Primary construction activities for the week of 8/20 thru 8/24 will consist of:

  • Deep Soil Mixing for the Lab Wing
  • Grinding of DSM columns to required elevation
  • Saw cutting at West Wing for Fiber Reroute begin in the latter part of the week.

Below is an up to date construction schedule:

MSIB CC 2018.08.17_