ramp:
    • Finish backfilling up to the fluid applied weather protection
    • Install the complete bentonite and fluid applied weather protection

Primary construction activities for the week of 07/29 thru 08/02 will consist of the following:  

|   * = Start or Finish was delayed    |   ** Activity taking longer than projected   |

  • ROOFING
  • High Roof Auditorium:
  • Continue to form and pour evacuation ramp and eyebrows
  • Low Roof Auditorium:
    • Continue installing roof
  • Lab Wing Main Roof:
    • Continue installing hot fluid-applied rubber asphalt
  • Penthouses:
  • Lab High Roof West:
    • Continue installing roof
  • FRAMING SHEATING (2nd & 3rd Floor)
  • Lab Wing – South Elevation:
    • Finish installing temp window protection (if needed) *
  • FRAMING SHEATING (1st Floor)
    • Lab Wing – South Elevation:
    • Finish installing flashings and window steel
  • Auditorium – North Elevation:
    • Finish installing exterior gyp
    • Start installation of window steel as well as the air and water barrier
    • Install the flashings
  • Auditorium – East Elevation:Auditorium – South Elevation:
    • to install window steel and flashings**
  • Auditorium – West Elevation:
    • Finish Installing weather barrier, window steel, and flashings
    • Begin installing temp window protection if needed
  • WINDOWS & SIDING
  • Lab Wing – West Elevation:
    • finish installing vertical siding
  • Lab Wing – North Elevation:
    • Continue installing vertical siding
    • Begin installing beauty cap and flashing
  • Lab Wing – East Elevation:
    • Install beauty cap and flashing
  • Lab Wing – South Elevation:
    • Finish installing beauty cap and flashing
    • Begin installing horizontal cleat
  • Auditorium – East Elevation:
    • Install flashings and trim
    • Install backer rod and caulk
    • Begin installing insulation and horizontal cleat
  • Auditorium – South Elevation:
  • Auditorium – West Elevation:
    • Finish installing vertical Z girt and install windows, flashings and trim
  • Auditorium – North Elevation:
    • Begin installing vertical Z girt
  • INTERIOR BUILDOUT
  • Mechanical & Back of House:
    • Install panels/feeders in electric rooms
  • Lab Wing Level 2 – Rough-in:
    • Finish Stuff and spray for STC’s
  • Stairs:
    • Continue to finish stair interiors
  • SITE IMPROVEMENTS
  • ODF&W Parking and Sidewalks:
    • Remove asphalt and fine grade East side
  • Ramp:
    • Finish backfilling up to the fluid applied weather protection
    • Begin the complete bentonite and fluid applied weather protection

Primary construction activities for the week of 07/01 thru 07/05 will consist of the following:  

|   * = Start or Finish was delayed    |   ** Activity taking longer than projected   |

  • ROOFING
  • High Roof Auditorium:
  • Continue to form and pour evacuation ramp and eyebrows
  • Low Roof Auditorium:
    • Continue installing roof
  • Lab Wing Main Roof:
    • Continue installing hot fluid-applied rubber asphalt (tying to exterior walls)
  • Penthouses:
  • Lab High Roof West:
    • Continue installing roof
  • FRAMING SHEATING (2nd & 3rd Floor)
  • Lab Wing – South Elevation:
    • Finish installing temp window protection (if needed) *
  • FRAMING SHEATING (1st Floor)
    • Lab Wing – South Elevation:
    • Install flashings and window steel
  • Auditorium – North Elevation:
    • Finish installing steel studs
    • Start installing exterior gyp
  • Auditorium – East Elevation:
    • Start installing flashings, window steel, and temp window protection (if needed)
      • Auditorium – South Elevation:
    • to install window steel and flashings**
  • Auditorium – West Elevation:
    • Finish Installing weather barrier, window steel, and flashings
  • WINDOWS & SIDING
  • Lab Wing – West Elevation:
    • finish installing vertical siding
  • Lab Wing – North Elevation:
    • Continue installing vertical siding and windows
  • Lab Wing – East Elevation:
    • Continue installing vertical siding
    • Installing windows
    • Start installing backer rod and caulk and vertical wood cladding *
  • Lab Wing – South Elevation:
    • Continue installing windows, flashings & trim, and horizontal cleat
  • Auditorium – East Elevation:
    • Finish installing windows and vertical Z girt
  • Auditorium – South Elevation:
  • Auditorium – West Elevation:
    • Finish installing vertical Z girt and install windows flashings and trim
  • INTERIOR BUILDOUT
  • Mechanical & Back of House:
    • Install panels/feeders in electric rooms and place all house keeping pads.
  • Lab Wing Level 2 – Rough-in:
    • Install MEP in walls
    • Finish Stuff and spray for STC’s
  • SITE IMPROVEMENTS
  • ODF&W Parking and Sidewalks:
    • Fine grade the parking lot to be ready for asphalt
    • Excavating for Rain Garden #2 *

