Primary construction activities for the week of 02/24 thru 02/28 will consist of the following:
| * = Activity delayed |
- ROOFING
- Penthouse Framing and Sheathing:
- Continue Installing Metal Siding
- INTERIOR BUILDOUT
- Lab Wing – Level 1 – Commons Spaces,
Café, & Fireplace:
- Finish Painting Walls
- Paint Open to Structure *
- Install Tile and Grout at Café Back Wall
- Install Cabinets in Café
- Start Installing Tile and Grout at Fireplace
- Common Spaces All Levels – Stair Three
Finish Work:
- Continue Installing Wood Panels*
- Commons Wing – Level 1 – Bathrooms
& A/V Hard Lid Rooms:
- Install Plumbing Trim Out
- Install Electrical Trim Out
- Install Grab Rails and Toilet Partitions
- Lab
Wing – Level 1 – Bathrooms and Hard Lid
Rooms:
- Install Plumbing Trim Out
- Install Electrical Trim Out
- Lab Wing – Level 2 – Bathrooms and Hard Lid Rooms:
- No Activities this upcoming Week.
- Lab
Wing – Level 3 – Bathrooms and Hard Lid
Rooms:
- Finish MEP Hard Lids
- MEP Inspection for Hard Lids
- Commons Wing – Auditorium:
- Continue Installing Acoustical Panels
- Commons Wing – Innovation Lab:
- Finish installing ACT tiles
- Finish Crane Install
- Start Installing Wood Paneling
- Start Installing Lights and MEP Finishes
- Commons Wing – Level 2 – Design 3D
& Art Studio:
- Correct Andersen Punch
Commons Wing – Level 2 – Sound Control & Vestibules:
- No activities this upcoming week.
- Commons Wing – Level 2 – Perforated
Drywall Sound Control:
- Finish Perforated Drywall*
- Lab Wing – Level 1 – Classrooms:
- Finish Installing Casework, Fume hoods, and Counter tops
- Install Base
- Lab
Wing – Level 2 – Common Spaces:
- Finish Third Coat Delay
- Start Andersen Punch
- Lab
Wing – Level 2 – Lab Area:
- Continue Installing Lab Casework and Fume hoods
- Lab
Wing – Level 2 – Offices and Conference
Rooms:
- Andersen Punch
- MEP Cover Inspection
- Start Installing Ceiling Tiles
- Lab Wing – Level 3 Rough-in – Orange South:
- Electrical in OTS
- Paint MEPFP in OTS
- Start Pipe ID
- Lab Wing – Level 3 Rough-in – Blue Northeast:
- Finish Insulating
- Electrical in OTS
- Lab Wing – Level 3 Rough-in – Green Northwest:
- Finish TU Test
- Finish Insulating
- Lab Wing – Level 3 Rough-in – Purple Core
Area Labs:
- Finish TU Test*
- Finish Insulating
- Common Spaces – Level 3
- Start Polish Floors*
- Roof Level – East Penthouse, Lobby and
Staging
- Install Gyp
- Start Finishing Gyp
- INTERIOR BUILDOUT
- Elevator 1:
- Workman’s Inspection*
- Workman’s Service Use
- Elevator 2:
- Continue Installing elevator
- Stair 1:
- Paint Walls Lower Landings
- Start to Prep Handrails
- Stair 2:
- Start Cleaning and Patching Walls and Landings
- Stair 4:
- No activities this week.
- SITE IMPROVEMENTS
- Phase 3 West Site Improvements:
- Finish Installing Electrical Conduits OEG*
- Finish Install Concrete Walks Building*
- Start to Dig RG#1 and Clean up South Side Bank