Primary construction activities for the week of 12/23 thru 12/27 will consist of the following:
| * = Activity delayed |
- ROOFING
- Penthouse Framing and Sheathing:
- Continue framing soffit
- Installing electrical in soffit start delayed to after New Year
- CANOPIESCommons Wing Soffit: Finish installing trim and metal soffit panels
- WINDOWS & SIDING
- Commons Wing – South Elevation:
- Continue installing siding
- Commons Wing – West Elevation:
- Finish installing beauty cap and flashing
- INTERIOR BUILDOUT
- Commons Wing – Level 1 – Bathrooms
& A/V Hard Lid Rooms:
- Finish install electrical in hard lids *
- MEP inspection for hard lids *
- Start gyping walls and lids *
- Lab
Wing – Level 1 – Bathrooms and Hard Lid Rooms Labs:
- Finish installing electrical in hard lids
- Lab
Wing – Level 3 – Bathrooms and Hard Lid Rooms Labs:
- Start installing electrical in hard lids
- Commons Wing – Auditorium:
- Finish installing electrical
- Start finishing balance of walls
- Commons Wing – Innovation Lab:
- Finish installing ACT grid *
- Start installing electrical in ACT ceiling *
- Commons Wing – Level 2 – Design 3D
& Art Studio:
- Finish installing ACT tiles
- Finish installing electrical
- Commons Wing – Level 2 – Sound Control
and Vestibules:
- Finish installing lids and walls
- Start painting
- Lab Wing – Level 1 – Mechanical & Back of House:
- Finish installing panels and feeders in electric rooms *
- Lab Wing – Level 1 – Commons Spaces, Café,
& Fireplace:
- Finish installing wall electrical
- Framing hard lid at Café and VEST V0102
- Start finishing MEP in hard lids at Café and VEST V0102
- Lab Wing – Level 2 – Rough-in:
- Continue installing cable tray at OTS and Commons *
- Lab
Wing – Level 2 – Labs:
- Finishing overhead electrical in Lab Area
- Lab
Wing – Level 2 – Offices and Conference Rooms:
- Continue finishing MEP in grid *
- Lab Wing – Level 3 Rough-in – South:
- Finish taping and finishing gyp
- Painting
- Lab Wing – Level 3 Rough-in – East:
- Start taping and finishing gyp
- Lab Wing – Level 3 Rough-in – West:
- Start installing backing and gyp
- Lab Wing – Level 3 Rough-in – Core Area Labs:
- Installing wall electrical rough-in
- Roof – West Penthouse ELEV Equip Room:
- Continue installing shaft frame, gyp, and finish
- Installing disconnects and elevator equipment delayed until after the New Year *
- Lab Wing – Elevator 2:
- Continue installing elevator
- Lab Wing – Stair 1:
- Start cleaning and patching walls and landings