Primary construction activities for the week of 07/01 thru 07/05 will consist of the following:

|   * = Start or Finish was delayed    |   ** Activity taking longer than projected   |

  • ROOFING
  • High Roof Auditorium:
  • Continue to form and pour evacuation ramp and eyebrows
  • Low Roof Auditorium:
    • Continue installing roof
  • Lab Wing Main Roof:
    • Continue installing hot fluid-applied rubber asphalt (tying to exterior walls)
  • Penthouses:
    • Installing water barrier
  • Lab High Roof West:
    • Continue installing roof

 

  • FRAMING SHEATING (2nd & 3rd Floor)
  • Lab Wing – South Elevation:
    • Finish installing temp window protection (if needed) *

 

  • FRAMING SHEATING (1st Floor)
    • Lab Wing – South Elevation:
  • Continue to install temp window protection where needed
  • Auditorium – North Elevation:
    • Finish installing steel studs
    • Start installing exterior gyp
  • Auditorium – East Elevation:
    • Start installing flashings, window steel, and temp window protection (if needed)
      • Auditorium – South Elevation:
    • Continue to install window steel and flashings**
  • Auditorium – West Elevation:
    • Installing weather barrier, window steel, and flashings

 

  • WINDOWS & SIDING
  • Lab Wing – West Elevation:
    • finish installing vertical siding
  • Lab Wing – North Elevation:
    • Continue installing vertical siding and windows

 

 

 

 

  • Lab Wing – East Elevation:
    • Continue installing vertical siding
    • Installing windows
    • Start installing backer rod and caulk and vertical wood cladding *
  • Lab Wing – South Elevation:
    • Continue installing windows, flashings & trim, and horizontal cleat
  • Auditorium – East Elevation:
    • Start installing windows and vertical Z girt
  • Auditorium – South Elevation:
    • Continue installing vertical Z girt

 

  • INTERIOR BUILDOUT
  • Mechanical & Back of House:
    • Finish painting top out for MEP to start, start installing panels/feeders in electric rooms and place all house keeping pads.
  • Lab Wing Level 2 – Rough-in:
    • Install MEP in walls
    • Finish installing gyp top out one side of walls at duct locations
    • Continue tape and finish one side top out

 

  • SITE IMPROVEMENTS
  • ODF&W Parking and Sidewalks:
    • FRPS west and south curbs
    • Excavating for Rain Garden #2 *

 

Primary construction activities for the week of 07/01 thru 07/05 will consist of the following:

|   * = Start or Finish was delayed    |   ** Activity taking longer than projected   |

  • ROOFING
  • Low Roof Auditorium:
    • Start installing roof
  • Lab Wing Main Roof:
    • Continue installing hot fluid-applied rubber asphalt (tying to exterior walls)
  • Penthouses:
    • Installing water barrier
  • Lab High Roof West:
    • Continue installing roof

 

  • FRAMING SHEATING (2nd & 3rd Floor)
  • Lab Wing – South Elevation:
    • Finish installing temp window protection (if needed) *

 

  • FRAMING SHEATING (1st Floor)
    • Lab Wing – South Elevation:
  • Installing window steel at head & sill, flashings, and air & water barrier
  • Auditorium – North Elevation:
    • Finish installing steel studs
    • Start installing exterior gyp
  • Auditorium – East Elevation:
    • Start installing flashings, window steel, and temp window protection (if needed)
      • Auditorium – South Elevation:
    • Continue installing air & water barrier, window steel, and flashings **
  • Auditorium – West Elevation:
    • Finish installing steel studs **
    • Start installing exterior gyp *

 

  • WINDOWS & SIDING
  • Lab Wing – West Elevation:
    • Continue installing vertical wood cladding
  • Lab Wing – North Elevation:
    • Continue installing vertical wood cladding and windows

