Primary construction activities for the week of 08/12 thru 08/16 will consist of the following:  

|   * = Start or Finish was delayed    |   ** Activity taking longer than projected   |

  • ROOFING
  • High Roof Auditorium:
  • Low Roof Auditorium:
    • Continue framing and sheeting at truss
    • Finish installing green gert and foam
    • Install furring
    • Begin installing window
  • Lab Wing Main Roof:
    • Conduct water test
    • Begin installing drain matt foam and rock ballast
  • Penthouses:
  • Lab High Roof West:
  • FRAMING SHEATING
    • – South Elevation:
    • Finish installing window steel
  • Commons Wing – North Elevation:
    • Finish installing temp window protection (if needed) *
  • Commons Wing – East Elevation:
  • Commons Wing – West Elevation:
    • Finish installing temp window protection if needed
  • WINDOWS & SIDING
  • Lab Wing – West Elevation:
    • Finish installing vertical siding MWC
  • Lab Wing – North Elevation:
    • Finish installing vertical siding MWC
    • Begin installing beauty cap and flashing
  • Lab Wing – East Elevation:
  • Lab Wing – South Elevation:
    • Begin installing horizontal cleat
    • Finish Installing beauty cap and flashing
  • Auditorium – East Elevation:
    • Finish installing windows
    • Install flashings and trim
    • Install backer rod and caulk
    • Begin installing insulation and horizontal cleat
  • Auditorium – South Elevation:
  • Auditorium – West Elevation:
    • Finish installing vertical Z girt and install windows
    • Begin installing flashings and trim
    • Begin backer rod and caulk
  • Auditorium – North Elevation:
    • Finish installing vertical Z girt
    • Finish Installing windows
    • Begin to install flashings and trim
    • Install backer rod and caulk
  • INTERIOR BUILDOUT
  • Rough in Framing Commons Wing
  • Begin to frame auditorium fire walls and concrete furring
  • Mechanical & Back of House:
    • Install panels/feeders in electric rooms
    • Continue to install all MEP in Mechanical spaces on the first floor
  • Rough in Remaining First Floor:
  • Finishing Framing
  • QC all MEP openings in the walls
  • Begin installing MEP in walls
  • Lab Wing Level 2 – Rough-in:
    • Finish complete balance of MEP in walls
    • Install drywall on the East and Southwest
    • Stuff and Spray STC’s Donut
  • Roof Level:
  • Install Gyp
  • Stuff and Spray Top of Wall
  • Install Ceiling OTS Insulation
  • Begin to Paint Room
  • Elevators:
  • Procure Elevator
  • Stairs:
    • Continue to finish stair interiors
  • SITE IMPROVEMENTS
  • ODF&W Parking and Sidewalks:
    • Install Irrigation
    • Finish Final Grade West and North around swales
    • Begin Installing top soil
    • Begin Installing light Poles
  • Ramp:
    • Finish backfilling up to -42”
    • Install temporary handrail posts and railing
    • Begin backfilling to elevation

Primary construction activities for the week of 08/05 thru 08/09 will consist of the following:  

|   * = Start or Finish was delayed    |   ** Activity taking longer than projected   |

