Primary construction activities for the week of 10/21 thru 10/25 will consist of the following:  

|   * = Start or Finish was delayed    |   ** Activity taking longer than projected   |

  • ROOFING
  • High Roof Auditorium:
  • Lab High Roof West:
    • Continue installing roofing
  • Penthouse Framing and Sheathing:
    • Installing insulation
    • Start installing scrim and hat channels
  • WINDOWS & SIDING
  • Auditorium – South Elevation:
    • Installing backer rod and caulk
    • Start installing glass and pressure bar
  • Auditorium – West Elevation:
    • Installing backer rod and caulk
    • Start installing glass and pressure bar
  • Auditorium – North Elevation:
    • Finish installing vertical siding MWC
  • Auditorium – East Elevation:
    • Finish installing beauty cap and flashing *
  • INTERIOR BUILDOUT
  • Commons Wing – Rough-in Framing:
  • Continue framing bathroom shear walls and walls
  • Finish installing MEP at 2nd floor corridors
  • Installing seat sheathing
  • Start installing balance drywall at 2nd floor walls
  • Commons Wing – Auditorium:
    • Start installing scaffolding for finish and painting
  • Lab Wing – Level 1 Rough-in Remaining:
  • Start installing overhead MEP at OTS
  • Lab Wing –  Level 2 Rough-in:
    • Continue installing cable tray at OTS and Commons
  • Lab Wing – Level 2 – Offices and Conference Rooms
    • Finish installing MEP at ceilings
    • Start installing grid
  • Lab Wing – Level 2 – Labs:
    • Finish installing grid and necessary tiles
  • Lab Wing – Level 2 – Bathrooms and Hard Lid Rooms
    • Finish installing MEP at hard lids.
    • Start installing gyp walls and lids (contingent on MEP inspection)
  • Lab Wing –  Level 3 Rough-in:
    • Continue installing MEP in Labs overhead
    • Continue framing walls at E/3 then clockwise
  • Roof – West Penthouse ELEV Equip Room:
  • Finish installing fire protection
  • Installing cover for MEP
  • Roof – East Penthouse Storage, ELEV Lobby, & Staging:
  • Finish finishing Gyp *
  • Stuff and spraying top of wall
  • Installing ceiling OTS insulation
  • Start painting the room
  • SITE IMPROVEMENTS
  • Courtyard:
    • Finish placing rock for East sidewalk

Start pouring E

Primary construction activities for the week of 10/14 thru 10/18 will consist of the following:  

|   * = Start or Finish was delayed    |   ** Activity taking longer than projected   |

  • ROOFING
  • High Roof Auditorium:
  • Lab Wing Main Roof:
    • Start installing insulation
  • Lab High Roof West:
    • Start installing roofing
  • WINDOWS & SIDING
  • Auditorium – South Elevation:
    • Finish installing windows and vertical siding MWC
  • Auditorium – West Elevation:
    • Finish installing windows*
    • Installing vertical siding MWC
  • Auditorium – North Elevation:
    • Finish installing beauty cap and flashing
    • Installing vertical siding MWC
  • Auditorium – East Elevation:
    • Finish installing beauty cap and flashing
    • Continue installing vertical siding MWC
  • INTERIOR BUILDOUT
  • Mechanical Back of House:
    • Finish installing all MEP in mechanical spaces 1st floor
  • Commons Wing – Rough-in Framing:
  • Finish MEP in Walls on 2nd floor
  • Framing bathroom shear walls and walls
  • Start installing MEP at 2nd floor corridors
  • Lab Wing – Level 1 Rough-in Remaining:
  • Finish installing OTS insulation
  • Painting top out and OTS
  • Lab Wing –  Level 2 Rough-in:
    • Finish installing Electrical in OTS Commons
    • Continue installing cable tray at OTS and Commons
  • Lab Wing – Level 2 – Offices and Conference Rooms
    • Start installing MEP at ceilings
  • Lab Wing – Level 2 – Labs:
    • Installing grid and necessary tiles
  • Lab Wing – Level 2 – Bathrooms and Hard Lid Rooms
    • Start framing hard lids
    • Start installing MEP at hard lids.
  • Lab Wing –  Level 3 Rough-in:
    • Start installing MEP in Labs overhead
    • Start framing walls at E/3 then clockwise
  • Roof – West Penthouse ELEV Equip Room:
  • Installing elevator equipment
  • Start installing fire protection
  • Roof – East Penthouse Storage, ELEV Lobby, & Staging:
  • Installing Gyp *
  • Start finishing Gyp *
  • SITE IMPROVEMENTS
  • Courtyard:
    • Pour 5 Heavy (FRPS) (Form, Rebar, Pour, Strip (FRPS))*
    • Pour 6 Heavy (FRPS) *
    • Start placing rock for East sidewalk