 

 

 

 

  • Lab Wing – East Elevation:
    • Finish installing horizontal cleat (pulled off to go to South side) *
    • Installing flashings and trim
    • Start installing backer rod and caulk and vertical wood cladding *
  • Lab Wing – South Elevation:
    • Continue installing windows, flashings & trim, and horizontal cleat
  • Auditorium – East Elevation:
    • Start installing windows and vertical Z girt
  • Auditorium – South Elevation:
    • Continue installing vertical Z girt

 

  • INTERIOR BUILDOUT
  • Mechanical & Back of House:
    • Finish installing gyp top out & electrical rooms, tape & finish one side top out, stuffing and spraying for STC’s, sound board at OTS ceilings, and extending down rods
  • Lab Wing Level 2 – Rough-in:
    • Finish installing gyp top out one side of walls at duct locations
    • Continue installing MEP in Labs
    • Start tape and finish one side top out

 

  • SITE IMPROVEMENTS
  • Mechanical Enclosure M0101:
    • Setting Generator and ACCH-101

 

  • ODF&W Parking and Sidewalks:
    • Start installing rebar for sidewalks and mono curbs *
    • Excavating for Rain Garden #2 *

Primary construction activities for the week of 06/24 thru 06/28 will consist of the following:

|   * = Start or Finish was delayed    |   ** Start or Finish postponed   |

  • ROOFING
  • Evacuation Ramp:
    • Install expansion joint and trench drain
    • Install hot rubber roofing (moved to Lab to strip in)
  • Lab Wing Main Roof:
    • Continue installing hot fluid-applied rubber asphalt (tying to exterior walls)
  • Penthouses:
    • Finish installing framing *
    • Start installing sheathing *
  • Lab High Roof West:
    • Continue installing roof

 

  • FRAMING SHEATING (2nd & 3rd Floor)
  • Lab Wing – South Elevation:
    • Finish installing temp window protection (if needed)

 

  • FRAMING SHEATING (1st Floor)
    • Lab Wing – West Elevation:
  • Finish installing window steel at head & sill, flashings, air & water barrier, and temp window protection (if needed)*
    • Lab Wing – East Elevation:
  • Finish installing temp window protection (if needed) *
    • Lab Wing – South Elevation:
  • Start installing exterior gyp
  • Start installing air & water barrier, flashings, and window steel at head & sill
  • Auditorium – North Elevation:
    • Continue installing steel studs
      • Auditorium – South Elevation:
    • Installing air & water barrier, window steel, and flashings
  • Auditorium – West Elevation:
    • Installing steel studs
    • Start installing exterior gyp

 

 

 

  • WINDOWS & SIDING
  • Lab Wing – West Elevation:
    • Continue installing vertical wood cladding
  • Lab Wing – North Elevation:
    • Continue installing vertical wood cladding and windows
  • Lab Wing – East Elevation:
    • Finish installing horizontal cleat
    • Installing flashings and trim
    • Start installing backer rod and caulk * and vertical wood cladding
  • Lab Wing – South Elevation:
    • Finish installing vertical Z girt
    • Continue installing windows
    • Start installing flashings and trim
  • Auditorium – South Elevation:
    • Start installing vertical Z girt

 

  • INTERIOR BUILDOUT
  • Mechanical & Back of House:
    • Start stuffing and spraying for STC’s **
    • Start tape and finish one side top out
  • Lab Wing Level 2 – Rough-in:
    • Finish framing walls (starting at E/3 clockwise)
    • Continue installing MEP in Labs
    • Start installing gyp top out one side of walls at duct locations

 

  • SITE IMPROVEMENTS
  • Mechanical Enclosure M0101:
    • Finish forming sidewalks & steps and placing sidewalk and steps
  • ODF&W Parking and Sidewalks:
    • Start forming sidewalks and mono curbs *
    • Importing rock & rough grade and excavating for Rain Garden #2

 

Primary construction activities for the week of 06/17 thru 06/21 will consist of the following:

 * = Start or Finish was delayed

  • ROOFING
  • Evacuation Ramp:
    • Finish Hot rubber roofing *
    • Form and install foam at 1st 3rd of the Ramp
  • High Roof Auditorium:
    • Start installing zinc roofing
  • Low Roof Auditorium:
    • Continue installing foam into Epic deck, insulation, and cover board
  • Lab Wing Main Roof:
    • Continue installing hot fluid-applied rubber asphalt (tying to exterior walls)
  • Penthouses:
    • Finish installing framing *
    • Start installing sheathing *
  • Lab High Roof West:
    • Continue installing roof

