Primary construction activities for the week of 12/23 thru 12/27 will consist of the following:  

|   * = Activity delayed    |

  • ROOFING
  • Penthouse Framing and Sheathing:
    • Continue framing soffit
    • Installing electrical in soffit start delayed to after New Year
  • CANOPIESCommons Wing Soffit: Finish installing trim and metal soffit panels
  • WINDOWS & SIDING
  • Commons Wing – South Elevation:
    • Continue installing siding
  • Commons Wing – West Elevation:
    • Finish installing beauty cap and flashing
  • INTERIOR BUILDOUT
  • Commons Wing – Level 1 – Bathrooms & A/V Hard Lid Rooms:
    • Finish install electrical in hard lids *
    • MEP inspection for hard lids *
    • Start gyping walls and lids *
  • Lab Wing –  Level 1 – Bathrooms and Hard Lid Rooms Labs:
    • Finish installing electrical in hard lids
  • Lab Wing –  Level 3 – Bathrooms and Hard Lid Rooms Labs:
    • Start installing electrical in hard lids
  • Commons Wing – Auditorium:
    • Finish installing electrical
    • Start finishing balance of walls
  • Commons Wing – Innovation Lab:
    • Finish installing ACT grid *
    • Start installing electrical in ACT ceiling *
  • Commons Wing – Level 2 – Design 3D & Art Studio:
    • Finish installing ACT tiles
    • Finish installing electrical
  • Commons Wing – Level 2 – Sound Control and Vestibules:
    • Finish installing lids and walls
    • Start painting
  • Lab Wing – Level 1 – Mechanical & Back of House:
  • Finish installing panels and feeders in electric rooms *
  • Lab Wing – Level 1 – Commons Spaces, Café, & Fireplace:
    • Finish installing wall electrical
    • Framing hard lid at Café and VEST V0102
    • Start finishing MEP in hard lids at Café and VEST V0102
  • Lab Wing – Level 2 – Rough-in:
    • Continue installing cable tray at OTS and Commons *
  • Lab Wing – Level 2 – Labs:
    • Finishing overhead electrical in Lab Area
  • Lab Wing –  Level 2 – Offices and Conference Rooms:
    • Continue finishing MEP in grid *
  • Lab Wing –  Level 3 Rough-in – South:
    • Finish taping and finishing gyp
    • Painting
  • Lab Wing –  Level 3 Rough-in – East:
    • Start taping and finishing gyp
  • Lab Wing –  Level 3 Rough-in – West:
    • Start installing backing and gyp
  • Lab Wing –  Level 3 Rough-in – Core Area Labs:
    • Installing wall electrical rough-in
  • Roof – West Penthouse ELEV Equip Room:
  • Continue installing shaft frame, gyp, and finish
  • Installing disconnects and elevator equipment delayed until after the New Year *
  • Lab Wing –  Elevator 2:
    • Continue installing elevator
  • Lab Wing – Stair 1:
    • Start cleaning and patching walls and landings