Primary construction activities for the week of 10/07 thru 10/11 will consist of the following:  

|   * = Start or Finish was delayed    |   ** Activity taking longer than projected   |

  • ROOFING
  • High Roof Auditorium:
  • Lab Wing Main Roof:
    • All topping poured. Start installing Z Girt next week.
  • WINDOWS & SIDING
  • Auditorium – South Elevation:
    • Start installing windows
  • Auditorium – West Elevation:
    • Finish installing windows
    • Start installing backer rod and caulk
  • Auditorium – North Elevation:
    • Finish installing beauty cap and flashing
    • Installing vertical siding MWC
  • INTERIOR BUILDOUT
  • Commons Wing – Rough-in Framing:
  • Finish MEP above and below Mezz decking
  • Start framing 1st floor walls
  • Start MEP in Walls on 2nd floor *
  • Lab Wing – Level 1 Rough-in Remaining:
  • Finish stuff and spray at head of walls
  • Installing OTS insulation
  • Lab Wing –  Level 2 Rough-in:
  • Finish installing Duct Work in OTS Commons and Offices
    • Continue installing Electrical in OTS Commons
    • Continue installing cable tray at OTS and Commons
  • Lab Wing –  Level 3 Rough-in:
    • Start laying out walls and wall penetrations
  • Roof – West Penthouse ELEV Equip Room:
  • Continue installing Fire Protection *
  • Roof – East Penthouse Storage, ELEV Lobby, & Staging:
  • Installing Gyp *
  • Start finishing Gyp *
  • SITE IMPROVEMENTS
  • Courtyard:
    • Finishing Pour 4 (Form, Rebar, Pour, Strip (FRPS))
    • Finishing Pour 5 Heavy (FRPS)
    • Finishing Pour 6 Heavy (FRPS)

Primary construction activities for the week of 09/30 thru 10/5 will consist of the following:  

|   * = Start or Finish was delayed    |   ** Activity taking longer than projected   |

  • ROOFING
  • High Roof Auditorium:
  • Lab Wing Main Roof:
    • Rebar installed, pouring next week
  • WINDOWS & SIDING
  • Lab Wing – North Elevation:
  • Lab Wing – South Elevation:
  • Auditorium – East Elevation:
  • Auditorium – South Elevation:
  • Auditorium – West Elevation:
    • Finish installing vertical siding MWC
    • Install glass and pressure bar
    • Install beauty cap and flashing
  • Auditorium – North Elevation:
    • Start installing glass and pressure bar *
    • Start installing insulation and horizontal cleat
    • Install glass and pressure bar
    • Install beauty cap and flashing
  • INTERIOR BUILDOUT
  • Commons Wing – Rough-in Framing:
  • MEP in Walls on 2nd floor *
  • Start installing upper seating framing
  • Install bathroom carriers
  • Frame first floors
  • MEP above and below  Mezz decking
  • Mechanical & Back of House:
    • Continue to install all MEP in Mechanical spaces on the 1st floor
  • Lab Wing – Rough in Remaining First Floor:
  • Finish installing Top Out
  • Start top out finish *
  • Lab Wing –  Level 2 Rough-in:
    • to install Hydronic piping in OTS Commons
    • Fire Protection in OTS commons
    • Continue to install Electrical in OTS Commons
    • Continue to install Plumbing in OTS Commons
    • Continue to install Duct Work in OTS Commons and Offices
    • Finishing all paint on 2nd floor *
  • Roof – West Penthouse ELEV Equip Room:
  • Installing Fire Protection *
  • Install cover for MEP
  • Roof – East Penthouse Stor, ELEV Lobby & Staging:
  • Install Gyp *
  • Start finishing Gyp *
  • Install ceiling ots insulation
  • Start painting room
  • SITE IMPROVEMENTS
  • Ramp:
  • Courtyard:
    • Finish grade
    • Begin pours