 

  • FRAMING SHEATING (2nd & 3rd Floor)
  • Lab Wing – South Elevation:
    • Finish installing air & water barrier
    • Continue installing flashing at pop outs, window steel at pop outs
    • Start installing temp window protection (if needed)

 

  • FRAMING SHEATING (1st Floor)
    • Lab Wing – West Elevation:
  • Finish installing window steel at head & sill, flashings, air & water barrier, and temp window protection (of needed)*
    • Lab Wing – North Elevation:
  • Finish installing window steel at window head & sill, flashings, and air & water barrier, and temp window protection (if needed) *
    • Lab Wing – East Elevation:
  • Finish installing window steel at window head & sill, flashings, and air & water barrier
  • Start installing temp window protection (if needed) *
    • Lab Wing – South Elevation:
  • Continue installing steel studs

 

 

  • Auditorium – North Elevation:
    • Continue installing steel studs
      • Auditorium – South Elevation:
    • Finish installing steel stud floor clips *
    • Continue installing steel studs *
  • Auditorium – West Elevation:
    • Finish installing steel stud floor clips *
  • Innovation Lab:
    • Installing window steel

 

  • WINDOWS & SIDING
  • Lab Wing – West Elevation:
    • Continue installing vertical wood cladding
  • Lab Wing – North Elevation:
    • Continue installing insulation & horizontal cleat, flashings & trim, vertical wood cladding, and windows
  • Lab Wing – East Elevation:
    • Installing flashings and trim
    • Start installing backer rod and caulk
  • Lab Wing – South Elevation:
    • Start installing vertical Z girt and windows

 

  • INTERIOR BUILDOUT
  • Mechanical & Back of House:
    • Finish installing in-wall MEP at Electrical Rooms *
    • Finish installing gyp top out *
    • Start stuffing and spraying for STC’s
  • Lab Wing Level 2 – Rough-in:
    • Continue installing MEP in Labs
    • Continue framing walls (starting at E/3 clockwise)

 

  • SITE IMPROVEMENTS
  • Mechanical Enclosure M0101:
    • Stripping retaining walls, damp proofing walls, back filling walls, and forming sidewalks & steps
    • Start placing sidewalk and steps at EOW
  • ODF&W Parking and Sidewalks:
    • Finish excavating for Public Rain Garden*
    • Finish balance of storm work *
    • Installing pole base and electrical for exterior light poles
    • Start forming sidewalks and mono curbs

Primary construction activities for the week of 06/10 thru 06/14 will consist of:

  • ROOFING
    • High Roof Auditorium:
      • Finish installing roof
    • Evacuation Ramp:
      • Start Hot rubber roofing *
    • Low Roof Auditorium:
      • Start installing foam into Epic deck
    • Lab Wing Main Roof:
      • Continue installing hot fluid-applied rubber asphalt (tying to exterior walls)
    • Penthouses:
      • Finish installing framing *
      • Start installing sheathing *
    • Lab High Roof West:
      • Continue installing roof

 

  • FRAMING SHEATING (2nd & 3rd Floor)
    • Lab Wing – North Elevation:
      • Finish installing temp window protection (if needed)
    • Lab Wing – East Elevation:
      • Finish installing temp window protection (if needed)
    • Lab Wing – South Elevation:
      • Start installing air & water barrier, window steel at pop outs, and flashing at pop outs

 

  • FRAMING SHEATING (1st Floor)
    • Lab Wing – West Elevation:
      • Finish installing exterior gyp board, window steel at head & sill, flashings, and air & water barrier *
    • Lab Wing – North Elevation:
      • Finish installing window steel at window head & sill, flashings, and air & water barrier, and temp window protection *
    • Lab Wing – East Elevation:
      • Finish installing exterior gyp, air & water barrier, flashings, and window steel at head & sill *
    • Lab Wing – South Elevation:
      • Start installing steel studs *
    • Auditorium – North Elevation:
      • Continue installing steel studs
    • Auditorium – South Elevation:
      • Finish installing steel stud floor clips *
      • Continue installing steel studs *
    • Auditorium – West Elevation:
      • Finish installing steel stud floor clips *

