Primary construction activities for the week of 01/06 thru 01/10 will consist of the following:  

|   * = Activity delayed    |

  • ROOFING
  • Penthouse Framing and Sheathing:
    • Continue framing soffit
  • CANOPIESWest Canopy V0102:Start installing roof panels
  • WINDOWS & SIDING
  • Commons Wing – East Elevation:
    • Finish installing beauty cap and flashing
  • Commons Wing – North Elevation:
    • Installing beauty cap and flashing
  • Commons Wing – South Elevation:
    • Installing beauty cap and flashing
  • Commons Wing – West Elevation:
    • Installing beauty cap and flashing
  • INTERIOR BUILDOUT
  • Lab Wing –  Level 2 – Bathrooms and Hard Lid Rooms:
    • Start installing tiling
  • Commons Wing – Level 1 – Bathrooms & A/V Hard Lid Rooms:
    • Finish grinding floors
    • Installing floor protection
  • Lab Wing –  Level 1 – Bathrooms and Hard Lid Rooms:
    • Finish installing MEP in hard lids
    • MEP inspection for hard lids
  • Lab Wing –  Level 3 – Bathrooms and Hard Lid Rooms:
    • Finish framing hard lids
    • Start installing MEP in hard lids
  • Commons Wing – Auditorium:
    • Start installing electrical *
    • Balance of walls pushed out to 1st week of February
  • Commons Wing – Innovation Lab:
    • Finish installing MEP in ACT ceiling *
  • Commons Wing – Level 2 – Design 3D & Art Studio:
    • Finish installing MEP in ceilings and inspection for MEP ceilings *
    • Installing ceiling tiles *
    • Installing base
    • Installing electrical *
  • Commons Wing – Level 2 – Sound Control and Vestibules:
    • Finish installing lids and walls
    • Start painting
  • Lab Wing – Level 1 – Mechanical & Back of House:
  • Finish installing panels and feeders in electric rooms *
  • Finish all MEP in 1st floor mechanical spaces *
  • Lab Wing – Level 1 – Commons Spaces, Café, & Fireplace:
    • Grinding floors
    • Framing hard lid at Café and VEST V0102
    • Finishing MEP in hard lids at Café and VEST V0102
  • Lab Wing – Level 2 – Rough-in:
    • Continue installing cable tray at OTS and Commons
  • Lab Wing – Level 2 – Commons Spaces:
    • Installing casework and windowsills
    • Start installing carpet
  • Lab Wing – Level 2 – Labs:
    • Finishing overhead electrical in Lab Area
    • Continue applying moisture mitigation
  • Lab Wing –  Level 2 – Offices and Conference Rooms:
    • Continue finishing MEP in grid *
  • Lab Wing –  Level 3 Rough-in – South:
    • Start installing mechanical hangers, seismic, and piping
  • Lab Wing –  Level 3 Rough-in – East:
    • Finish taping and finishing gyp
    • Start paint
  • Lab Wing –  Level 3 Rough-in – West:
    • Start taping and finishing gyp
  • Lab Wing –  Level 3 Rough-in – Core Area Labs:
    • Start installing backing and gyp
  • Lab Wing –  Level 3 Rough-in – Core Area Labs:
    • Start polishing floors
  • Roof – West Penthouse ELEV Equip Room:
  • Continue installing shaft frame, gyp, and finish
  • Installing disconnects and elevator equipment pushed out until 01/14
  • INTERIOR BUILDOUT
  • Elevator 2:
    • Continue installing elevator
  • Stair 1:
    • Start cleaning and patching walls and landings *
  • Stair 3:
    • Installing stair stringers and risers