Primary construction activities for the week of 09/23 thru 09/27 will consist of the following:  

|   * = Start or Finish was delayed    |   ** Activity taking longer than projected   |

  • ROOFING
  • High Roof Auditorium:
  • Lab Wing Main Roof:
    • Rebar installed, pouring next week
  • WINDOWS & SIDING
  • Lab Wing – North Elevation:
  • Continue installing Curtain Wall Center
  • Lab Wing – South Elevation:
    • Finishing installing MWC *
  • Auditorium – East Elevation:
    • Finish installing vertical siding MWC
    • Installing beauty cap and flashing
  • Auditorium – South Elevation:
  • Auditorium – West Elevation:
  • Finish installing vertical siding MWC
  • Auditorium – North Elevation:
    • Installing flashings and trim
    • Installing backer rod and caulk *
    • Start installing glass and pressure bar *
    • Start installing insulation and horizontal cleat
  • INTERIOR BUILDOUT
  • Commons Wing – Rough-in Framing:
  • Finish installing MEP and fire Protection in auditorium high ceiling
  • Start MEP in Walls on 2nd floor *
  • Finish installing MEP in Soffit and wall above
  • Start installing bathroom carriers *
  • Start installing metal decking and  replace beams
  • Start building soffit hard lid, duct, beam, and walls
  • Start installing upper seating framing
  • Mechanical & Back of House:
    • Finish installing panels/feeders in electric rooms
    • Continue to install all MEP in Mechanical spaces on the 1st floor
  • Lab Wing – Rough in Remaining First Floor:
  • Finish installing Top Out
  • Start top out finish *
  • Lab Wing –  Level 2 Rough-in:
    • to install Hydronic piping in OTS Commons
    • Fire Protection in OTS commons
    • Continue to install Electrical in OTS Commons
    • Continue to install Plumbing in OTS Commons
    • Continue to install Duct Work in OTS Commons and Offices
    • Finishing all paint on 2nd floor *
  • Roof – West Penthouse ELEV Equip Room:
  • Finish installing Elevator equipment *
  • Installing Fire Protection *
  • Roof – East Penthouse Stor, ELEV Lobby & Staging:
  • Install Gyp *
  • Start finishing Gyp *
  • SITE IMPROVEMENTS
  • Ramp:
    • Install rebar
    • Placing 2nd half of Ramp slab
    • Begin Pouring ramp slab
    • Start installing trench drain
  • Courtyard:
    • Installing Storm and Electrical
    • Start cutting to grade

Primary construction activities for the week of 09/16 thru 09/20 will consist of the following:  

|   * = Start or Finish was delayed    |   ** Activity taking longer than projected   |

