Primary construction activities for the week of 01/06 thru 01/10 will consist of the following:
| * = Activity delayed |
- ROOFING
- Penthouse Framing and Sheathing:
- Continue framing soffit
- CANOPIESWest Canopy V0102:Start installing roof panels
- WINDOWS & SIDING
- Commons Wing – East Elevation:
- Finish installing beauty cap and flashing
- Commons Wing – North Elevation:
- Installing beauty cap and flashing
- Commons Wing – South Elevation:
- Installing beauty cap and flashing
- Commons Wing – West Elevation:
- Installing beauty cap and flashing
- INTERIOR BUILDOUT
- Lab Wing – Level 2 – Bathrooms and Hard Lid Rooms:
- Start installing tiling
- Commons Wing – Level 1 – Bathrooms
& A/V Hard Lid Rooms:
- Finish grinding floors
- Installing floor protection
- Lab
Wing – Level 1 – Bathrooms and Hard Lid Rooms:
- Finish installing MEP in hard lids
- MEP inspection for hard lids
- Lab
Wing – Level 3 – Bathrooms and Hard Lid Rooms:
- Finish framing hard lids
- Start installing MEP in hard lids
- Commons Wing – Auditorium:
- Start installing electrical *
- Balance of walls pushed out to 1st week of February
- Commons Wing – Innovation Lab:
- Finish installing MEP in ACT ceiling *
- Commons Wing – Level 2 – Design 3D
& Art Studio:
- Finish installing MEP in ceilings and inspection for MEP ceilings *
- Installing ceiling tiles *
- Installing base
- Installing electrical *
- Commons Wing – Level 2 – Sound Control
and Vestibules:
- Finish installing lids and walls
- Start painting
- Lab Wing – Level 1 – Mechanical & Back of House:
- Finish installing panels and feeders in electric rooms *
- Finish all MEP in 1st floor mechanical spaces *
- Lab Wing – Level 1 – Commons Spaces, Café,
& Fireplace:
- Grinding floors
- Framing hard lid at Café and VEST V0102
- Finishing MEP in hard lids at Café and VEST V0102
- Lab Wing – Level 2 – Rough-in:
- Continue installing cable tray at OTS and Commons
- Lab Wing – Level 2 – Commons Spaces:
- Installing casework and windowsills
- Start installing carpet
- Lab
Wing – Level 2 – Labs:
- Finishing overhead electrical in Lab Area
- Continue applying moisture mitigation
- Lab
Wing – Level 2 – Offices and Conference Rooms:
- Continue finishing MEP in grid *
- Lab Wing – Level 3 Rough-in – South:
- Start installing mechanical hangers, seismic, and piping
- Lab Wing – Level 3 Rough-in – East:
- Finish taping and finishing gyp
- Start paint
- Lab Wing – Level 3 Rough-in – West:
- Start taping and finishing gyp
- Lab Wing – Level 3 Rough-in – Core Area Labs:
- Start installing backing and gyp
- Lab Wing – Level 3 Rough-in – Core Area Labs:
- Start polishing floors
- Roof – West Penthouse ELEV Equip Room:
- Continue installing shaft frame, gyp, and finish
- Installing disconnects and elevator equipment pushed out until 01/14
- INTERIOR BUILDOUT
- Elevator 2:
- Continue installing elevator
- Stair 1:
- Start cleaning and patching walls and landings *
- Stair 3:
- Installing stair stringers and risers