 

  • WINDOWS & SIDING
    • Lab Wing – West Elevation:
      • Continue installing siding horizontal cleat
      • Start installing vertical siding wood cladding *
    • Lab Wing – North Elevation:
      • Continue installing windows
      • Start installing flashings and trim
    • Lab Wing – East Elevation:
      • Installing windows
      • Start installing vertical z girt

 

  • INTERIOR BUILDOUT
    • Mechanical & Back of House:
      • Finish installing in-wall MEP at Electrical Rooms
      • Finish installing gyp top out
    • Lab Wing Level 2 – Rough-in:
      • Continue installing MEP in Labs
      • Continue framing walls (starting at E/3 clockwise)

 

  • SITE IMPROVEMENTS
    • Mechanical Enclosure M0101:
      • Installing rebar, pouring, and stripping Generator Pad and footings *
    • ODF&W Parking and Sidewalks:
      • Finish balance of storm work *
      • Installing Storm FC Manhole No.1 and storm chambers
      • Excavating for Public Rain Garden

 

  • SITEWORK & UTILITIES
    • Finish installing potable water and fire water laterals

 

 * = Start or Finish was delayed

Primary construction activities for the week of 06/03 thru 06/07 will consist of the following:

ZONING LEGEND

Z1 = East Commons Wing  |  Z2 = West Commons Wing  |  Z3 = West Lab Wing  |  Z4 = Middle of Lab Wing   |  Z5 = East Lab Wing

  • ROOFING
    • High Roof Auditorium:
      • Continue installing roof
    • Evacuation Ramp:
      • Finish installing handrails
      • Start Hot rubber roofing
    • Penthouses:
      • Finish installing framing
      • Installing sheathing
    • Lab High Roof West:
      • Continue installing roof
  • FRAMING SHEATING (2nd & 3rd Floor)
    • Lab Wing – North Elevation:
      • Finish installing flashings at pop outs
      • Continue installing temp window protection (if needed)
    • Lab Wing – East Elevation:
      • Finish installing flashings at pop outs and air & water barrier
    • Lab Wing – South Elevation:
      • Finish installing steel studs
      • Installing exterior gyp
  • FRAMING SHEATING (1st Floor)
    • Lab Wing – West Elevation:
      • Finish installing window steel at window head & sill, flashings, and air & water barrier
      • Start installing temp windows (if needed)
    • Lab Wing – North Elevation:
      • Finish installing exterior gyp
      • Start installing window steel at window head & sill, flashings, and air & water barrier
      • Installing temp window protection (if needed)
    • Lab Wing -East Elevation:
      • Finish installing steel studs (was postponed)
      • Installing exterior gyp
      • Start installing window steel at window head & sill, flashings, and air & water barrier at EOW
      • Installing temp window protection (if needed)
    • Lab Wing – South Elevation:
      • Start installing steel studs
    • Auditorium – South Elevation:
      • Continue installing steel studs
      • Start installing exterior gyp
    • Auditorium – West Elevation:
      • Start installing steel studs
    • Auditorium – North Elevation:
      • Start installing steel studs
  • WINDOWS & SIDING
    • Lab Wing – West Elevation:
      • Continue installing siding horizontal cleat
      • Start installing vertical siding wood cladding
    • Lab Wing – North Elevation:
      • Continue installing vertical Z girts and windows
    • Lab Wing – East Elevation:
      • Start installing vertical Z girts and windows
  • INTERIOR BUILDOUT
    • Mechanical & Back of House:
      • Finish framing walls
      • Installing in-wall MEP at Electrical Rooms
      • Start installing gyp top out
    • Lab Wing Level 2 – Rough-in:
      • Continue installing MEP in Labs
      • Start framing walls (starting at E/3 clockwise)
    • Stair 1:
      • Pouring stairs
  • SITE IMPROVEMENTS
    • Mechanical Enclosure M0101:
      • Installing rebar, pouring, and stripping Generator Pad and footings
      • Forming and installing rebar at one retaining wall
    • ODF&W Parking and Sidewalks:
      • Installing balance of storm work
      • Start installing pole base and electrical
    • Ramp:
      • Installing bentonite and fluid-applied waterproofing
  • SITEWORK & UTILITIES
    • Install potable water and fire water laterals