  • ROOFING
  • High Roof Auditorium:
  • Low Roof Auditorium:
    • Finish installing siding
    • Begin Installing Zinc Roofing
  • Lab Wing Main Roof:
    • Continue to install the exterior concrete topping slabs
  • Penthouses:
  • Lab High Roof West:
  • FRAMING SHEATING
    • – South Elevation:
  • Commons Wing – North Elevation:
  • Commons Wing – East Elevation:
  • Commons Wing – West Elevation:
  • WINDOWS & SIDING
  • Lab Wing – West Elevation:
  • Lab Wing – North Elevation:
  • Install Curtain Wall Center
  • Lab Wing – East Elevation:
  • Lab Wing – South Elevation:
  • Auditorium – East Elevation:
    • Finish installing windows
    • Begin Backer rod and caulk
  • Auditorium – South Elevation:
  • Auditorium – West Elevation:
  • Continue installing vertical siding MWC
  • Auditorium – North Elevation:
    • Finish installing windows
    • Backer rod and caulk
    • Begin installing glass and pressure bar
    • Install flashing and trim
  • INTERIOR BUILD-OUT
  • Rough in Framing Commons Wing
  • Begin build soffit and wall above and below
  • Begin to install top out for MEP to start 2nd floor
  • Begin installing MEP and fire Protection in auditorium high ceiling
  • Begin MEP in Walls on 2nd floor
  • MEP soffit and wall above
  • Install Bathroom carriers
  • Begin to install bathroom carriers
  • Mechanical & Back of House:
    • Install panels/feeders in electric rooms
    • Continue to install all MEP in Mechanical spaces on the first floor
  • Rough in Remaining First Floor:
  • Install Top Out
  • Begin top out finish
  • Lab Wing Level 2 – Rough-in:
    • to install hydronic piping in OTS Commons
    • fire protection in OTS commons
    • Continue to install electrical in OTS Commons
    • Continue to install Plumbing in OTS Commons
    • Continue to install Duct Work in OTS Commons
    • Finish all paint on 2nd floor
  • Level 3:
  • Roof Level:
  • Finish MEP in walls
  • Finish installing Elevator equipment
  • Begin Installing fire protection
  • Install Gyp
  • Finish Gyp
  • Elevators:
  • Stairs:
  • SITE IMPROVEMENTS
  • ODFW Parking and Sidewalks:
  • Ramp:
    • Install edge form and rebar
    • Begin Pouring ramp slab
    • Install storm channel and electrical
    • Begin cutting to grade

Primary construction activities for the week of 09/09 thru 09/13 will consist of the following:  

|   * = Start or Finish was delayed    |   ** Activity taking longer than projected   |

  • ROOFING
  • High Roof Auditorium:
  • Low Roof Auditorium:
    • Finish installing siding
    • Begin Installing Zinc Roofing
  • Lab Wing Main Roof:
    • Continue to install the exterior concrete topping slabs
  • Penthouses:
  • Lab High Roof West:
  • FRAMING SHEATING
    • – South Elevation:
  • Commons Wing – North Elevation:
  • Commons Wing – East Elevation:
  • Commons Wing – West Elevation:
  • WINDOWS & SIDING
  • Lab Wing – West Elevation:
  • Lab Wing – North Elevation:
  • Lab Wing – East Elevation:
  • Lab Wing – South Elevation:
  • Auditorium – East Elevation:
    • Finish installing windows
    • Begin Backer rod and caulk
  • Auditorium – South Elevation:
  • Auditorium – West Elevation:
  • Continue installing vertical siding MWC
  • Auditorium – North Elevation:
    • Finish installing windows
    • Finish backer rod and caulk
    • Begin installing glass and pressure bar
    • Finish installing Z Girt
    • Install flashings and trim
  • INTERIOR BUILDOUT
  • Rough in Framing Commons Wing
  • Finish installing head of wall at fire walls
  • Begin build soffit and wall above and below
  • Finish fr4aming 2nd floor walls
  • Begin to install top out for MEP to start 2nd floor
  • Begin installing MEP and fire Protection in auditorium high ceiling
  • Mechanical & Back of House:
    • Install panels/feeders in electric rooms
    • Continue to install all MEP in Mechanical spaces on the first floor
  • Rough in Remaining First Floor:
  • Install Top Out
  • Lab Wing Level 2 – Rough-in:
    • fire protection in OTS commons
    • Begin to install electrical in OTS Commons
    • Begin to install Plumbing in OTS Commons
    • Begin to install Duct Work in OTS Commons
    • Continue to finish east and southwest
    • Begin to finish balance of walls
  • Level 3:
  • Roof Level:
  • Finish MEP in walls
  • Install Elevator equipment
  • Install Gyp
  • Finish Gyp
  • Elevators:
  • Stairs:
  • SITE IMPROVEMENTS
  • ODFW Parking and Sidewalks:
  • Ramp:
    • Install Storm and Electrical in Courtyard

