Primary construction activities for the week of 05/25 thru 05/29 will consist of the following:  

|   * = Activity delayed    |

  • ROOFING
  • Install Tsunami Signs:
    • No Activities this Upcoming Week.
  • INTERIOR BUILDOUT
  • Lab Wing – Level 1 – Commons Spaces, Café, & Fireplace:
    • Finish Third Coat Delay
    • Andersen Punch
    • Correct Punch
    • O/A Punch
  • Common Spaces All Levels – Stair Three Finish Work:
    • No Activities this Upcoming Week.
  • Commons Wing – Level 1 – Bathrooms & A/V Hard Lid Rooms:
    • Complete Punch
    • O/A Punch
    • Complete O/A Punch
  • Lab Wing – Level 1 – Bathrooms and Hard Lid Rooms:
    • Complete Punch
    • O/A Punch
    • Complete O/A Punch
  • Lab Wing – Level 2 – Bathrooms and Hard Lid Rooms:
    • Complete Punch
    • O/A Punch
    • Complete O/A Punch
  • Lab Wing – Level 3 – Bathrooms and Hard Lid Rooms:
    • Complete Punch
    • O/A Punch
    • Complete O/A Punch
  • Commons Wing – Auditorium:
    • Cure out Wood Floor and Seating
  • Commons Wing – Innovation Lab:
    • Finish Installing Lights and MEP Finishes*
    • Andersen Punch
  • Commons Wing – Level 2 – Design 3D & Art Studio:
    • Correct O/A Punch
  • Commons Wing – Level 2 – Sound Control & Vestibules:
    • Install New Cooling to SC Room
  • Commons Wing – Level 2 – Perforated Drywall & Sound Control:
    • Install Expansion Joints in Floor
  • Lab Wing – Level 1 – Classrooms:
    • Third Coat Delay
    • Andersen Punch
    • Correct Andersen Punch
  • Lab Wing – Level 2 – Common Spaces:
    • Andersen Punch*
  • Lab Wing – Level 2 – Lab Area:
    • No Activities this Upcoming Week.
  • Lab Wing – Level 2 – Offices and Conference Rooms:
    • Correct O/A Punch
  • Common Spaces – Level 3
    • Install Ceiling Sound Baffles
    • Andersen Punch
  • Lab Wing – Level 3
    • Paint Third Coat Delay
    • Install Balance of Tiles
  • Offices and Conference Rooms – Level 3
    • Andersen Punch
  • East Penthouse Storage – Roof Level
    • O/A Punch
  • INTERIOR BUILDOUT
  • Elevator 1:
    • Finish Workman’s Service Use
  • Elevator 2:
    • Finish Installing Elevator*
  • SITE IMPROVEMENTS
  • Phase 3 West Site Improvements:

No Activities this Upcoming Week

Primary construction activities for the week of 05/25 thru 05/29 will consist of the following:  