  • ROOFING
  • High Roof Auditorium:
  • Low Roof Auditorium:
    • Continue installing roof
  • Lab Wing Main Roof:
    • Continue installing hot fluid-applied rubber asphalt
  • Penthouses:
  • Lab High Roof West:
  • FRAMING SHEATING
    • Lab Wing – South Elevation:
    • Finish installing flashings and window steel
  • Auditorium – North Elevation:
    • Finish installing temp window protection (if needed) *
  • Auditorium – East Elevation:Auditorium – South Elevation:
    • Finish installing Window Steel
  • Auditorium – West Elevation:
    • Finish installing temp window protection if needed
  • WINDOWS & SIDING
  • Lab Wing – West Elevation:
    • finish installing vertical siding MWC
  • Lab Wing – North Elevation:
    • Finish installing vertical siding MWC
    • Begin installing beauty cap and flashing
  • Lab Wing – East Elevation:
  • Lab Wing – South Elevation:
    • Begin installing horizontal cleat
  • Auditorium – East Elevation:
    • Install flashings and trim
    • Install backer rod and caulk
    • Begin installing insulation and horizontal cleat
  • Auditorium – South Elevation:
  • Auditorium – West Elevation:
    • Finish installing vertical Z girt and install windows
    • Begin installing flashings and trim
    • Begin back rod and caulk
  • Auditorium – North Elevation:
    • Finish installing vertical Z girt
    • Finish Installing windows
    • Begin to install flashings and trim
  • INTERIOR BUILDOUT
  • Mechanical & Back of House:
    • Install panels/feeders in electric rooms
  • Lab Wing Level 2 – Rough-in:
    • Finish Stuff and spray for STC’s
  • Roof Level:
  • Finish MEP in Walls
  • Install Gyp
  • Elevators:
  • Procure Elevator
  • Stairs:
    • Continue to finish stair interiors
  • SITE IMPROVEMENTS
  • ODFW Parking and Sidewalks:
    • Pave Parking first lift
    • Pave parking 2nd lift
    • Excavate Public Rain Garden after Paving
  • Ramp:
    • Finish backfilling up to the fluid applied weather protection
    • Install the complete bentonite and fluid applied weather protection

Primary construction activities for the week of 07/29 thru 08/02 will consist of the following:  

|   * = Start or Finish was delayed    |   ** Activity taking longer than projected   |

  • ROOFING
  • High Roof Auditorium:
  • Continue to form and pour evacuation ramp and eyebrows
  • Low Roof Auditorium:
    • Continue installing roof
  • Lab Wing Main Roof:
    • Continue installing hot fluid-applied rubber asphalt
  • Penthouses:
  • Lab High Roof West:
    • Continue installing roof
  • FRAMING SHEATING (2nd & 3rd Floor)
  • Lab Wing – South Elevation:
    • Finish installing temp window protection (if needed) *
  • FRAMING SHEATING (1st Floor)
    • Lab Wing – South Elevation:
    • Finish installing flashings and window steel
  • Auditorium – North Elevation:
    • Finish installing exterior gyp
    • Start installation of window steel as well as the air and water barrier
    • Install the flashings
  • Auditorium – East Elevation:Auditorium – South Elevation:
    • to install window steel and flashings**
  • Auditorium – West Elevation:
    • Finish Installing weather barrier, window steel, and flashings
    • Begin installing temp window protection if needed
  • WINDOWS & SIDING
  • Lab Wing – West Elevation:
    • finish installing vertical siding
  • Lab Wing – North Elevation:
    • Continue installing vertical siding
    • Begin installing beauty cap and flashing
  • Lab Wing – East Elevation:
    • Install beauty cap and flashing
  • Lab Wing – South Elevation:
    • Finish installing beauty cap and flashing
    • Begin installing horizontal cleat
  • Auditorium – East Elevation:
    • Install flashings and trim
    • Install backer rod and caulk
    • Begin installing insulation and horizontal cleat
  • Auditorium – South Elevation:
  • Auditorium – West Elevation:
    • Finish installing vertical Z girt and install windows, flashings and trim
  • Auditorium – North Elevation:
    • Begin installing vertical Z girt
  • INTERIOR BUILDOUT
  • Mechanical & Back of House:
    • Install panels/feeders in electric rooms
  • Lab Wing Level 2 – Rough-in:
    • Finish Stuff and spray for STC’s
  • Stairs:
    • Continue to finish stair interiors
  • SITE IMPROVEMENTS
  • ODF&W Parking and Sidewalks:
    • Remove asphalt and fine grade East side
  • Ramp:
    • Finish backfilling up to the fluid applied weather protection
    • Begin the complete bentonite and fluid applied weather protection