Primary construction activities for the week of 09/01 thru 09/05 will consist of the following:  

|   * = Start or Finish was delayed    |   ** Activity taking longer than projected   |

  • ROOFING
  • High Roof Auditorium:
  • Low Roof Auditorium:
    • Continue installing siding
  • Lab Wing Main Roof:
    • Continue to install the exterior concrete topping slabs
  • Penthouses:
  • Lab High Roof West:
  • FRAMING SHEATING
    • – South Elevation:
  • Commons Wing – North Elevation:
  • Commons Wing – East Elevation:
  • Commons Wing – West Elevation:
  • WINDOWS & SIDING
  • Lab Wing – West Elevation:
  • Lab Wing – North Elevation:
  • Lab Wing – East Elevation:
  • Lab Wing – South Elevation:
    • Finish installing vertical siding MWC
  • Auditorium – East Elevation:
    • Install beauty cap and flashing
  • Auditorium – South Elevation:
  • Auditorium – West Elevation:
    • Finish  installing glass and pressure bar
    • Finish installing insulation and horizontal cleat
    • Begin installing beauty cap and flashing
    • Begin installing vertical siding MWC
  • Auditorium – North Elevation:
    • Install beauty cap and flashing
    • Finish installing vertical siding MWC
  • INTERIOR BUILD OUT
  • Rough in Framing Commons Wing
  • Finish the MEP fire walls
  • Install balance drywall 2nd floor walls
  • Mechanical & Back of House:
    • Install panels/feeders in electric rooms
    • Continue to install all MEP in Mechanical spaces on the first floor
  • Rough in Remaining First Floor:
  • Finish installing MEP in walls
  • Lab Wing Level 2 – Rough-in:
    • fire protection in OTS commons
    • Begin to install electrical in OTS Commons
    • Begin to install Plumbing in OTS Commons
    • Begin to install Duct Work in OTS Commons
    • Begin to paint East and Southwest
    • Begin to finish balance of walls
  • Level 3:
  • Continue MEP in labs
  • Roof Level:
  • Install fire protection and cover for MEP
  • Begin MEP in walls
  • Elevators:
  • Stairs:
    • Continue to finish stair interiors
  • SITE IMPROVEMENTS
  • ODFW Parking and Sidewalks:
  • Ramp:
    • Continue to install Rock at Storm Channel
    • Cut to grade

Primary construction activities for the week of 08/26 thru 08/30 will consist of the following:  

|   * = Start or Finish was delayed    |   ** Activity taking longer than projected   |

  • ROOFING
  • High Roof Auditorium:
  • Low Roof Auditorium:
    • Begin installing siding
  • Lab Wing Main Roof:
    • Finish installing drain mat foam and rock ballast
    • Begin to install the exterior concrete topping slabs
  • Penthouses:
  • Lab High Roof West:
  • FRAMING SHEATING
    • – South Elevation:
  • Commons Wing – North Elevation:
  • Commons Wing – East Elevation:
  • Commons Wing – West Elevation:
  • WINDOWS & SIDING
  • Lab Wing – West Elevation:
  • Lab Wing – North Elevation:
    • Finish installing beauty cap and flashing
  • Lab Wing – East Elevation:
  • Lab Wing – South Elevation:
    • Begin installing vertical siding MWC
  • Auditorium – East Elevation:
    • Install glass and pressure bar
    • Install vertical siding MWC
    • Finish installing insulation and horizontal cleat
  • Auditorium – South Elevation:
  • Auditorium – West Elevation:
    • Finish installing flashing and trim
    • Finish Installing backer rod and caulk
    • Begin installing glass and pressure bar
    • Begin installing insulation and horizontal cleat
  • Auditorium – North Elevation:
    • Finish installing backer rod and caulk
    • Finish installing insulation and horizontal cleat
    • Begin installing vertical siding MWC
  • INTERIOR BUILD-OUT
  • Rough in Framing Commons Wing
  • Finish framing the auditorium fire walls and concrete furring
  • Begin the MEP fire walls
  • Begin framing the 2nd floor walls
  • Install MEP in 2nd floor corridors
  • Mechanical & Back of House:
    • Install panels/feeders in electric rooms
    • Continue to install all MEP in Mechanical spaces on the first floor
  • Rough in Remaining First Floor:
  • Finish installing MEP in walls
  • Lab Wing Level 2 – Rough-in:
    • Extend Down Rods
    • Finish East and SW
    • Finish balance of walls
    • Finish the Drywall balance of wall labs
  • Level 3:
  • Install HM doors
  • Begin MEP in labs
  • Roof Level:
  • Install Elevator Equipment
  • Elevators:
  • Stairs:
    • Continue to finish stair interiors
  • SITE IMPROVEMENTS
  • ODFW Parking and Sidewalks:
    • Finish Punch Phase one Civil
  • Ramp:
    • Continue to install Rock at Storm Channel
    • Excavate swales and build dune