|   * = Activity delayed    |

  • ROOFING
  • Install Tsunami Signs:
    • No Activities this Upcoming Week.
  • INTERIOR BUILDOUT
  • Lab Wing – Level 1 – Commons Spaces, Café, & Fireplace:
    • Fireplace Install and Grout
    • Begin Third Coat Delay*
    • Finish Installing Wood Ceiling*
    • Finish Electrical Trim Out
  • Common Spaces All Levels – Stair Three Finish Work:
    • No Activities this Upcoming Week.
  • Commons Wing – Level 1 – Bathrooms & A/V Hard Lid Rooms:
    • Complete Punch
    • O/A Punch
    • Complete O/A Punch
  • Lab Wing – Level 1 – Bathrooms and Hard Lid Rooms:
    • Complete Punch
    • O/A Punch
    • Complete O/A Punch
  • Lab Wing – Level 2 – Bathrooms and Hard Lid Rooms:
    • Complete Punch
    • O/A Punch
    • Complete O/A Punch
  • Lab Wing – Level 3 – Bathrooms and Hard Lid Rooms:
    • Complete Punch
    • O/A Punch
    • Complete O/A Punch
  • Commons Wing – Auditorium:
    • Finish Installing Wood Flooring
  • Commons Wing – Innovation Lab:
    • Finish Installing Lights and MEP Finishes*
    • Andersen Punch
  • Commons Wing – Level 2 – Design 3D & Art Studio:
    • Correct Andersen Punch
    • O/A Punch
    • Correct O/A Punch
  • Commons Wing – Level 2 – Sound Control & Vestibules:
    • Install Counter Tops
    • Install Carpet
    • Install Base
  • Lab Wing – Level 1 – Classrooms:
    • Correct Andersen Punch
    • O/A Punch
  • Lab Wing – Level 2 – Common Spaces:
    • Andersen Punch*
  • Lab Wing – Level 2 – Lab Area:
    • Finish Painting Third Coat Delay
  • Lab Wing – Level 2 – Offices and Conference Rooms:
    • Correct Andersen Punch
    • O/A Punch
    • Correct O/A Punch
  • Common Spaces – Level 3
    • Third Coat Delay
  • Lab Wing – Level 3
    • Install Base
  • Offices and Conference Rooms – Level 3
    • Andersen Punch
  • INTERIOR BUILDOUT
  • Elevator 1:
    • Continue Workman’s Service Use
  • Elevator 2:
    • Continue Installing Elevator*
  • SITE IMPROVEMENTS
  • Phase 3 West Site Improvements:
    • Cure AC
    • Install Striping and Signage

Primary construction activities for the week of 05/15 thru 05/22 will consist of the following:  

|   * = Activity delayed    |

  • ROOFING
  • Install Tsunami Signs:
    • No Activities this Upcoming Week.
  • INTERIOR BUILDOUT
  • Lab Wing – Level 1 – Commons Spaces, Café, & Fireplace:
    • Install Base*
    • Fireplace Install and Grout
    • Paint Conduit and Hangers for Wood Ceiling
    • Begin Third Coat Delay*
    • Install Wood Ceiling
  • Common Spaces All Levels – Stair Three Finish Work:
    • Finish Installing Panels
  • Commons Wing – Level 1 – Bathrooms & A/V Hard Lid Rooms:
    • Complete Punch
    • O/A Punch
    • Complete O/A Punch
  • Lab Wing – Level 1 – Bathrooms and Hard Lid Rooms:
    • Complete Punch
    • O/A Punch
    • Complete O/A Punch
  • Lab Wing – Level 2 – Bathrooms and Hard Lid Rooms:
    • Complete Punch
    • O/A Punch
    • Complete O/A Punch
  • Lab Wing – Level 3 – Bathrooms and Hard Lid Rooms:
    • Complete Punch
    • O/A Punch
    • Complete O/A Punch
  • Commons Wing – Auditorium:
    • Continue Installing Wood Flooring
  • Commons Wing – Innovation Lab:
    • Finish Installing Lights and MEP Finishes*
  • Commons Wing – Level 2 – Design 3D & Art Studio:
    • Correct Andersen Punch
    • O/A Punch
    • Correct O/A Punch
  • Commons Wing – Level 2 – Sound Control & Vestibules:
    • Install ACT Tiles
    • Install Counter Tops
    • Install Carpet
    • Install Base
  • Lab Wing – Level 1 – Classrooms:
    • Correct Andersen Punch
    • O/A Punch
    • Correct O/A Punch
  • Lab Wing – Level 2 – Common Spaces:
    • Third Coat Delay*
    • Andersen Punch*
  • Lab Wing – Level 2 – Lab Area:
    • Third Coat Delay
  • Lab Wing – Level 2 – Offices and Conference Rooms:
    • Correct O/A Punch
  • Common Spaces – Level 3
    • Install Ceiling Tectum Panels and Sound Baffles
  • Lab Wing – Level 3
    • Install MEP In Cabinets and Countertops
    • Install Base
    • Finish Electrical
  • Offices and Conference Rooms – Level 3
    • Paint Third Coat Delay*
  • INTERIOR BUILDOUT
  • Elevator 1:
    • Continue Workman’s Service Use
  • Elevator 2:
    • Continue Installing Elevator*
  • SITE IMPROVEMENTS
  • Phase 3 West Site Improvements:
    • Cure AC
    • Cut Out & Pour Manhole Rings

