Primary construction activities for the week of 04/13 thru 04/17 will consist of the following:  

|   * = Activity delayed    |

  • ROOFING
  • Penthouse Framing:
    • Finish Installing Metal Siding
  • Install Tsunami Signs:
    • No Activities this Upcoming Week.
  • INTERIOR BUILDOUT
  • Lab Wing – Level 1 – Commons Spaces, Café, & Fireplace:
    • Install Electrical Conduit to Lighting in Wood Paneling
  • Common Spaces All Levels – Stair Three Finish Work:
    • Fab Wood Panels*
    • Start Installing Wood Panels
  • Commons Wing – Level 1 – Bathrooms & A/V Hard Lid Rooms:
    • Finish Installing Electrical Trim Out*
  • Lab Wing – Level 1 – Bathrooms and Hard Lid Rooms:
    • No Activities this Upcoming Week.
  • Lab Wing – Level 2 – Bathrooms and Hard Lid Rooms:
    • Finish Installing Grab Rails and Toilet Partitions*
    • Andersen Punch*
    • Complete Punch
  • Lab Wing – Level 3 – Bathrooms and Hard Lid Rooms:
    • No Activities this Upcoming Week.
  • Commons Wing – Auditorium:
    • Finish Seating Framing
    • Install Screen
  • Commons Wing – Innovation Lab:
    • Install Lights and MEP Finishes
  • Commons Wing – Level 2 – Design 3D & Art Studio:
    • Third Coat Delay
    • Andersen Punch
    • Correct Andersen Punch
  • Commons Wing – Level 2 – Sound Control & Vestibules:
    • No Activities this Upcoming Week.
  • Commons Wing – Level 2 – Perforated Drywall Sound Control:
    • No Activities this Upcoming Week.
  • Lab Wing – Level 1 – Classrooms:
    • Install Finish MEP
  • Lab Wing – Level 2 – Common Spaces:
    • No Activities this Upcoming Week.
  • Lab Wing – Level 2 – Lab Area:
    • Finish HVAC Connections in Ceiling
  • Lab Wing – Level 2 – Offices and Conference Rooms:
    • No Activities this Upcoming Week.
  • Lab Wing – Level 3 Rough-in – Orange South:
    • No Activities this Upcoming Week.
  • Lab Wing – Level 3 Rough-in – Blue Northeast:
    • Paint MEPFP in OTS*
    • Pipe ID*
  • Lab Wing – Level 3 Rough-in – Green Northwest:
    • Hydronic Pipe Insulation Delay COVID 19*
  • Lab Wing – Level 3 Rough-in – Purple Core Area Labs:
    • Finish Pipe ID*
  • Common Spaces – Level 3
    • Install Carpet
    • Install Base
  • Lab Wing – Level 3
    • Continue Installing Rubber Flooring
  • Offices and Conference Rooms – Level 3
    • Finish Electrical
  • Roof Level – East Penthouse, Lobby and Staging
    • No Activities this Upcoming Week.
  • INTERIOR BUILDOUT
  • Elevator 1:
    • Continue Workman’s Service Use
  • Elevator 2:
    • Continue Installing Elevator*
  • Stair 1:
    • No activities this week.
  • Stair 2:
    • No Activities this Upcoming Week.
  • Stair 4:
    • No Activities this Upcoming Week.
  • SITE IMPROVEMENTS
  • Phase 3 West Site Improvements:
    • No Activities this Upcoming Week.