Primary construction activities for the week of 04/13 thru 04/17 will consist of the following:
| * = Activity delayed |
- ROOFING
- Penthouse Framing:
- Finish Installing Metal Siding
- Install Tsunami Signs:
- No Activities this Upcoming Week.
- INTERIOR BUILDOUT
- Lab Wing – Level 1 – Commons Spaces, Café, & Fireplace:
- Install Electrical Conduit to Lighting in Wood Paneling
- Common Spaces All Levels – Stair Three Finish Work:
- Fab Wood Panels*
- Start Installing Wood Panels
- Commons Wing – Level 1 – Bathrooms & A/V Hard Lid Rooms:
- Finish Installing Electrical Trim Out*
- Lab Wing – Level 1 – Bathrooms and Hard Lid Rooms:
- No Activities this Upcoming Week.
- Lab Wing – Level 2 – Bathrooms and Hard Lid Rooms:
- Finish Installing Grab Rails and Toilet Partitions*
- Andersen Punch*
- Complete Punch
- Lab Wing – Level 3 – Bathrooms and Hard Lid Rooms:
- No Activities this Upcoming Week.
- Commons Wing – Auditorium:
- Finish Seating Framing
- Install Screen
- Commons Wing – Innovation Lab:
- Install Lights and MEP Finishes
- Commons Wing – Level 2 – Design 3D & Art Studio:
- Third Coat Delay
- Andersen Punch
- Correct Andersen Punch
- Commons Wing – Level 2 – Sound Control & Vestibules:
- No Activities this Upcoming Week.
- Commons Wing – Level 2 – Perforated Drywall Sound Control:
- No Activities this Upcoming Week.
- Lab Wing – Level 1 – Classrooms:
- Install Finish MEP
- Lab Wing – Level 2 – Common Spaces:
- No Activities this Upcoming Week.
- Lab Wing – Level 2 – Lab Area:
- Finish HVAC Connections in Ceiling
- Lab Wing – Level 2 – Offices and Conference Rooms:
- No Activities this Upcoming Week.
- Lab Wing – Level 3 Rough-in – Orange South:
- No Activities this Upcoming Week.
- Lab Wing – Level 3 Rough-in – Blue Northeast:
- Paint MEPFP in OTS*
- Pipe ID*
- Lab Wing – Level 3 Rough-in – Green Northwest:
- Hydronic Pipe Insulation Delay COVID 19*
- Lab Wing – Level 3 Rough-in – Purple Core Area Labs:
- Finish Pipe ID*
- Common Spaces – Level 3
- Install Carpet
- Install Base
- Lab Wing – Level 3
- Continue Installing Rubber Flooring
- Offices and Conference Rooms – Level 3
- Finish Electrical
- Roof Level – East Penthouse, Lobby and Staging
- No Activities this Upcoming Week.
- INTERIOR BUILDOUT
- Elevator 1:
- Continue Workman’s Service Use
- Elevator 2:
- Continue Installing Elevator*
- Stair 1:
- No activities this week.
- Stair 2:
- No Activities this Upcoming Week.
- Stair 4:
- No Activities this Upcoming Week.
- SITE IMPROVEMENTS
- Phase 3 West Site Improvements:
- No Activities this Upcoming Week.