Primary construction activities for the week of 05/11 thru 05/15 will consist of the following:  

|   * = Activity delayed    |

  • ROOFING
  • Install Tsunami Signs:
    • No Activities this Upcoming Week.
  • INTERIOR BUILDOUT
  • Lab Wing – Level 1 – Commons Spaces, Café, & Fireplace:
    • Install Wood Ceiling and Lighting
    • Install Base*
    • Begin Third Coat Delay
  • Common Spaces All Levels – Stair Three Finish Work:
    • Install Outside Panels
  • Commons Wing – Level 1 – Bathrooms & A/V Hard Lid Rooms:
    • Complete Punch
    • O/A Punch
    • Complete O/A Punch
  • Lab Wing – Level 1 – Bathrooms and Hard Lid Rooms:
    • Complete Punch
    • O/A Punch
    • Complete O/A Punch
  • Lab Wing – Level 2 – Bathrooms and Hard Lid Rooms:
    • Complete Punch
    • O/A Punch
    • Complete O/A Punch
  • Lab Wing – Level 3 – Bathrooms and Hard Lid Rooms:
    • Complete Punch
    • O/A Punch
  • Commons Wing – Auditorium:
    • Continue Installing Wood Flooring
  • Commons Wing – Innovation Lab:
    • Start Installing Lights and MEP Finishes*
  • Commons Wing – Level 2 – Design 3D & Art Studio:
    • Correct Andersen Punch
    • O/A Punch
    • Correct O/A Punch
  • Commons Wing – Level 2 – Sound Control & Vestibules:
    • Finish Installing MEP in Sound Control Ceiling*
    • Inspect MEP in Sound Control Ceiling*
    • Install ACT Tiles
    • Install Counter Tops
  • Commons Wing – Level 2 – Perforated Drywall Sound Control:
    • No Activities this Upcoming Week.
  • Lab Wing – Level 1 – Classrooms:
    • Correct Andersen Punch
    • O/A Punch
    • Correct O/A Punch
  • Lab Wing – Level 2 – Common Spaces:
    • Third Coat Delay
    • Andersen Punch
  • Lab Wing – Level 2 – Lab Area:
    • Finish Install of Electrical
  • Lab Wing – Level 2 – Offices and Conference Rooms:
    • Correct Andersen Punch
    • O/A Punch
    • Correct O/A Punch
  • Common Spaces – Level 3
    • Finish Installing Floor Boxes and Finish Electrical
  • Lab Wing – Level 3
    • Install Balance of Tiles and Clouds
    • Install Lab Counter Tops
  • Offices and Conference Rooms – Level 3
    • Paint Third Coat Delay
  • Roof Level – East Penthouse, Lobby and Staging
    • No Activities this Upcoming Week.
  • INTERIOR BUILDOUT
  • Elevator 1:
    • Continue Workman’s Service Use
  • Elevator 2:
    • Continue Installing Elevator*
  • SITE IMPROVEMENTS
  • Phase 3 West Site Improvements:
    • Finish all Landscaping
    • Remove Onsite Storage
    • Fine Grade for AC
    • ADA Ramps and Walks
    • Install AC
    • Cut Out & Pour Manhole Rings

Primary construction activities for the week of 05/04 thru 05/08 will consist of the following:  

