Primary construction activities for the week of 05/04 thru 05/08 will consist of the following:  

|   * = Activity delayed    |

  • ROOFING
  • Install Tsunami Signs:
    • Finish to Reinstall Siding
    • Install Signs
  • INTERIOR BUILDOUT
  • Lab Wing – Level 1 – Commons Spaces, Café, & Fireplace:
    • Install Wood Ceiling and Lighting
    • Install Base*
    • Finish Electrical Trim Out
  • Common Spaces All Levels – Stair Three Finish Work:
    • Finish Installing Wood Panels*
  • Commons Wing – Level 1 – Bathrooms & A/V Hard Lid Rooms:
    • Complete Punch
    • O/A Punch
    • Complete O/A Punch
  • Lab Wing – Level 1 – Bathrooms and Hard Lid Rooms:
    • Complete Punch
    • O/A Punch
    • Complete O/A Punch
  • Lab Wing – Level 2 – Bathrooms and Hard Lid Rooms:
    • Complete Punch
    • O/A Punch
    • Complete O/A Punch
  • Lab Wing – Level 3 – Bathrooms and Hard Lid Rooms:
    • Install Electrical Trim Out*
    • Install Toilet Accessories
    • Andersen Punch
    • Complete Punch
  • Commons Wing – Auditorium:
    • Continue Installing Wood Flooring
  • Commons Wing – Innovation Lab:
    • Start Installing Lights and MEP Finishes*
  • Commons Wing – Level 2 – Design 3D & Art Studio:
    • Correct Andersen Punch
    • O/A Punch
    • Correct O/A Punch
  • Commons Wing – Level 2 – Sound Control & Vestibules:
    • Finish Installing MEP in Sound Control Ceiling*
    • Inspect MEP in Sound Control Ceiling*
    • Install ACT Tiles
    • Install Counter Tops
  • Commons Wing – Level 2 – Perforated Drywall Sound Control:
    • No Activities this Upcoming Week.
  • Lab Wing – Level 1 – Classrooms:
    • Correct Andersen Punch
    • O/A Punch
  • Lab Wing – Level 2 – Common Spaces:
    • Third Coat Delay
    • Andersen Punch
  • Lab Wing – Level 2 – Lab Area:
    • No Activities this Upcoming Week.
  • Lab Wing – Level 2 – Offices and Conference Rooms:
    • Correct Andersen Punch
    • O/A Punch
    • Correct O/A Punch
  • Common Spaces – Level 3
    • Continue Installing Floor Boxes and Finish Electrical
  • Lab Wing – Level 3
    • Install Balance of Tiles and Clouds
  • Offices and Conference Rooms – Level 3
    • Paint Third Coat Delay
  • Roof Level – East Penthouse, Lobby and Staging
    • Install MEP in Tops and Trim Room
  • INTERIOR BUILDOUT
  • Elevator 1:
    • Continue Workman’s Service Use
  • Elevator 2:
    • Continue Installing Elevator*
  • Stair 4:
    • No Activities this Upcoming Week.
  • SITE IMPROVEMENTS
  • Phase 3 West Site Improvements:
    • Finish Curbs South End
    • ADA Parking Stalls
    • Install Balance Curbs and Walks
    • Remove Onsite Storage
    • Finish Landscaping
    • Fine Grade for AC
    • ADA Ramps and Walks West of Marine Science Drive
Print Friendly, PDF & Email

Leave a reply

<a href="" title=""> <abbr title=""> <acronym title=""> <b> <blockquote cite=""> <cite> <code> <del datetime=""> <em> <i> <q cite=""> <s> <strike> <strong> 

required