Primary construction activities for the week of 01/13 thru 01/17 will consist of the following:
| * = Activity delayed |
- ROOFING
- Penthouse Framing and Sheathing:
- Start installing electrical in soffit
- Finish framing soffit
- CANOPIESWest Canopy V0102:Installing soffit and wall panels
- INTERIOR BUILDOUT
- Lab Wing – Level 2 – Bathrooms and Hard Lid Rooms:
- Finish installing tiling
- Commons Wing – Level 1 – Bathrooms
& A/V Hard Lid Rooms:
- Start gyping walls and lids
- Lab
Wing – Level 1 – Bathrooms and Hard Lid Rooms:
- Start gyping walls and lids
- Lab
Wing – Level 3 – Bathrooms and Hard Lid Rooms:
- Installing top out and fire tape
- Commons Wing – Auditorium:
- Continue installing electrical
- Commons Wing – Innovation Lab:
- Finish installing MEP in ACT ceiling *
- Inspecting MEP in ACT ceiling
- Start installing ACT tiles
- Start installing Gantry Crane
- Commons Wing – Level 2 – Design 3D
& Art Studio:
- Installing base *
- Installing finish electrical *
- Andersen Punch
- Lab Wing – Level 1 – Commons Spaces, Café,
& Fireplace:
- Gyping all remaining walls at Café and VEST V0102 ceilings
- Start finishing walls
- Lab Wing – Level 2 – Rough-in:
- Continue installing cable tray at OTS and Commons
- Lab Wing – Level 2 – Commons Spaces:
- Installing casework and windowsills *
- Start installing carpet *
- Start installing base
- Lab
Wing – Level 2 – Labs:
- Finishing overhead electrical in Lab Area
- Finish applying moisture mitigation
- Lab
Wing – Level 2 – Offices and Conference Rooms:
- Finishing MEP in grid *
- Lab Wing – Level 3 Rough-in – South:
- Finish installing mechanical hangers, seismic, and piping – then test
- Start insulating mechanical
- Lab Wing – Level 3 Rough-in – East:
- Finish painting
- Start installing mechanical hangers, seismic, and piping
- Lab Wing – Level 3 Rough-in – West:
- Finish taping and finishing gyp
- Start painting
- Lab Wing – Level 3 Rough-in – Core Area Labs:
- Finish installing backing and gyp
- Start taping and finish gyp
- Lab Wing – Level 3 Rough-in – Commons Spaces
- Continue polishing floors
- Roof – West Penthouse ELEV Equip Room:
- Finish installing shaft frame, gyp, and finish
- Start installing disconnects
- Roof – East Penthouse Stor, Elev Lobby
& Staging:
- Start framing walls
- INTERIOR BUILDOUT
- Elevator 2:
- Continue installing elevator
- Stair 1:
- Start cleaning and patching walls and landings *
- Stair 3:
- Installing precast treads
- Stair 4:
- Installing down rods and landings
- Installing treads and risers