|   * = Activity delayed    |

  • ROOFING
  • Install Tsunami Signs:
    • Finish to Reinstall Siding
    • Install Signs
  • INTERIOR BUILDOUT
  • Lab Wing – Level 1 – Commons Spaces, Café, & Fireplace:
    • Install Wood Ceiling and Lighting
    • Install Base*
    • Finish Electrical Trim Out
  • Common Spaces All Levels – Stair Three Finish Work:
    • Finish Installing Wood Panels*
  • Commons Wing – Level 1 – Bathrooms & A/V Hard Lid Rooms:
    • Complete Punch
    • O/A Punch
    • Complete O/A Punch
  • Lab Wing – Level 1 – Bathrooms and Hard Lid Rooms:
    • Complete Punch
    • O/A Punch
    • Complete O/A Punch
  • Lab Wing – Level 2 – Bathrooms and Hard Lid Rooms:
    • Complete Punch
    • O/A Punch
    • Complete O/A Punch
  • Lab Wing – Level 3 – Bathrooms and Hard Lid Rooms:
    • Install Electrical Trim Out*
    • Install Toilet Accessories
    • Andersen Punch
    • Complete Punch
  • Commons Wing – Auditorium:
    • Continue Installing Wood Flooring
  • Commons Wing – Innovation Lab:
    • Start Installing Lights and MEP Finishes*
  • Commons Wing – Level 2 – Design 3D & Art Studio:
    • Correct Andersen Punch
    • O/A Punch
    • Correct O/A Punch
  • Commons Wing – Level 2 – Sound Control & Vestibules:
    • Finish Installing MEP in Sound Control Ceiling*
    • Inspect MEP in Sound Control Ceiling*
    • Install ACT Tiles
    • Install Counter Tops
  • Commons Wing – Level 2 – Perforated Drywall Sound Control:
    • No Activities this Upcoming Week.
  • Lab Wing – Level 1 – Classrooms:
    • Correct Andersen Punch
    • O/A Punch
  • Lab Wing – Level 2 – Common Spaces:
    • Third Coat Delay
    • Andersen Punch
  • Lab Wing – Level 2 – Lab Area:
    • No Activities this Upcoming Week.
  • Lab Wing – Level 2 – Offices and Conference Rooms:
    • Correct Andersen Punch
    • O/A Punch
    • Correct O/A Punch
  • Common Spaces – Level 3
    • Continue Installing Floor Boxes and Finish Electrical
  • Lab Wing – Level 3
    • Install Balance of Tiles and Clouds
  • Offices and Conference Rooms – Level 3
    • Paint Third Coat Delay
  • Roof Level – East Penthouse, Lobby and Staging
    • Install MEP in Tops and Trim Room
  • INTERIOR BUILDOUT
  • Elevator 1:
    • Continue Workman’s Service Use
  • Elevator 2:
    • Continue Installing Elevator*
  • Stair 4:
    • No Activities this Upcoming Week.
  • SITE IMPROVEMENTS
  • Phase 3 West Site Improvements:
    • Finish Curbs South End
    • ADA Parking Stalls
    • Install Balance Curbs and Walks
    • Remove Onsite Storage
    • Finish Landscaping
    • Fine Grade for AC
    • ADA Ramps and Walks West of Marine Science Drive

Primary construction activities for the week of 04/27 thru 05/01 will consist of the following:  