Primary construction activities for the week of 08/19 thru 08/23 will consist of the following:  

|   * = Start or Finish was delayed    |   ** Activity taking longer than projected   |

  • ROOFING
  • High Roof Auditorium:
  • Low Roof Auditorium:
    • Finish installing furring
    • Install windows
  • Lab Wing Main Roof:
    • Continue installing drain mat foam and rock ballast\
    • Set AHU-401 & EF401 and 402
  • Penthouses:
  • Lab High Roof West:
  • FRAMING SHEATING
    • – South Elevation:
    • Finish installing window steel
  • Commons Wing – North Elevation:
    • Finish installing temp window protection (if needed) *
  • Commons Wing – East Elevation:
  • Commons Wing – West Elevation:
    • Finish installing temp window protection if needed
  • WINDOWS & SIDING
  • Lab Wing – West Elevation:
  • Lab Wing – North Elevation:
    • Finish installing vertical siding MWC
    • Begin installing beauty cap and flashing
  • Lab Wing – East Elevation:
  • Lab Wing – South Elevation:
    • Begin installing horizontal cleat
    • Finish Installing beauty cap and flashing
  • Auditorium – East Elevation:
    • Finish installing windows
    • Install flashings and trim
    • Install backer rod and caulk
    • Begin installing insulation and horizontal cleat
  • Auditorium – South Elevation:
  • Auditorium – West Elevation:
    • Finish installing vertical Z girt and install windows
    • Begin installing flashing and trim
    • Begin backer rod and caulk
  • Auditorium – North Elevation:
    • Finish Installing windows
    • Begin to install flashing and trim
    • Install backer rod and caulk
    • Begin installing insulation and horizontal cleat
  • INTERIOR BUILD-OUT
  • Rough in Framing Commons Wing
  • Begin to frame the auditorium fire walls and concrete furring
  • Finish the MEP walls on the 2nd floor
  • Mechanical & Back of House:
    • Install panels/feeders in electric rooms
    • Continue to install all MEP in Mechanical spaces on the first floor
  • Rough in Remaining First Floor:
  • Begin installing MEP in walls
  • Lab Wing Level 2 – Rough-in:
    • Install sound board at OTS Ceilings Donut
    • Paint Top out for MEP to start Donut
    • Finish East and SW
    • Finish the Complete balance of MEP in the walls
    • Begin the Drywall balance of wall labs
  • Roof Level:
  • Finish Painting Room
  • Install the Disconnects
  • Begin Installing Elevator equipment
  • Elevators:
  • Stairs:
    • Continue to finish stair interiors
  • SITE IMPROVEMENTS
  • ODFW Parking and Sidewalks:
    • Install signs and stripe
    • Begin Punch Phase one Civil
  • Ramp:
    • Finish back-filling up to Elevation
    • Begin to install Rock at Storm Channel