Primary construction activities for the week of 02/10 thru 02/14 will consist of the following:  

|   * = Activity delayed    |

  • ROOFING
  • Penthouse Framing and Sheathing:
    • Paint Soffit
    • Install Z Girt Insulation and Hat Channels
    • Install Metal Siding
  • INTERIOR BUILDOUT
  • Lab Wing – Level 1 – Commons Spaces, Café, & Fireplace:
    • Finishing walls *
  • Common Spaces All Levels – Stair Three Finish Work:
    • Measure for Wood Panels
    • Fab Wood Panels
    • Install Wood Panels
  • Lab Wing – Level 2 – Bathrooms and Hard Lid Rooms:
    • Start & Finish installing toilet accessories *
    • Start Andersen Punch
    • Start Complete Punch
  • Commons Wing – Level 1 – Bathrooms & A/V Hard Lid Rooms:
    • Paint
    • Start Install Tile
  • Lab Wing – Level 1 – Bathrooms and Hard Lid Rooms:
    • Paint
    • Start Install Tile
  • Lab Wing – Level 3 – Bathrooms and Hard Lid Rooms:
    • Start Framing Hard Lids
  • Commons Wing – Auditorium:
    • Start & Finish Install 1.5” Metal Deck*
    • Finish Balance of Walls
  • Commons Wing – Innovation Lab:
    • Finish installing MEP in ACT ceiling *
    • Inspect MEP in ACT ceiling *
    • Start installing ACT tiles *
    • Start Crane Install
  • Commons Wing – Level 2 – Design 3D & Art Studio:
    • Install ceiling tiles*
    • Install Base
    • Install Finish Electrical
    • Third Coat Delay
    • Andersen Punch
  • Commons Wing – Level 2 – Sound Control & Vestibules:
    • Install Ceiling Grid in Sound Control
    • Install MEP in Sound Control Ceiling
    • Inspect MEP in Sound Control Ceiling
  • Commons Wing – Level 2 – Perforated Drywall Sound Control:
    • Install Perforated Drywall
    • Finish Perforated Drywall
  • Lab Wing – Level 1 – Classrooms:
    • Pain Walls
    • Install Ceiling Grid
    • Install MEP in Ceiling
    • Inspect MEP in Ceiling
  • Lab Wing – Level 2 – Common Spaces:
    • Finish Installing Carpet
    • Install Base
    • Install Floor Boxes
  • Lab Wing –  Level 2 – Offices and Conference Rooms:
    • Finishing MEP in grid *
    • Finish Installing Carpet
    • Install Base
    • Install Doors and Hardware
  • Lab Wing – Level 3 Rough-in – Orange South:
    • Finish Duct and TU Install*
    • Start TU Test*
  • Lab Wing – Level 3 Rough-in – Blue Northeast:
    • Finish Duct and TU Install*
    • Start TU Test*
  • Lab Wing – Level 3 Rough-in – Green Northwest:
    • Start Duct and TU Install
  • Lab Wing – Level 3 Rough-in – Purple Core Area Labs:
    • Finish Duct and TU Install
    • Start TU Test
  • Roof Level – East Penthouse, Lobby and Staging
    • Start and Finish MEP in Walls
  • INTERIOR BUILDOUT
  • Elevator 1:
    • Continue installing elevator
    • MEP and Cap Screw
  • Elevator 2:
    • Start installing elevator
  • Stair 1:
    • Finish cleaning and patching walls and landings
  • Stair 4:
    • Reinstall Handrail at Siding
  • SITE IMPROVEMENTS
  • Phase 3 West Site Improvements:
    • Install Electrical Conduits OEG*
    • Install Storm Water Planters and West Curbs & ADA
    • Install Light Pole Foundations
    • Install Irrigation Sleeves
    • Start Install Concrete Walks Building