|   * = Activity delayed    |

  • ROOFING
  • Install Tsunami Signs:
    • Finish Re-waterproofing Area
    • Continue to Reinstall Siding
  • North Elevation:
    • Finish Installing Curtain Wall Center
  • INTERIOR BUILDOUT
  • Lab Wing – Level 1 – Commons Spaces, Café, & Fireplace:
    • Start to Install Wood Ceiling and Lighting
    • Finish Install of Fireplace
    • Install Wood Paneling
    • Install Base
  • Common Spaces All Levels – Stair Three Finish Work:
    • Finish Installing Wood Panels
  • Commons Wing – Level 1 – Bathrooms & A/V Hard Lid Rooms:
    • Complete Punch
    • O/A Punch
  • Lab Wing – Level 1 – Bathrooms and Hard Lid Rooms:
    • Complete Punch
    • O/A Punch
  • Lab Wing – Level 2 – Bathrooms and Hard Lid Rooms:
    • Complete Punch
    • O/A Punch
  • Lab Wing – Level 3 – Bathrooms and Hard Lid Rooms:
    • Finish Installing Plumbing Trim Out
    • Install Electrical Trim Out*
  • Commons Wing – Auditorium:
    • Continue Installing Wood Flooring
  • Commons Wing – Innovation Lab:
    • Install Lights and MEP Finishes*
  • Commons Wing – Level 2 – Design 3D & Art Studio:
    • Correct Andersen Punch
    • O/A Punch
  • Commons Wing – Level 2 – Sound Control & Vestibules:
    • Finish Installing MEP in Sound Control Ceiling
    • Inspect MEP in Sound Control Ceiling
    • Install ACT Tiles
    • Install Counter Tops
  • Commons Wing – Level 2 – Perforated Drywall Sound Control:
    • No Activities this Upcoming Week.
  • Lab Wing – Level 1 – Classrooms:
    • 3rd Coat Delay
    • Andersen Punch
    • Correct Andersen Punch
  • Lab Wing – Level 2 – Common Spaces:
    • No Activities this Upcoming Week.
  • Lab Wing – Level 2 – Lab Area:
    • Finish Electrical Install
  • Lab Wing – Level 2 – Offices and Conference Rooms:
    • No Activities this Upcoming Week.
  • Lab Wing – Level 3 Rough-in – Orange South:
    • No Activities this Upcoming Week.
  • Lab Wing – Level 3 Rough-in – Blue Northeast:
    • No Activities this Upcoming Week.
  • Lab Wing – Level 3 Rough-in – Green Northwest:
    • No Activities this Upcoming Week.
  • Lab Wing – Level 3 Rough-in – Purple Core Area Labs:
    • No Activities this Upcoming Week.
  • Common Spaces – Level 3
    • Install Base
    • Continue Installing Floor Boxes and Finish Electrical
  • Lab Wing – Level 3
    • Install Glass in Glass Wall
    • Finish MEP in Ceiling Grid
  • Offices and Conference Rooms – Level 3
    • Finish Electrical
    • Paint 3rd Coat Delay
  • Roof Level – East Penthouse, Lobby and Staging
    • Install MEP in Tops and Trim Room
  • INTERIOR BUILDOUT
  • Elevator 1:
    • Continue Workman’s Service Use
  • Elevator 2:
    • Continue Installing Elevator*
  • Stair 1:
    • No activities this week.
  • Stair 2:
    • No Activities this Upcoming Week.
  • Stair 4:
    • No Activities this Upcoming Week.
  • SITE IMPROVEMENTS
  • Phase 3 West Site Improvements:
    • Finish Excavating Rain Garden 2
    • Install Balance Curbs and Walks North and South

Primary construction activities for the week of 04/20 thru 04/24 will consist of the following:  

