Primary construction activities for the week of 05/04 thru 05/08 will consist of the following:
| * = Activity delayed |
- ROOFING
- Install Tsunami Signs:
- Finish to Reinstall Siding
- Install Signs
- INTERIOR BUILDOUT
- Lab Wing – Level 1 – Commons Spaces, Café, & Fireplace:
- Install Wood Ceiling and Lighting
- Install Base*
- Finish Electrical Trim Out
- Common Spaces All Levels – Stair Three Finish Work:
- Finish Installing Wood Panels*
- Commons Wing – Level 1 – Bathrooms & A/V Hard Lid Rooms:
- Complete Punch
- O/A Punch
- Complete O/A Punch
- Lab Wing – Level 1 – Bathrooms and Hard Lid Rooms:
- Complete Punch
- O/A Punch
- Complete O/A Punch
- Lab Wing – Level 2 – Bathrooms and Hard Lid Rooms:
- Complete Punch
- O/A Punch
- Complete O/A Punch
- Lab Wing – Level 3 – Bathrooms and Hard Lid Rooms:
- Install Electrical Trim Out*
- Install Toilet Accessories
- Andersen Punch
- Complete Punch
- Commons Wing – Auditorium:
- Continue Installing Wood Flooring
- Commons Wing – Innovation Lab:
- Start Installing Lights and MEP Finishes*
- Commons Wing – Level 2 – Design 3D & Art Studio:
- Correct Andersen Punch
- O/A Punch
- Correct O/A Punch
- Commons Wing – Level 2 – Sound Control & Vestibules:
- Finish Installing MEP in Sound Control Ceiling*
- Inspect MEP in Sound Control Ceiling*
- Install ACT Tiles
- Install Counter Tops
- Commons Wing – Level 2 – Perforated Drywall Sound Control:
- No Activities this Upcoming Week.
- Lab Wing – Level 1 – Classrooms:
- Correct Andersen Punch
- O/A Punch
- Lab Wing – Level 2 – Common Spaces:
- Third Coat Delay
- Andersen Punch
- Lab Wing – Level 2 – Lab Area:
- No Activities this Upcoming Week.
- Lab Wing – Level 2 – Offices and Conference Rooms:
- Correct Andersen Punch
- O/A Punch
- Correct O/A Punch
- Common Spaces – Level 3
- Continue Installing Floor Boxes and Finish Electrical
- Lab Wing – Level 3
- Install Balance of Tiles and Clouds
- Offices and Conference Rooms – Level 3
- Paint Third Coat Delay
- Roof Level – East Penthouse, Lobby and Staging
- Install MEP in Tops and Trim Room
- INTERIOR BUILDOUT
- Elevator 1:
- Continue Workman’s Service Use
- Elevator 2:
- Continue Installing Elevator*
- Stair 4:
- No Activities this Upcoming Week.
- SITE IMPROVEMENTS
- Phase 3 West Site Improvements:
- Finish Curbs South End
- ADA Parking Stalls
- Install Balance Curbs and Walks
- Remove Onsite Storage
- Finish Landscaping
- Fine Grade for AC
- ADA Ramps and Walks West of Marine Science Drive