Primary construction activities for the week of 05/25 thru 05/29 will consist of the following:
| * = Activity delayed |
- ROOFING
- Install Tsunami Signs:
- No Activities this Upcoming Week.
- INTERIOR BUILDOUT
- Lab Wing – Level 1 – Commons Spaces, Café, & Fireplace:
- Finish Third Coat Delay
- Andersen Punch
- Correct Punch
- O/A Punch
- Common Spaces All Levels – Stair Three Finish Work:
- No Activities this Upcoming Week.
- Commons Wing – Level 1 – Bathrooms & A/V Hard Lid Rooms:
- Complete Punch
- O/A Punch
- Complete O/A Punch
- Lab Wing – Level 1 – Bathrooms and Hard Lid Rooms:
- Complete Punch
- O/A Punch
- Complete O/A Punch
- Lab Wing – Level 2 – Bathrooms and Hard Lid Rooms:
- Complete Punch
- O/A Punch
- Complete O/A Punch
- Lab Wing – Level 3 – Bathrooms and Hard Lid Rooms:
- Complete Punch
- O/A Punch
- Complete O/A Punch
- Commons Wing – Auditorium:
- Cure out Wood Floor and Seating
- Commons Wing – Innovation Lab:
- Finish Installing Lights and MEP Finishes*
- Andersen Punch
- Commons Wing – Level 2 – Design 3D & Art Studio:
- Correct O/A Punch
- Commons Wing – Level 2 – Sound Control & Vestibules:
- Install New Cooling to SC Room
- Commons Wing – Level 2 – Perforated Drywall & Sound Control:
- Install Expansion Joints in Floor
- Lab Wing – Level 1 – Classrooms:
- Third Coat Delay
- Andersen Punch
- Correct Andersen Punch
- Lab Wing – Level 2 – Common Spaces:
- Andersen Punch*
- Lab Wing – Level 2 – Lab Area:
- No Activities this Upcoming Week.
- Lab Wing – Level 2 – Offices and Conference Rooms:
- Correct O/A Punch
- Common Spaces – Level 3
- Install Ceiling Sound Baffles
- Andersen Punch
- Lab Wing – Level 3
- Paint Third Coat Delay
- Install Balance of Tiles
- Offices and Conference Rooms – Level 3
- Andersen Punch
- East Penthouse Storage – Roof Level
- O/A Punch
- INTERIOR BUILDOUT
- Elevator 1:
- Finish Workman’s Service Use
- Elevator 2:
- Finish Installing Elevator*
- SITE IMPROVEMENTS
- Phase 3 West Site Improvements:
No Activities this Upcoming Week