|   * = Activity delayed    |

  • ROOFING
  • Penthouse Framing:
    • No Activities this Upcoming Week.
  • Install Tsunami Signs:
    • Re-waterproof Area
    • Start to Reinstall Siding
  • INTERIOR BUILDOUT
  • Lab Wing – Level 1 – Commons Spaces, Café, & Fireplace:
    • Start to Install Wood Ceiling and Lighting
    • Finish Install of Fireplace
  • Common Spaces All Levels – Stair Three Finish Work:
    • Start Installing Wood Panels*
  • Commons Wing – Level 1 – Bathrooms & A/V Hard Lid Rooms:
    • Complete Punch
  • Lab Wing – Level 1 – Bathrooms and Hard Lid Rooms:
    • Complete Punch
  • Lab Wing – Level 2 – Bathrooms and Hard Lid Rooms:
    • Complete Punch
    • O/A Punch
  • Lab Wing – Level 3 – Bathrooms and Hard Lid Rooms:
    • Install Plumbing Trim Out
    • Install Electrical Trim Out
  • Commons Wing – Auditorium:
    • Start to Install Wood Flooring
  • Commons Wing – Innovation Lab:
    • Install Lights and MEP Finishes*
  • Commons Wing – Level 2 – Design 3D & Art Studio:
    • Correct Andersen Punch
    • O/A Punch
  • Commons Wing – Level 2 – Sound Control & Vestibules:
    • Install Ceiling Grid in Sound Control and Framing
    • Install MEP in Sound Control Ceiling
  • Commons Wing – Level 2 – Perforated Drywall Sound Control:
    • No Activities this Upcoming Week.
  • Lab Wing – Level 1 – Classrooms:
    • Install Finish MEP
    • Install Carpet and Base
  • Lab Wing – Level 2 – Common Spaces:
    • No Activities this Upcoming Week.
  • Lab Wing – Level 2 – Lab Area:
    • Finish HVAC Connections in Ceiling
  • Lab Wing – Level 2 – Offices and Conference Rooms:
    • No Activities this Upcoming Week.
  • Lab Wing – Level 3 Rough-in – Orange South:
    • No Activities this Upcoming Week.
  • Lab Wing – Level 3 Rough-in – Blue Northeast:
    • Pipe ID*
  • Lab Wing – Level 3 Rough-in – Green Northwest:
    • No Activities this Upcoming Week.
  • Lab Wing – Level 3 Rough-in – Purple Core Area Labs:
    • No Activities this Upcoming Week.
  • Common Spaces – Level 3
    • Install Base
    • Install Carpet
    • Install Floor Boxes and Finish Electrical
  • Lab Wing – Level 3
    • Install Lab Casework and Fume Hoods
    • Finish MEP in Ceiling Grid
  • Offices and Conference Rooms – Level 3
    • Finish Electrical
  • Roof Level – East Penthouse, Lobby and Staging
    • Install Countertops
  • INTERIOR BUILDOUT
  • Elevator 1:
    • Continue Workman’s Service Use
  • Elevator 2:
    • Continue Installing Elevator*
  • Stair 1:
    • No activities this week.
  • Stair 2:
    • No Activities this Upcoming Week.
  • Stair 4:
    • No Activities this Upcoming Week.
  • SITE IMPROVEMENTS
  • Phase 3 West Site Improvements:
    • No Activities this Upcoming Week.

Primary construction activities for the week of 04/13 thru 04/17 will consist of the following:  

|   * = Activity delayed    |

  • ROOFING
  • Penthouse Framing:
    • Finish Installing Metal Siding
  • Install Tsunami Signs:
    • No Activities this Upcoming Week.
  • INTERIOR BUILDOUT
  • Lab Wing – Level 1 – Commons Spaces, Café, & Fireplace:
    • Install Electrical Conduit to Lighting in Wood Paneling
  • Common Spaces All Levels – Stair Three Finish Work:
    • Fab Wood Panels*
    • Start Installing Wood Panels
  • Commons Wing – Level 1 – Bathrooms & A/V Hard Lid Rooms:
    • Finish Installing Electrical Trim Out*
  • Lab Wing – Level 1 – Bathrooms and Hard Lid Rooms:
    • No Activities this Upcoming Week.
  • Lab Wing – Level 2 – Bathrooms and Hard Lid Rooms:
    • Finish Installing Grab Rails and Toilet Partitions*
    • Andersen Punch*
    • Complete Punch
  • Lab Wing – Level 3 – Bathrooms and Hard Lid Rooms:
    • No Activities this Upcoming Week.
  • Commons Wing – Auditorium:
    • Finish Seating Framing
    • Install Screen
  • Commons Wing – Innovation Lab:
    • Install Lights and MEP Finishes
  • Commons Wing – Level 2 – Design 3D & Art Studio:
    • Third Coat Delay
    • Andersen Punch
    • Correct Andersen Punch
  • Commons Wing – Level 2 – Sound Control & Vestibules:
    • No Activities this Upcoming Week.
  • Commons Wing – Level 2 – Perforated Drywall Sound Control:
    • No Activities this Upcoming Week.
  • Lab Wing – Level 1 – Classrooms:
    • Install Finish MEP
  • Lab Wing – Level 2 – Common Spaces:
    • No Activities this Upcoming Week.
  • Lab Wing – Level 2 – Lab Area:
    • Finish HVAC Connections in Ceiling
  • Lab Wing – Level 2 – Offices and Conference Rooms:
    • No Activities this Upcoming Week.
  • Lab Wing – Level 3 Rough-in – Orange South:
    • No Activities this Upcoming Week.
  • Lab Wing – Level 3 Rough-in – Blue Northeast:
    • Paint MEPFP in OTS*
    • Pipe ID*
  • Lab Wing – Level 3 Rough-in – Green Northwest:
    • Hydronic Pipe Insulation Delay COVID 19*
  • Lab Wing – Level 3 Rough-in – Purple Core Area Labs:
    • Finish Pipe ID*
  • Common Spaces – Level 3
    • Install Carpet
    • Install Base
  • Lab Wing – Level 3
    • Continue Installing Rubber Flooring
  • Offices and Conference Rooms – Level 3
    • Finish Electrical
  • Roof Level – East Penthouse, Lobby and Staging
    • No Activities this Upcoming Week.
  • INTERIOR BUILDOUT
  • Elevator 1:
    • Continue Workman’s Service Use
  • Elevator 2:
    • Continue Installing Elevator*
  • Stair 1:
    • No activities this week.
  • Stair 2:
    • No Activities this Upcoming Week.
  • Stair 4:
    • No Activities this Upcoming Week.
  • SITE IMPROVEMENTS
  • Phase 3 West Site Improvements:
    • No Activities this Upcoming Week.

Primary construction activities for the week of 04/06 thru 04/10 will consist of the following:  

|   * = Activity delayed    |

  • ROOFING
  • Penthouse Framing:
    • Continue Installing Metal Siding
  • Install Tsunami Signs:
    • Install Stainless Steel Sign Holder
    • Re-waterproof Area
  • INTERIOR BUILDOUT
  • Lab Wing – Level 1 – Commons Spaces, Café, & Fireplace:
    • Install Finish MEP
    • Finish MEP to Fireplace
  • Common Spaces All Levels – Stair Three Finish Work:
    • Fab Wood Panels*
  • Commons Wing – Level 1 – Bathrooms & A/V Hard Lid Rooms:
    • Complete Punch
  • Lab Wing – Level 1 – Bathrooms and Hard Lid Rooms:
    • Finish Installing Toilet Accessories*
    • Andersen Punch*
    • Complete Punch
  • Lab Wing – Level 2 – Bathrooms and Hard Lid Rooms:
    • Finish Installing Grab Rails and Toilet Partitions
    • Install Toilet Accessories
    • Andersen Punch
    • Complete Punch
  • Lab Wing – Level 3 – Bathrooms and Hard Lid Rooms:
    • Finish Installing Plumbing Trim Out
    • Install Electrical Trim Out
    • Start Installing Grab Rails and Toilet Partitions
  • Commons Wing – Auditorium:
    • Finish Seating Framing
    • Install Wood Flooring
  • Commons Wing – Innovation Lab:
    • Correct Andersen Punch*
  • Commons Wing – Level 2 – Design 3D & Art Studio:
    • Correct Andersen Punch*
  • Commons Wing – Level 2 – Sound Control & Vestibules:
    • Install Ceiling Grid in Sound Control
    • Install MEP in Sound Control Ceiling
  • Commons Wing – Level 2 – Perforated Drywall Sound Control:
    • No Activities this Upcoming Week.
  • Lab Wing – Level 1 – Classrooms:
    • Install Finish MEP
    • 3rd Coat Delay
    • Install ACT Tile
    • Andersen Punch
    • Correct Andersen Punch
  • Lab Wing – Level 2 – Common Spaces:
    • No Activities this Upcoming Week.
  • Lab Wing – Level 2 – Lab Area:
    • Install Balance of Tiles and Clouds
  • Lab Wing – Level 2 – Offices and Conference Rooms:
    • No Activities this Upcoming Week.
  • Lab Wing – Level 3 Rough-in – Orange South:
    • No Activities this Upcoming Week.
  • Lab Wing – Level 3 Rough-in – Blue Northeast:
    • Paint MEPFP in OTS
    • Pipe ID*
  • Lab Wing – Level 3 Rough-in – Green Northwest:
    • Hydronic Pipe Insulation Delay COVID 19*
  • Lab Wing – Level 3 Rough-in – Purple Core Area Labs:
    • Finish Pipe ID*
  • Common Spaces – Level 3
    • No Activities this Upcoming Week.
  • Lab Wing – Level 3
    • Start Installing Rubber Flooring
  • Offices and Conference Rooms – Level 3
    • Finish Installing Windowsills and Casework*
  • Roof Level – East Penthouse, Lobby and Staging
    • Start Installing Finishes*
  • INTERIOR BUILDOUT
  • Elevator 1:
    • Continue Workman’s Service Use
  • Elevator 2:
    • Workman’s Inspection
    • Workman’s Service Use
  • Stair 1:
    • No activities this week.
  • Stair 2:
    • No Activities this Upcoming Week.
  • Stair 4:
    • No Activities this Upcoming Week.
  • SITE IMPROVEMENTS
  • Phase 3 West Site Improvements:
    • No Activities this Upcoming Week.

Primary construction activities for the week of 03/30 thru 04/03 will consist of the following:  

|   * = Activity delayed    |

  • ROOFING
  • Penthouse Framing:
    • Continue Installing Metal Siding
  • INTERIOR BUILDOUT
  • Lab Wing – Level 1 – Commons Spaces, Café, & Fireplace:
    • Install Finish MEP
  • Common Spaces All Levels – Stair Three Finish Work:
    • Fab Wood Panels
  • Commons Wing – Level 1 – Bathrooms & A/V Hard Lid Rooms:
    • Andersen Punch
    • Complete Punch
  • Lab Wing – Level 1 – Bathrooms and Hard Lid Rooms:
    • Finish Installing Toilet Accessories
    • Andersen Punch
    • Complete Punch
  • Lab Wing – Level 2 – Bathrooms and Hard Lid Rooms:
    • Install Grab Rails and Toilet Partitions
    • Install Toilet Accessories
    • Andersen Punch
  • Lab Wing – Level 3 – Bathrooms and Hard Lid Rooms:
    • Finish Painting
    • Install Counters
    • Install Plumbing Trim Out
  • Commons Wing – Auditorium:
    • Finish Seating Framing
  • Commons Wing – Innovation Lab:
    • Correct Andersen Punch
  • Commons Wing – Level 2 – Design 3D & Art Studio:
    • Correct Andersen Punch.
  • Commons Wing – Level 2 – Sound Control & Vestibules:
    • No Activities this Upcoming Week.
  • Commons Wing – Level 2 – Perforated Drywall Sound Control:
    • No Activities this Upcoming Week.
  • Lab Wing – Level 1 – Classrooms:
    • Install Base
    • Install Finish MEP
  • Lab Wing – Level 2 – Common Spaces:
    • No Activities this Upcoming Week.
  • Lab Wing – Level 2 – Lab Area:
    • Install Base
  • Lab Wing – Level 2 – Offices and Conference Rooms:
    • No Activities this Upcoming Week.
  • Lab Wing – Level 3 Rough-in – Orange South:
    • Finish Pipe ID.
  • Lab Wing – Level 3 Rough-in – Blue Northeast:
    • Finish Pipe ID.
  • Lab Wing – Level 3 Rough-in – Green Northwest:
    • No activities this upcoming week.
  • Lab Wing – Level 3 Rough-in – Purple Core Area Labs:
    • Finish Pipe ID.
  • Common Spaces – Level 3
    • Install Casework and Windowsills
  • Lab Wing – Level 3
    • No Activities this Upcoming Week.
  • Offices and Conference Rooms – Level 3
    • Finish Installing Windowsills and Casework*
    • Install Ceiling Tiles
    • MEP Cover Inspection
  • Roof Level – East Penthouse, Lobby and Staging
    • Paint Room
    • Start Installing Finishes
  • INTERIOR BUILDOUT
  • Elevator 1:
    • Continue Workman’s Service Use
  • Elevator 2:
    • Continue Installing elevator
  • Stair 1:
    • No activities this week.
  • Stair 2:
    • No Activities this Upcoming Week.
  • Stair 4:
    • No Activities this Upcoming Week.
  • SITE IMPROVEMENTS
  • Phase 3 West Site Improvements:
    • Seed Areas
    • Start Installing Mulch